Sei sulla pagina 1di 13

Introduction: The Recent Focus on Asset Management

The ISO 55000 series of standards, launched in January 2014, establishes a global standard for asset management systems. The series has three
parts:

• ISO 55000 – Overview with standard terms and definitions


• ISO 55001 – Requirements specifications
• ISO 55002 – Implementation guidelines

These standards provide the elements of a holistic asset management program and should be referenced when creating a corporate or site asset
management policy and program. LCE’s asset management system implementation framework model, based on the ISO 55000 management
system for asset management, establishes the key concepts and flow that are necessary for many important asset management-related deliverables.
The implementation methodology comprises more than 80 key processes and eight critical knowledge domains that are associated with each
individual life cycle phase. At the heart of the implementation framework is an asset life cycle management system delivering value, as illustrated in
Figure 1.

Figure 1 – LCE’s Asset Management System Implementation Framework

© Life Cycle Engineering, Inc. | www.LCE.com 2


Asset Life Cycle Management
The ISO 55000 Asset Management Standard clearly establishes the expectation that assets will be managed throughout their life cycle. LCE’s asset
management system framework integrates the asset management capabilities processes, procedures and knowledge into the asset life cycle stages.
Risk-based asset management (RBAM) principles and practices are deeply integrated into the asset life cycle’s four stages.

Business Case stage produces the Create or Acquire stage of the lifecycle is
business case, the single most important where the decisions made have the greatest
document in helping an organization’s impact on the total cost of ownership of an
leadership evaluate the return on physical acquired or created asset. This is also where
asset investments. It defines the problem the greatest collaboration of a cross-
statement and resulting business functional team is needed to ensure that
opportunity, if solved. The business case is intended benefits will be realized. Detailed
more than just financial justification. The key engineering through commissioning occurs
processes associated with the business case in this phase. Important deliverables pass
phase include strategic planning, capital from stage to stage as the process moves the
planning and evaluation, life cycle cost acquired or created asset from an idea onto
analysis, and auditing. the shop floor.

Dispose or Replace stage occurs when Operate & Maintain stage is where value
the disposal, decommissioning, or is created. The newly commissioned assets
replacement of an asset is necessary function to provide the solution defined in
following the end of an asset’s service life the business case. This is also the longest
or change in asset requirements due to phase by duration of the asset lifecycle.
rationalization. If unplanned, this phase can Once this phase of the life cycle is reached,
have a significant negative impact on an only about 15% of the total operational cost
organization’s financial statement. can be influenced. Since this phase of the
life cycle is focused on the assets meeting
their function, the tools used are focused on
continuous improvement.

© Life Cycle Engineering, Inc. | www.LCE.com 3


Life Cycle Costing and Investment Decisions
Life cycle costing is usually a combined effort between reliability engineering and accounting.

• Reliability engineering
o Identifies costs associated with the acquisition, installation, operations, maintenance, and disposal of assets
o Performs reliability and maintainability analysis to estimate “sustaining costs”
o Defines the design parameters required to achieve optimum life cycle costs
• Accounting
o Defines calculations for depreciation, taxes, and discount factors used to determine net present value
o Quantifies requirements for capital investment vs. cost
o Audit computations against good accounting practices

A list of common life cycle investment options (○) broken down by lifecycle stage (●) provides the granularity needed to estimate cost. Investment
options are compared in terms of net present value (NPV). NPV compares the amount invested today to the present value of the future cash
receipts from the investment. In other words, the amount invested is compared to the future cash amounts after they are discounted by a rate of
return.

• Concept • Create/acquire
o Research and o Manufacturing and
development construction
o Engineering design o Facilities
o Modeling and testing o Testing
o Installation
o Commissioning and startup
o Initial logistic support

• Decommission • Operate
and dispose and maintain
o Disposal o Operate
o Maintain
o Equipment modifications

© Life Cycle Engineering, Inc. | www.LCE.com 4


Risk-based Asset Management Strategy
Whether an organization seeks a holistic implementation of an asset management system and ISO 55000 certification, or a more tactical application
to achieve performance gains, a risk-based approach delivers the greatest value from assets at the lowest cost.

An effective asset management system provides transparency to risk so that the appropriate decisions can be made throughout an asset’s life cycle.
For guidance on risk management, the ISO 55000 series defers to ISO 31000. Figure 2 illustrates the guidelines and principles for a risk
management process in accordance with ISO 31000.

A risk-based asset management strategy couples risk


management, standard work, and condition-based
maintenance to properly apply resources based on
process criticality. This ensures that proper controls are
put in place and reliability analysis is used to ensure
continuous improvement. An effective risk-based
management system includes an enterprise asset
management or resource solution that properly catalogs
asset attribute data, a functional hierarchy, criticality
analysis, risk and failure analysis, control plans,
reliability analysis and continuous improvement.

Figure 2 - Process for Assessing and Managing Risk (ISO 31000:2009)

© Life Cycle Engineering, Inc. | www.LCE.com 5


The Four Phases in LCE’s Risk-based Asset Management (RBAM®)
Implementation Model
Phase 1: Classify

Process Flow Diagram – Functional block diagrams are used in


the classify phase when establishing functional hierarchy. Value
stream maps are developed to identify waste and gain clear
understanding of how asset reliability impacts the value stream.

Figure 2 - RBAM Implementation Model

Database Development – This is probably one of the


most overlooked components of a successful risk-based
asset management system. For your system to meet
corporate objectives, data for each asset must be clearly
captured based on its type and required attribute data.
Figure 3 is an example of developing the “asset type
attribute” fields.

Figure 3 – Classified by Asset Type

© Life Cycle Engineering, Inc. | www.LCE.com 6


Phase 1: Classify
Collection – Data can be collected manually, with the aid of electronic media, and even digital imagery.
Figure 4 shows a digital picture of an electric motor specification tag.

RBAM Implementation Model

Figure 4 – Digital Image of Motor Specification Tag

Cataloging – It’s critically important to create a functional hierarchy. The hierarchy will provide the level to which work orders are assigned, bills of
material are written, and failure analysis is conducted. It also allows for rollups to cost centers, providing total cost of ownership and budgetary
analysis.

Figure 5 – Functional Hierarchy Example – ISO 14224


© Life Cycle Engineering, Inc. | www.LCE.com 7
Phase 2: Analyze
Criticality Analysis – The next step is to create an analysis of your equipment and the significance of failure to
work flows, business processes, value stream, etc. As the example below illustrates, this analysis includes such
considerations as environmental impact, safety, production, quality or reputation issues associated with the
organization.

RBAM Implementation Model

Figure 6 – Criticality Analysis Example

Risk analysis – Identifying risk is the first step in risk management. Your analysis needs to include potential sources of risk, the severity if uncontrolled, and the
likelihood of occurrence. An example of a simple risk table is presented below. Those items in the “A” category have the greatest risk and therefore receive the
most attention.

Figure 7 - Risk Analysis Table

© Life Cycle Engineering, Inc. | www.LCE.com 8


Phase 2: Analyze
Failure analysis – The next step is to conduct some formal failure analysis to determine the predominant
failure modes that will be addressed based on risk ranking. The complexity of the analysis will depend on
the criticality analysis. An example would be a Reliability Centered Maintenance approach to those most
critical assets. This method usually requires a cross-functional team and is fairly time consuming.

Failure mode and effect analysis (FMEA) is performed on the most critical assets.
RBAM Implementation Model

Figure 8 – FMEA Example – Ref. IEC 60812

Risk Ranking – The risk ranking is a product of the risk priority number from the failure analysis and the criticality analysis. This ranking enables you
to deploy corporate resources to the assets and predominant failure modes that have the greatest risk of impacting corporate objectives (stakeholder
requirements) and the process value stream.

© Life Cycle Engineering, Inc. | www.LCE.com 9


Phase 3: Control
Control plans consist of tasks that will be accomplished to mitigate or eliminate the risk of failure by
targeting how equipment is maintained and operated. Standard work must be established to minimize
variations in execution. Each FMEA can produce the following control strategies:

RBAM Implementation Model

Control Strategy Examples


Predictive Maintenance (PdM) activities are based on a specific • Thickness testing used to monitor pressure vessel corrosion
operating condition of an asset to detect the onset of a failure prior to • Infrared thermography used to detect an abnormally hot fan drive pulley due to
becoming a functional failure. drive belt misalignment
• Vibration analysis used to monitor the condition of a critical centrifuge bearing

Preventive Maintenance (PM) activities are scheduled to be completed • Changing HVAC air handler drive belts every year regardless of wear
based on a specific time or cycle regardless of the asset condition. • Changing oil in a gearbox every 6-months regardless of oil condition
• Injecting 2 ounces of a specific grease into a conveyor bearing

Operator Care (OC) tasks are executed by operators during normal • Operator daily inspection of oil level in a critical compressor
production. • Operator weekly cleaning of inlet screens to cooling tower pumps
• Operator quarterly test of tank high level alarm

Design modification or reliability upgrade projects intended to minimize • Installing a seal-less pump to reduce risk of a shaft seal leak
unacceptable risks. • Installing redundant equipment to reduce risk to the value stream
• Upgrading blower impeller material from ductile iron to stainless steel to
reduce the risk of corrosion-related failure

Another control strategy, stocking critical spares, is intended to lower the risk to the value stream in the event of an equipment failure requiring the
spare. It is imperative to keep them in stock or readily available at all times. While the intent is clearly not to use them on a regular basis (if at all), the
negative consequences of not having one when needed far outweighs the purchase cost of the spare and inventory costs associated with
maintaining them in the storeroom or close at hand. Critical spares are often expensive, sometimes one-of-a kind items, with anticipated low usage
and frequently long lead times. However, if a high-risk failure mode lacks a mitigating action, then stocking a critical spare may be the default
strategy.

© Life Cycle Engineering, Inc. | www.LCE.com 10


Phase 4: Measure
Measures must be established that define the key performance indicators supporting the value stream
and corporate objectives.

Overall Equipment Effectiveness (OEE) is a good high-level metric that will point your investigation to the
areas of opportunity. OEE is based on “controllable” performance within a plant or production area. OEE
is a ratio of actual/ scheduled performance for Availability, Performance and Quality as illustrated in
Figure 9.
RBAM Implementation Model

Figure 9 – Calculating OEE Points to Areas of Opportunity for Improvement

© Life Cycle Engineering, Inc. | www.LCE.com 11


Phase 4: Measure (cont.)
Once the control plans are defined, planned, scheduled, resourced, and then executed, historical data can
be coupled with work order history, failure codes, material usage, etc. and then utilized in probability
modeling, such as Weibull distribution, to gain an understanding of where the limiting factors reside.

RBAM Implementation Model

Figure 10 – Reliability Analysis Examples

The measures and results point to continuous improvement opportunities, supported by strategies that include:
• Audits/ reviews
• FMEA reviews
• Loss elimination
• Root cause analysis
• Regulatory reviews
• Preventive maintenance optimization

© Life Cycle Engineering, Inc. | www.LCE.com 12


Implementing a Risk-based Asset Management Approach
The development and implementation of a Risk-based Asset Management process will insure that the assets required by the organization to meet
the stakeholder requirements are designed, installed, operated and maintained in the optimal manner to achieve those stakeholder expectations at
the best total cost of ownership across the assets’ life cycle.

Implementation of an RBAM process begins with documenting the stakeholder requirements. From this information we can establish the
corporation’s risk tolerance. That information is then used to analyze the respective assets and develop the appropriate operating, maintenance and
capital plans. Of course the best plans in the world are worthless if the organization lacks the time, resources (people and money), or organizational
discipline to effectively and efficiently implement them. Therefore the required asset management capabilities will also need to be deployed. And
finally, the key performance indicators need to be in place, with associated processes for collecting, analyzing, and responding to them, to verify that
the plans are producing the required performance.

For more information about how LCE has helped organizations apply these principles and deliver the most value from their assets at the lowest cost,
please contact us at info@LCE.com or visit www.LCE.com.

© Life Cycle Engineering, Inc. | www.LCE.com 13

Potrebbero piacerti anche