Heijunka
Heijunka
Production Leveling
Planning CUSTOMER
SUPPLIER FG STORES
I have Only 5
Nos,
Received Only
13 Nos.????
RAW MATERIAL
Step 1 PACKING
Step 2
PACKING CUSTOMER
FG STORES
BIN
WIP Reservoir
Received 50 Nos. Immediately..
Step 2
Order is directly delivered from FG Reservoir, that signals for required Kanban
quantities to Packing Dept, that pulls material from WIP Reservoir; that in turns
pulls material from Step 1; that pulls from Raw Material
Tools of Heijunka
• Planning
• Visual Systems
• Line Balancing
• Each Heijunka Board should clearly communicate day wise plan for
each manufacturing step..!!
The Manufacturing plan & its status is 100% visible to all. No need to phone
calls, mails & oral communications.
Machine Numbers
H1 Board - H2 Board -
Dispatch Testing
H3 Board - H2 Board -
Assembly Stores
The table above shows the usable hours in each day (columns) for the whole
month of 20 days. Each hour (table cell) a product can be manufactured, the
table allows making production planning visual.
In such a case, the client ordering a unit of each type, 6 in total, and ordering the
first day of the month, has to wait the month's end (20 working days) before being
delivered.
All that waiting for an accumulated production time of 6 hours. The ratio
usable time / total time is: 6 / 20 x 7 = 4%
In the table above, the monthly requirements are in column B. The weekly
average requirement is in (C). As we can only manufacture complete and
discrete units, there is a need for rounding in (D). Rounding give a excess time,
for which we need to choose how to use, e.g. what product should be
produced "in excess" (E). The column E becomes the weekly production plan.
In column F the new monthly result if we apply our pattern 4 time, and for which
we check the consistency with requirement (B), in column G. Adjustment
between excess and shortage is done in the fourth week.
• The table above shows the usable hours in each day (columns) for the whole
month of 20 days. Each hour (table cell) a product can be manufactured, the
table allows making production planning visual.
Performance
Our client whishing a unit of each product can be delivered the second day.
Performance measured by the ratio usable time / total time; 6 / 2 x 7 = 43%