Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
2. PURPOSE .................................................................................................. 3
3. SCOPE ....................................................................................................... 3
7. FABRICATION ........................................................................................... 5
PWTP2-QA-CR-CON-ARU-0392-B
Quality Control System
For the Plant Fabrication of Structural Steel
Baras Plant
Sitio Rizza Brgy. Pinugay, Baras, Rizal 1
8.2.1. RECORD OF TESTING .................................................................... 9
8.2.2. VISUAL INSPECTION OF WELDS ...................................................... 9
8.2.3. SURFACE FLAW DETECTION ......................................................... 10
8.2.4. ULTRASONIC EXAMINATION ......................................................... 10
8.2.5. ACCEPTANCE CRITERIA AND CORRECTIVE ACTION ......................... 10
9. ACCURACY OF FABRICATION .................................................................. 14
PWTP2-QA-CR-CON-ARU-0392-B
Quality Control System
For the Plant Fabrication of Structural Steel
Baras Plant
Sitio Rizza Brgy. Pinugay, Baras, Rizal 2
1. GENERAL
This document consist of processes and operations to provide assurance that finished
steelworks shall conform to the Project Specification in accordance with the
requirements of this guideline.
2. PURPOSE
The purpose of this document is to ensure that fabrications are carried out according
to specifications and in a safe manner.
3. SCOPE
This document covers the processes and quality control in the fabrication of steel
structures requirements for the following buildings:
a) BAF
b) DAF
c) Sludge
d) Genset
e) Chemical Building 1
f) Chemical Building 2
4. REFERENCE DOCUMENTS
The quality control guidelines as presented in the subsequent part of this document
shall be in place in identifying all materials and workmanship from procurement to
delivery and subsequent incorporation into the works. It is essential that monitoring
shall be carried out to ensure performance of materials and workmanship incorporated
into the final works is not inferior to those specified in the design.
PWTP2-QA-CR-CON-ARU-0392-B
Quality Control System
For the Plant Fabrication of Structural Steel
Baras Plant
Sitio Rizza Brgy. Pinugay, Baras, Rizal 3
5.1. CONTROL OF DOCUMENTS
The following documents shall be establish and maintain procedures for approval,
issue, and data required for the operation of the quality control. Required
documentation shall include, but may not be limited to, the following:
All records required by the contract documents shall be available for review by the
Client or his representative.
6. PROCESS MANAGEMENT
Incoming materials shall be matched against delivery receipt and purchase orders. The
materials shall also be checked if it is comply with the following criterion:
a. Size: conformance to dimensional tolerances
b. Surface condition: the material has no defects
c. Material grade : conformance to A36 steel
Material shall not be used or processed until it has been complied with the above
criterion and approved for use
All materials delivered shall be check and verify its material specification prior to
incorporate into the work.
All steel to be used in the Works shall have a mill test certificate. Where individual
pieces, lots, and batches are restocked, the identification system shall be maintained.
The material grades of all steel shall bear an identifiable markings of “S36S”, in
corresponding to its material specification.
PWTP2-QA-CR-CON-ARU-0392-B
Quality Control System
For the Plant Fabrication of Structural Steel
Baras Plant
Sitio Rizza Brgy. Pinugay, Baras, Rizal 4
Where areas of steelwork are indicated on the drawings as being unmarked, they shall
be left free of all markings and hard stamping.
6.4. HANDLING
Steelwork shall be bundled, packed, handled and transported in a safe manner so that
permanent distortion does not occur and surface damage is minimized.
The AJF shall define inspection points and inspection record requirements to verify
conformance to the contract documents, including the following:
AJF shall provide access to and cooperation with the Clients' designated representative
for inspection of the work as required. Unless specific provisions are included in the
contract documents, such inspections shall be scheduled so as not to impede the
progress of production.
The AJF shall ensure that all verification has been performed in conformance with
contract requirements and this document.
AJF shall maintain procedures to ensure that all items are properly prepared, handled,
and/or packaged for storage and shipping to prevent damage to product.
7. FABRICATION
The fabrication of structural steel shall be carried out in a fabrication plant, this allows
the fabricated steelworks and its components in precise and of assured quality.
Generally, the structural steel passes through a series of operation during the course
of its fabrication. The sequence of activities in fabricating the structural steels are
shown in the flowchart below.
PWTP2-QA-CR-CON-ARU-0392-B
Quality Control System
For the Plant Fabrication of Structural Steel
Baras Plant
Sitio Rizza Brgy. Pinugay, Baras, Rizal 5
FABRICATION PROCEDURE FLOW CHART
Start
Person in charge:
Plant’s QC Inspector
Return to
Warehouseman Material Inspection NCR
Supplier
Rejected
Accepted
Person in charge:
Plant’s QC Inspector
Foreman
Surface Cleaning NCR
Skilled Worker
Accepted
Rejected
Rejected
Punching and Drilling NCR
Rejected
Accepted
Test and
Fitting and Reaming NCR
Full Trace
Accepted
Person in charge:
Plant’s QC Inspector
Foreman Rejected
Welder Welding NCR
Skilled Worker
Accepted
Rejected
Mock up Assembly NCR
Accepted
Person in charge:
Plant’s QC Inspector
Foreman Rejected
Painter Protective Treatment NCR
Skilled Worker
Accepted
End
The sequence and importance of operation will vary depending on the type of
fabrication required. All these operation are explained briefly in the subsequent parts
of the Section.
PWTP2-QA-CR-CON-ARU-0392-B
Quality Control System
For the Plant Fabrication of Structural Steel
Baras Plant
Sitio Rizza Brgy. Pinugay, Baras, Rizal 6
7.1. SURFACE CLEANING
Structural sections from the rolling mills may require surface cleaning to remove mill
scale prior to fabrication and painting. Surface cleaning shall be carried out using blast
cleaning or sand blasting. The method employs the abrasive action of particles that
are projected on to the surface of the steel at high speed by centrifugal impeller to
remove rust, and roughen the surface before applying the coating.
By using shot or slag grits, both of which have an angular profile, surface oxides are
removed and a rougher surface is obtained to provide an adequate key for metal
spraying or special paint.
Cutting and shaping of steel shall be carried by flame cutting or burning. In this
method, the steel is heated locally by a pressurised mixture of oxygen and a
combustible gas such as propane, which passes through a ring of small holes in a
cutting nozzle. The heat is focussed on to a very narrow band and the steel melts at
15000°C when a jet of high-pressure oxygen is released through a separate hole in the
centre of the nozzle to blast away the molten metal in globules. The desired cuts are
obtained quickly by this process. However due to a rapid thermal cycle of heating and
cooling, residual stresses and distortion are induced and hence structural sections that
are fabricated using flame cutting are treated specially in the design of structural
steelwork.
Flame-cut edges which are free from significant irregularities shall be accepted without
further treatment except for the removal of dross, otherwise cut edges shall be dressed
to remove irregularities.
Although most of fabrication shops have a wide range of machines, which can form
holes for connection in structural steel works. The punching and drilling of holes will
be done using traditional drilling machine is the radial drill, a manually operated
machine, which drills individual holes in structural steelwork.
In this method, a pin or center punch and hammer to create a small dimple on to the
steel surface where the hole is mark. This gives the tip of your drill bit a place to ride
in as you begin to drill and to avoid the tendency to wander when you first start drilling.
Start drilling hole using the manual drilling machine with a smaller bit and drilling
successively larger holes with your drill bit until you reach the desired diameter of
hole.
For drilling holes larger than 6 mm, a cutting fluid is usually used in lubricating bit to
reduce friction and heat buildup, which makes drilling easier and your bits last longer.
Before final assembly, the component parts of a member are fitted-up temporarily with
bolts or small amount of welds. The fitting-up operation includes attachment of
PWTP2-QA-CR-CON-ARU-0392-B
Quality Control System
For the Plant Fabrication of Structural Steel
Baras Plant
Sitio Rizza Brgy. Pinugay, Baras, Rizal 7
previously omitted splice plates and other fittings and the correction of minor defects
found by the inspector.
In bolted work, especially when done manually, some holes in the connecting material
may not always be in perfect alignment and small amount of reaming may be required
to permit insertion of fasteners. In this operation, the holes are punched, 4 to 6 mm
smaller than final size, then after the pieces are assembled, the holes are reamed by
electric or pneumatic reamers to the correct diameter, to produce well matched holes.
7.5. WELDING
The strength of the entire structure depends upon the proper use of fastening
methods. The assemble components is fastened by welding of connection. Welding is
the most common method of shop fabrication of steel structures. In addition to being
simple to fabricate, welded connection considerably reduce the size of the joint and
the additional fixtures and plates
Welding shall be a metal arc process using in accordance with AWS D1.1 as
appropriate, together with other clauses contained in this section, unless otherwise
specifically permitted by the Client.
Welding consumables used shall be chosen to ensure that the mechanical properties
of the weld metal are not less than those required for the parent metal.
The assembly shall be accepted with the Client or his representative before it is
prepared for paint application.
The primer is applied directly on to the cleaned steel surface. Its purpose is to wet
the surface and to provide good adhesion for subsequently applied coats. Primers for
steel surfaces are also usually required to provide corrosion inhibition.
The intermediate coats are applied to build the total film thickness of the system. This
may involve application of several coats. The finishing coats provide the first-line
defence against the environment and also determine the final appearance in terms of
gloss, color, etc.
PWTP2-QA-CR-CON-ARU-0392-B
Quality Control System
For the Plant Fabrication of Structural Steel
Baras Plant
Sitio Rizza Brgy. Pinugay, Baras, Rizal 8
The procedure for the application of coating is listed below:
The paint coating and its application procedure as listed above shall be depends upon
the approved paint material.
8. WELDED CONNECTION
The test results shall be recorded and be available for inspection by the
Client.
PWTP2-QA-CR-CON-ARU-0392-B
Quality Control System
For the Plant Fabrication of Structural Steel
Baras Plant
Sitio Rizza Brgy. Pinugay, Baras, Rizal 9
inspection is performed (see Tables 1.0 and 2.0). Any welds which will be
rendered inaccessible by subsequent work shall be examined in accordance
with Tables 1.0 and 2.0 prior to the loss of access.
Operators carrying out final ultrasonic examination of the weld shall hold
a current certificate of competence from a nationally recognised authority.
PWTP2-QA-CR-CON-ARU-0392-B
Quality Control System
For the Plant Fabrication of Structural Steel
Baras Plant
Sitio Rizza Brgy. Pinugay, Baras, Rizal 10
Examples
Design Grade
Design Grade
PWTP2-QA-CR-CON-ARU-0392-B
Quality Control System
For the Plant Fabrication of Structural Steel
Baras Plant
Sitio Rizza Brgy. Pinugay, Baras, Rizal 11
DEFINITION OF ZONES AND WELD ORIENTATIONS
ACCEPTANCE REMEDIAL
REQUIREMENTS ACTION FOR
WELD PARTICULAR (all dimensions in mm) NON-
PARAMETER
TYPE CONDITIONS CONFORMING
(see Note 1 and 5 ) Fig WELDS
(see Note 2)
WELD GEOMETRY
Location All As specified on drawings Repair
Weld Type All As specified on drawings Refer to Engineer
≥ As specified on
Length All Repair
drawings
PROFILE
tb ≥ As drawing
Butt b,c Repair
(Av.50)
Throat
Repair or grind
Thickness
Fillet 1f ≥ As drawing a and MPI after
grinding
Leg Length Fillet 1f ≥ As drawing a Repair
Grind and MPI
Toe Angle All θ ≥ 90° a
after grinding
Cap/Root Bead
(Height or Butt Butt Joint -1 ≤ Cb ≤ 4 b Repair or grind
concavity)
m ≤ As drawing +
Butt Butt Joint 0.25t ≤ As drawing d Refer to engineer
+3
Misalignment
m ≤ As drawing +
All Cruciform Joint 0.50t and ≤ As e
drawing + 6
SURFACE DISCONTINUITIES
PWTP2-QA-CR-CON-ARU-0392-B
Quality Control System
For the Plant Fabrication of Structural Steel
Baras Plant
Sitio Rizza Brgy. Pinugay, Baras, Rizal 12
U1+ U2 ≤ 0.1t D,e
Longitudinal Weld Repair
(Av.100) And ≤ 2 D,e
Undercut All
U1+ U2 ≤ 0.05t D,e
Transverse Weld
(Av.100) And ≤ 1 D,e
rp ≤ As Repair and double
Single drawing+0.1t(Av.1c00) scope of
Longitudinal Weld c
Root Sided and ≤ As drawing Ultrasonic
Penetration +3 inspection
(lack of)
rp ≤ As
if root is
drawing+0.05t(Av.100)
(lack of) Transverse Weld c inaccessible
and ≤ As drawing
Butt
+2
All Welds d ≤ 3 F
Longitudinal Weld ∑d ≤ 20 in 100 (length) F
Porosity All Repair
∑ d ≤ 10 in 100
Transverse Weld f
(length)
Repair and
Lack of Fusion
All Not Permitted increase MPI
and Cracks
to 100% (Note 4)
H ≤ 3 + As drawing 1 e,g
All Welds ≤ 10 ) if h` < 6 1` g
Slag Lines and
≥ 10 ) g Repair and double
Lack of
All Σ1 ≤ 6t in 200 scope of U/S
Fusion/Root Longitudinal Weld g
(length) Inspection
Penetration
Σ1 ≤ 3t in 200
Transverse Weld g
(length)
Fillet or
Tee, Cruciform, Repair and double
Partial rg ≤ 2(Av 100 ) and a,e
Root Gap Corner and Lap scope of U/S
Pen ≤ 3 a,e
Joints Inspection
Butt
Repair and
increase U/S
Cracks All Not permitted
Inspection to
100%
Refer to Engineer
Tee, Cruciform,
and increase U/S
Lamellar Tears All Corner and Lap Not Permitted (Note 3)
Inspection to
Joints
100%
DIMENSIONAL SYMBOLS DEFINITION OF MEASUREMENTS
PWTP2-QA-CR-CON-ARU-0392-B
Quality Control System
For the Plant Fabrication of Structural Steel
Baras Plant
Sitio Rizza Brgy. Pinugay, Baras, Rizal 13
Notes:
1. Where there are two limits for one dimension both shall apply All limits are peak values unless
indicated as average
2. Where a repair is necessary an approved procedure must be used. If on increasing the scope
of inspection, further non-conformances are found, the scope shall be increased to 100% for the
joint type in question.
3. May be accepted up to the limits for slag lines if the joint is subjected to longitudinal shear only.
4. All welds to the same procedure.
5. Abbreviations: Av. 100 or Av.50 indicates the average value over 100mm or 50mm length
6. Where there are two limits for one dimension both shall apply All limits are peak values unless
indicated as average
7. Where a repair is necessary an approved procedure must be used. If on increasing the scope
of inspection, further non-conformances are found, the scope shall be increased to 100% for the
joint type in question.
8. May be accepted up to the limits for slag lines if the joint is subjected to longitudinal shear only.
9. All welds to the same procedure.
10. Abbreviations: Av. 100 or Av.50 indicates the average value over 100mm or 50mm length
11. Where there are two limits for one dimension both shall apply All limits are peak values unless
indicated as average
12. Where a repair is necessary an approved procedure must be used. If on increasing the scope
of inspection, further non-conformances are found, the scope shall be increased to 100% for the
joint type in question.
13. May be accepted up to the limits for slag lines if the joint is subjected to longitudinal shear only.
14. All welds to the same procedure.
15. Abbreviations: Av. 100 or Av.50 indicates the average value over 100mm or 50mm length
16. Where there are two limits for one dimension both shall apply All limits are peak values unless
indicated as average
17. Where a repair is necessary an approved procedure must be used. If on increasing the scope
of inspection, further non-conformances are found, the scope shall be increased to 100% for the
joint type in question.
18. May be accepted up to the limits for slag lines if the joint is subjected to longitudinal shear only.
19. All welds to the same procedure.
20. Abbreviations: Av. 100 or Av.50 indicates the average value over 100mm or 50mm length
9. ACCURACY OF FABRICATION
This section deals with the accuracy of fabrication of structural steel sections.
PWTP2-QA-CR-CON-ARU-0392-B
Quality Control System
For the Plant Fabrication of Structural Steel
Baras Plant
Sitio Rizza Brgy. Pinugay, Baras, Rizal 14
9.1. PERMITTED DEVIATIONS
Plan or Elevation
4 Straightness on Both Axes
5 Length
6 Curved or Cambered
PWTP2-QA-CR-CON-ARU-0392-B
Quality Control System
For the Plant Fabrication of Structural Steel
Baras Plant
Sitio Rizza Brgy. Pinugay, Baras, Rizal 15
9.1.2. PERMITTED DEVIATIONS FOR ELEMENTS OF FABRICATED MEMBERS
2 Position of Holes
3 Punched Holes
5 5 Flatness
PWTP2-QA-CR-CON-ARU-0392-B
Quality Control System
For the Plant Fabrication of Structural Steel
Baras Plant
Sitio Rizza Brgy. Pinugay, Baras, Rizal 16
9.1.3. PERMITTED DEVIATIONS IN PLATE GIRDER SECTIONS
2 Flange Width
Width of Bw or Bn
Δ
Δ=B/100 or 3mm
whichever is greater
4 Web Eccentricity
PWTP2-QA-CR-CON-ARU-0392-B
Quality Control System
For the Plant Fabrication of Structural Steel
Baras Plant
Sitio Rizza Brgy. Pinugay, Baras, Rizal 17
5 Flanges B Flange width
Out of flatness
7 Length
8 Flange Straightness
PWTP2-QA-CR-CON-ARU-0392-B
Quality Control System
For the Plant Fabrication of Structural Steel
Baras Plant
Sitio Rizza Brgy. Pinugay, Baras, Rizal 18
Δ = d/150 or 3mm whichever is the
greater
11 Cross Section at Bearings
12 Web Stiffeners
All variations after the work has started shall be accompanied by a Non-Conformance
Report (NCR), traceable throughout the entire process and signed off by the inspector.
11. DOCUMENTATION
The inspector shall secure the following documents during the fabrication such as
contract drawings, inspection report, fabrication checklist, mill certificates, detail and
erection drawings, welding records, test report, and photos as required.
PWTP2-QA-CR-CON-ARU-0392-B
Quality Control System
For the Plant Fabrication of Structural Steel
Baras Plant
Sitio Rizza Brgy. Pinugay, Baras, Rizal 19
12. ANNEX A
PWTP2-QA-CR-CON-ARU-0392-B
Quality Control System
For the Plant Fabrication of Structural Steel
Baras Plant
Sitio Rizza Brgy. Pinugay, Baras, Rizal 20
12.2. ANNEX B WELDING INSPECTOR ACCREDITATION
PWTP2-QA-CR-CON-ARU-0392-B
Quality Control System
For the Plant Fabrication of Structural Steel
Baras Plant
Sitio Rizza Brgy. Pinugay, Baras, Rizal 21
12.3. WORK INSPECTION REQUEST (WIR)
PWTP2-QA-CR-CON-ARU-0392-B
Quality Control System
For the Plant Fabrication of Structural Steel
Baras Plant
Sitio Rizza Brgy. Pinugay, Baras, Rizal 22
12.4. STRUCTURAL STEEL FABRICATION CHECKLIS
PWTP2-QA-CR-CON-ARU-0392-B
Quality Control System
For the Plant Fabrication of Structural Steel
Baras Plant
Sitio Rizza Brgy. Pinugay, Baras, Rizal 23
12.5. NON CONFORMANCE REPORT
NOTE:
Photos of non-complying components and its rectified or rejected components shall be
included on this document for proper documentation of this report.
PWTP2-QA-CR-CON-ARU-0392-B
Quality Control System
For the Plant Fabrication of Structural Steel
Baras Plant
Sitio Rizza Brgy. Pinugay, Baras, Rizal 24