Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
in Ammonia Plants
In addition to classifying the major causes of shutdowns, this survey
helped identify the most hazardous areas of operation in large tonnage
ammonia plants.
J.G. Sawyer
G.P.Williams
and
J.W. Clegg
Allied Chemical Corp.
Hopewell, Va.
62
Table 2
General classification of major equipment failures
Table 3
Top 10 major equipment failures causing the most downtime
offsite boilers, and improved 1,500 lb./sq. in. gauge steam the "tube and riser" area. (Included in this category are
pressure control system. It is also very probable that the collecting manifold cracks and thermowell failures). Of the
newer plants improved operation at the early stages because 16 pre-1968 plants surveyed, only four did not show a
of experience gained from the older plants. shutdown due to "tubes and risers". The average was one
The biggest problem with many of the newer plants has shutdown/yr. which lasted 1% days. Several plants have had
been the CÛ2 purification exchangers, most of which are in 2- and 3 failures/yr. One plant is planning a 100%
MEA service. They have also had somewhat more problems replacement of reformer tubes in 1972, and some of the
with the air and syn gas compressors than the older plants. other plants are making partial replacements annually.
To date, the newer, larger tonnage ammonia plants have Waste heat boiler failures appear to be the current
had the majority of their problems in the purification and number one industry problem on basis of total downtime.
compression areas, as shown in Table 2. The failures have been split between tube and pressure shell
Table 3 lists the "top 10" major equipment problems failures. The number of failures is not so great, but the
areas for pre-1968 ammonia plants, the 1968-69 plants, and repair time required to pull the bundles, repair tubes,
the total of all surveyed ammonia plants. See Table 5 for a and/or repair or reinsulate the shell has been very high;
complete, detailed listing of equipment failures. averaging about 23 days/failure. Two plants have had
It is interesting to note that the first three problem areas multiple failures and waiting time for parts has been up to
in each list of Table 3 account for over 50% of all major 40-50 days. Six of the plants surveyed have reinsulated
equipment failures. There is a significant break between their waste heat boiler shells. The transfer header failures
items 3 and 4, but only small differences, in days have been similar to the waste heat boiler pressure shell
downtime, between the balance of items on the lists. failures in that a loss of shroud protection and insulation
Many of the "older" plants have a definite problem in have resulted in ruptured pressure walls. (In one case a loss
63
Table 4 downtime from these failures is of short duration, averaging
Classification of downtime and about 2 days/shutdown, and the repairs are of a tube
shutdowns of all 22 plants surveyed. plugging nature. Some design changes have resulted when
% of Total % of Total buying new tube bundles, and most of the exchangers in
Downtime Days Number of S/D's MEA service now have stainless steel tubes in place of the
Turnaround 32% 10% original carbon steel. There has also been a bolt problem
Equipment Failures 59 59 with the internal heads in some le<ui-rich MEA exchangers.
Instrument Failures 2 11 Seventy-five percent of the plants surveyed used MEA as
Electrical Failures :.. 2 .... 10 the scrubbing media, so it was difficult to effectively
Other 5 .... 10
evaluate other systems. However, there are generally more
100% 100%
corrosion problems with MEA than Sulfinol or Hot
Carbonate systems. It should also be pointed out that while
Tojal downtime days from January, 1969 to May, 1971 = 2,571 days. only one shutdown was attributed to a CC>2 stripper leak,
Tdtal number of shutdowns from January, 1969 to May, 1971 = 466.
almost all plants are cladding the shells with stainless steel,
or at least coating the internal shell. Many plants
experiencing stripper leaks have repaired them in run. Some
of water level resulted in a rupture.) Four of the plants
plants are also using a corrosion inhibitor to further protect
surveyed have relined the transfer header in full-or in part.
the MEA system.
The greatest number of shutdowns has been caused by
It was surprising to note that catalysts are not usually a
failure of the syn gas compressor or its driver. These
primary cause of sudden shutdowns. They sometimes add
outages are usually of short duration, averaging about four
impetus towards calling a turnaround, but frequently a
days each. Bearings and, to a lesser extent, governor
plant will limp along until a major outage occurs which will
problems are most common. The overall average downtime
allow changeout.
of four days is somewhat higher than would be anticipated,
but it is influenced by a few major failures of balance
pistons, thrust bearings, turbine seal rings, etc., which Shutdown classifications
sometime necessitate rotor and/or diaphragm replacement. One of the primary purposes of the survey was to
Most plants are now scheduling major inspections every 2- classify various major causes of shutdowns. Table 4
to 3 yr. for all compressor trains. summarizes the categories, and Table 6 provides a more
Another item of concern is the number of exchanger complete breakdown.
failures throughout the industry. The total number Since 91% of the total downtime is related to
(excluding WHB's) ranks third behind the "syn gas turnarounds and equipment, major efforts are, and should
compressor" and "tubes and riser" failures. Most of the be, placed on them. Instrument and electrical problems
failures have been in the .CÛ2 purification exchanger, BFW play a larger part when number of shutdowns are the
preheat exchangers, and syn loop exchangers. Usually criteria, but-as a rule they result in short shutdowns, usually
Table 6
Number of shutdowns and downtime of large tonnage ammonia plants* ')
Instrument Failures Electrical Failures Turnarounds Equipment Failures "Other" Shutdowns Total Longest Run
No. Days<4> No. Days<4> No. Days<4> No. Days<4> No. Days<4> No. Days<4> Time, Days<3>
'63-'64 Ammonia Plants
Totals (16 plants) 35 . . . 39 36 ... 43 3 7 . . .611-... 219..1,195 40....119 367 .. 2,007
Avg./yr./plant 1 ... 1 1 ... 1 1 ... 1 6 . . . . 6.. 31 52 161
Total (22 plants) 50 . .. 55 .. 45 . .. 58 .. . . . 4 9 ... 811..... 273... 1,505 . 49 .... 142 .... . 466 . 2,571 . . ,. .. 3,762
%of Total 11% .. 2% . . . . 10%. . . 2%. . ,... 10%... 32%. . . 59% . 58'A% . 10%... 5%%.
Overall average/yr./plant . . . 1 .... 1 .. 1 .. . 1 ...... 1 ... 15%. . . 5 ... 29 . 1 ... 3 ...,.-. 9. . 49 171
(1) Survey covers operations from January, 1969 to May, 1971 (28 months).
(2) Corrected to delete downtime resulting from high ammonia inventory.
(3) Longest run time is number of consecutive "production days" in which ammonia was produced.
(4) Number of days downtime attributed to respective failure.
64
Table 5
Equipment failures in large tonnage ammonia plants*1)
'63—'67 Ammonia Plants '68-'69 Ammonia Plants Totals
CLASSIFICATION OF FAILURE (16 Plants) (6 Plants) (22 Plants)
No. Days Days/Yr/2) No. Days Days/Yr/2) No. Days Days/Yr.(2>
Primary Reforming area
Tubes & Risers 37 273 . . - ... - 37 .. 273
I.D. Fan 10 47 10 .. 47
Transfer Header. 7 91 . . — . . . . — .. . 7 .. 91
Catalyst 3 ... 31 . . - . . . . — .. . 3 .. 31
Convection Section & Piping . . . 6 . 66 .. 1 7 ... 7 .. 73
Sub total 63 508 13 1 7 Vï 64 515 10
Purification
Catalyst 2 .. . 7 .. 2 ... 9 .. 4 .. 16
Exchangers 10 . 19 .. 2 ... 4 .. 12 .. 23
CÛ2 Purification - Strippers .... 1 . 1 . . - ... - 1 .. 1
- Exchangers . . 16 .. . 36 . . . 1 3 ... 58 .. 29 .. 94
- Pumps & Piping 5 .. . 8 ........ - 5 .. 8
Piping & Flanges 5 . 9 .... 1 ... 1 .. 6 10
Sub total 39 80 2 18 72 5 57 152
Sub total 11 63 2 4 6 % 15 69
Sub total 16 36 19 40
65
The M.W. Kellogg ammonia plant in Hopewell, Va. A Clark .centrifugal syn gas compressor.
lasting less than a day. In some instances they have resulted 2. Secondary reformer/waste heat boiler area piping and
in major equipment damage, which is the greatest hazard in flange fires: Seven major flange fires were reported, and
large plants. About 40% of the plants surveyed have some pressure shell ruptures on WHB's have resulted in fires.
sort of "uninterruptible power supply" (or auxiliary 3. Oil fires around steam turbines have resulted in a few
battery) system. The main support for this type of system major and numerous minor fires.
is that continuous power to instruments and critical small 4. Ruptured piping and flange leaks in natural gas and
electrical motors allows a controlled shutdown during a hot syn gas lines and exchangers have resulted in several
power failure and, in some plants, permits continued fires.
operation of the "front-end" of the plant during a short 5. Leaking seals and flanges in the ammonia
power outage. refrigeration system have caused several "near miss"
An average of all 22 plants showed one 15 day accidents.
maintenance turnaround/yr. However, about one-third of Most fires occurred at the "weak link" in the system —
the plants reported one turnaround for the 28 month the flanged joint. Flanged joint rain shields are used by
survey period, another third reported two, and the last several plants to direct leaking gas in the least hazardous
third reported 3 to 5. For many of these plants, especially direction or to pipe it to a less hazardous location. Periodic
those reporting low turnaround rates, outages resulting checks for gas leaks throughout the plant can be made as an
from major equipment failures have been either long extra safety precaution.
enough and/or frequent enough that the annual turnaround Allied has experienced many of the above mentioned
was taken during these outages. It is interesting to note that fires and incidents, and to date have been extremly
the number of shutdowns from major equipment failures are fortunate that no one has been seriously injured. We can
six times greater than those for turnarounds, and that only emphasize that care and thoroughness must be
downtime is about double. exercised when engineering, constructing, and maintaining
hot gas flanges and pressure systems.
Safety
One of the main objectives of the survey was to identify Acknowledgment
areas in plant operations which have been the most We would like to extend our appreciation to those
hazardous. Following are some of the areas: companies and individuals who participated in the survey
1. Reformer penthouse fires: Three have been reported. and answered the rather lengthy questionnaire. #
66
DISCUSSION
Q. I see here where exchangers were the third largest cause In both cases, corrosion has been reduced from about 10-
of shutdowns. This may be getting back to a previous to 20 mils per year to about one to two mils per year. In
problem. On the syn gas compressor discharge, our cooler I both cases the MEA concentration has been increased from
think uses a carbon steel tubes, SA 106. Could anyone tell approximately 20% to more than 25%. Both inhibitors
me what material are using in this service? Is anyone using effectively control corrosion.
any other kind of material for this service? I believe that Jim Finneran of Kellogg can answer the
JIM ROBINETT, Du Pont - Beaumont. To answer that last questions on loading.
question, we went to some kind of stainless - I don't JIM FINNERAN, M.W. Kellogg Co.: I assume your pre-
remember just what it was in that heat exchanger, mainly 1968 plants are all post-about 1965 plants.
because of water side corrosion. In fact, we've gone SAWYER: You mean actual contract time?
completely stainless in all of our heat exchangers to stay FINNERAN: Startup time.
away from water side corrosion. SAWYER: Right, they are in that neighborhood, '65, '66.
Q. One of the large contributors to downtime was the MEA FINNERAN: So we're talking in general of the large and
system. Has anyone any leads on some way to prevent this modern plants. I can say that from our point of view the
corrosion, any steps at all? Is that considered in the survey? design basis for the MEA systems has not changed from the
SAWYER: It has been considered and there are several 1965 plant to the latest ones; that is, in terms of liquid
inhibitors on the market. I'd better not mention any names loading or temperatures or pressures within the system.
of companies. This is the main item now under There has in fact been an upgrading in material of
consideration for reducing MEA corrosion problems. And construction and I think someone has mentioned here
apparently one or two are inhibitor systems relatively where there has been a tendency to replace carbon steel
effective. with alloyed steel. So that the statistical differences that
Q. The paper mentioned that the newer plants are having you see are still sort of unexplained.
more trouble with the MEA system. Was that more trouble The materials are better and the process conditions are
or a greater percentage of the trouble? no worse. It may just be a statistical quirk. I can't explain
SAWYER: It was actually more days downtime. Gene. It it.
was a higher percentage but it was also more days MAYO: Isn't it possible that this is one of those problems
downtime. that we all run into when we attempt to sort out the causes
Q. Is there any change in the design that's caused that you of downtime that the more obscure causes tend to be
know of? buried in the bigger jobs, and the older plants that were
SAWYER: Not that I now of. I felt that actually the newer having reformer fires and problems with compressors and
plants have more stainless in them than the older ones. reformers were repairing their exchangers during those
Q. Is this really because they design the systems tighter so outages and didn't make note of that fact?
that you're loading up the rich and lean solutions with CÛ2 FINNERAN: It's quite possible.
more to cause corrosion? Because I know some gas plants Q. Perhaps mainly operators filled out the questionnaires,
before we started tightening up on the design, did not have but is any operators error type downtimes included in other
this problem under really the same conditions. categories?
SAWYER: I agree. I don't know of any increase in the SAWYER: We didn't ask for explanations of the "other"
loadings in the plants that I'm familiar with. The systems category, so I don't know.
are designed about the same, except for possibly materials ANON: A company at Pocatello told us about their
of construction. So I really can't answer why there have activated carbon filters and sand filters, sidestream filters
been more problems in the newer plants. that they used on their MEA streams, and we continued to
T.C. CARROLL, American Oil: I think one of the main use inhibitors but we went home and put some of these
reasons is that with the higher reforming pressures tfte sand filters and carbon filters on our two percent
reboilers are seeing much higher temperatures, and it sidestream of our MEA. Our MEA went from corrosive
doesn't take but a few additional degrees in the 250° range yellow to clear white and it stayed this way and our
to increase tube-skin temperatures to a point where severe corrosion's been greatly reduced. So I feel good about this.
corrosion occurs. I think this is one of the main reasons for FINNERAN: The usual design for most of the MEA plants
increased corrosion. includes an activated carson sidestream filter, but most of
SAWYER: That's correct. However, in the survey as I recall them do not use a sand filter. They have the sidestream bag
the reboilers were not the major contributor towards filters, the sidestream carbon drum, and the reclaimer.
downtime but it was in the lean-rich exchangers and the TONY TUCKER: African Explosives and Chemical
coolers themselves, not the reboilers. There were a few Industries: I notice the transfer line failures are fairly high
reboiler failures but not too many. on your list. And we had trouble with that, the transfer
Q. Fifteen years ago they used to design for about line, it never caused a shutdown but we redesigned it about
0.37-0.38 CO2 loading, and now it's up around 0.5. That's 18 months ago, a new shroud. We decided to use bubbled
a moj: mol ratio, and I believe this is too high. alumina. We installed this in March last year. We looked at
SAWYER: Well, I believe, that most of the plants were it in March this year, and it might never have been in
designed for 0.4 or 0.45, that I'm familiar with at any rate. service. It was just in excellent condition.
HAYS MAYO, Cooperative Farm Chemicals Assn.: At the And if anybody is interested in the design, I have it with
time I was associated with Hill Chemicals, the Borger plant me here.
used a commercially available inhibitor in the MEA system. SAWYER: I'd like, if I could to get Mr. Clark to comment
At one of their 600 ton ammonia plants, Farmland upon their new transfer header? I guess it's about a year
Industries uses a different commercially available inhibitor. now since they installed their firebrick type with no
67
shroud. along the line. We finally designed and installed a special
W.D. CLARK, ICI Billingham. We had the original design of brick lining, with no inner metal liner and have installed
transfer line on three units and had much trouble with two, and they look good. The third unit has a considerably
buckling of the 304 liner, loss of the Insulag and modified version of the original type and looks like lasting
overheating of the pressure shell. On one occasion the liners two or three years: when it shows signs of trouble we will
were so badly buckled that a small dog could not have got fit bricks.
68