Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
CHAPLANGCHHU DIVERSION
WAPCOS LIMITED
GURGAON
Combined Kholongchhu HEP & Chaplangchhu Diversion
Document information
Contents
Document information ..................................................................................................... 1
1. INTRODUCTION ......................................................................................................... 3
2. MODELLING THE WATER CONDUCTOR SYSTEM .......................................................... 3
2.1 Input Parameters: .................................................................................................. 4
2.2 Head Race Tunnel................................................................................................... 4
2.3 Friction Parameters: ............................................................................................... 5
2.4 Celerity .................................................................................................................. 5
2.5 Hydraulic Stability of Surge Tank ............................................................................ 6
2.6 Surge Tank Input Parameters ................................................................................. 7
2.7 Operating Rules: .................................................................................................... 7
3. RESULTS & DISCUSSIONS:........................................................................................... 9
4. WHAMO SIMULATION TIME HISTORIES:................................................................... 10
List of Tables:
Table 1 : Manning’s Roughness Co-efficient ........................................................................................... 5
Table 2 : Celerity ..................................................................................................................................... 5
Table 3 : Calculation of Thoma Area ....................................................................................................... 6
Table 4 : Summarizes the operating schedule for all the four cases. .................................................... 8
Table 5 : Max. Pr. Head at Junction between HRT & Connecting tunnel, Max. &Min. Water Level at
Surge Shaft & Max. Head at Turbine End ............................................................................................... 9
List of Figures:
Figure 1: System Schematic .................................................................................................................... 4
Figure 2: Simulation Time history at Surge Shaft for Full Load Acceptance (100-0) ............................ 14
Figure 3: Simulation Time history at Surge Shaft for Full Load Acceptance (0-100) ............................ 15
Figure 4: Simulation Time history at Surge Shaft for Specified Load Acceptance followed by Full Load
Rejection (0-100-0) ............................................................................................................................... 16
Figure 5: Simulation Time history at Surge Shaft for Full Load Rejection followed by Sequential Load
Acceptance (100-0-100) ........................................................................................................................ 17
Figure 6: Simulation Time history at Turbine End for Load Acceptance followed by Full Load Rejection
.............................................................................................................................................................. 18
List of Annexure:
Annexure 1 ........................................................................................................................................... 11
1. INTRODUCTION
Kholongchhu Hydro Electric Project (600 MW) is located on the Kholongchhu River in Trshiyangtse
District of Bhutan. The proposed Kholongchhu HEP comprises of a concrete gravity dam of 95 m high
and 165 m length at top, two intake cumulating into 4.7 m diameter feeder tunnel, with 350m long
two underground desilting chamber, 15.77 km long 5.7 m diameter horseshoe shaped head race
tunnel, a Surge tank of 9.5 m (finished) diameter followed by two steel lined pressure shafts each of
3.3 m diameter 2401 m in length bifurcating into 2.35 m dia just upstream of the Power House to
feed two generating units (total 4 units) installed inside the power house. The design discharge with
10% overloading for each unit is 24.48 m3/s and net head of 761.63m.
The proposed analysis is to assess pressure at various points in water conductor system (and water
levels in Surge Shaft) of Kholongchhu HEP Including impact of Chaplangchhu Diversion in transient
conditions. Transient conditions are the one in which sudden change in boundary conditions of the
flow causes extreme pressure to develop in the system. In a hydropower scheme, these conditions
are experienced during machine start up, sudden closure of the machine or combination of both.
m3/s and 97.9 m3/s respectively. As per WHAMO, only circular conduits is accepts. Therefore,
diameter of equivalent area circular section of main HRT-1 & HRT-2 are considered as 5.86 m for
non-circular sections.
Similarly, diameter of equivalent area of inlet tunnel & connecting tunnel of Chaplangchhu Diversion
is 2.09 m and diameter of drop shaft is 2.5 m which meets with main HRT of Kholongchhu HEP at RD
4446.0 m and center line elevation at 1507.36 m to divert 4 m3/s of discharge of Chaplangchhu nalla.
r = hydraulic radius
Table 1 : Manning’s Roughness Co-efficient
2.4 Celerity
Wave celerity is the speed with which a disturbance moves through a fluid. The celerity for head
race tunnel, surge tank & pressure shaft used in the model are given in the table below:
Table 2 : Celerity
Pressure Shaft
3.3 m dia. 978.8 3211.27
2.35 m dia. 1128.5 3702.43
Chaplangchhu Diversion
Inlet Tunnel & Connecting tunnel 1106.9 3631.57
Drop Shaft 1063.2 3488.19
The calculations of head losses and Thoma area for the surge tank are given in Annexure – 1. The
minimum required cross sectional area of surge tank with factor of safety 1.6 is 32.85 m2. However,
restricted orifice surge tank of size 9.5 m diameter is provided in the Salient features of the DPR.
Correspondingly, surge tank area of 70.88 m2 is provided.
The size of orifice is calculated based on the Calame and Gaden criterion as mentioned in clause
5.5.3.1 of IS 7396 Part-1. The calculations of the orifice size are given in Annexure – 1. The coefficient
of discharge (Cd) adopted for inflow and outflow through the surge tank orifice are considered as
0.62 and 0.75 respectively, which means a head loss coefficient (K = 1/ Cd2) of 2.6 and 1.78 for inflow
and outflow respectively. Considering the head race tunnel of 15770 long from desilting chamber to
surge shaft, the resistance offered by orifice of area about 4.155 m2 corresponding to 2.3 m orifice
diameter, is 73.54 m which satisfies the Calame and Gaden criterion (68.08 ≤ 73.54 ≤ 77.23).
Further, as per IS :7396 (Part-1), area of orifice should be such that the pressure in the tunnel at
orifice due to water hammer caused by total load rejection is nearly equal to the pressure due to
maximum rise of water level in the surge shaft at the time of worst upsurge. Considering the above
aspects, orifice area of 4.155 m2 corresponding to 2.3 m orifice diameter has been considered.
The time of closure (Tc) of 12 sec (for 100% to 0%) is adopted for the turbine. The time taken to start
the turbine is also taken as 12sec. The design discharge for each unit is 24.48 m3/s. Machine is
operated at no load with 10% of design discharge before loading it to 100%.
Case 4- Full Load Rejection followed by Specified Load Acceptance (100-0-100): Load is rejected by
all the turbines simultaneously in 12.0 s and the load is accepted by first unit at the point of
maximum negative velocity in HRT, which is observed to be 219 sec. Simultaneously, one by one all
the units accepted the full load after time tag of 216 sec. Minimum friction and reservoir level is at
MDDL assumed to get the worst results.
Table 4 : Summarizes the operating schedule for all the four cases.
Unit-1 Unit-2 Unit-3 Unit-4
Time (s) Discharge Time (s) Discharge Time (s) Discharge Time (s) Discharge
(m3/s) (m3/s) (m3/s) (m3/s)
Case: 100-0
0 24.48 0 24.48 0 24.48 0 24.48
Case: 100-0-100
0 24.48 0 24.48 0 24.48 0 24.48
30 24.48 30 24.48 30 24.48 30 24.48
42 0 42 0 42 0 42 0
219 0 435 0 651 0 867 0
231 24.48 447 24.48 663 24.48 879 24.48
5000 24.48 5000 24.48 5000 24.48 5000 24.48
Transient Analysis 10 | P a g e
Combined Kholongchhu HEP & Chaplangchhu Diversion
Annexure 1
KHOLONGCHHU HYDRO ELECTRIC PROJECT
Design of Restricted Orifice Surge Tank
Full reservior level 1572 m
MDDL 1558 m
C/L of machine 772.5 m
Avg. Gross Head = 794.83 m
Discharge through HRT before Junction = 85.00 cumec
Diversion Discharge in Chaplangchhu = 4.00 cumec
Discharge through HRT after Junction = 89.00 m
Discharge with 10% overloading = 97.90 cumecs
Total headloss in WCS = 33.30 m
Rated Head = 761.53 m
1. LOSSES IN HRT
Friction Loss in HRT from RD 617.964 m to RD 721.964 (HRT Start)
Dia of HRT D = 4.7 m Horseshoe Shape
2 2
Wetted Area A7 = 18.32 m (A7=0.8293 D )
Transient Analysis 11 | P a g e
Combined Kholongchhu HEP & Chaplangchhu Diversion
Transient Analysis 12 | P a g e
Combined Kholongchhu HEP & Chaplangchhu Diversion
Calame & Gaden Condition for maximum flow for orifice area
Z* /Sqrt(2) +1/4 hf <= hor <= Z*/Sqrt(2) +(3/4) X hf
Transient Analysis 13 | P a g e
Combined Kholongchhu HEP & Chaplangchhu Diversion
Figure 2: Simulation Time history at Surge Shaft for Full Load Acceptance (100-0)
Transient Analysis 14 | P a g e
Combined Kholongchhu HEP & Chaplangchhu Diversion
Figure 3: Simulation Time history at Surge Shaft for Full Load Acceptance (0-100)
Transient Analysis 15 | P a g e
Combined Kholongchhu HEP & Chaplangchhu Diversion
Figure 4: Simulation Time history at Surge Shaft for Specified Load Acceptance followed by Full Load Rejection (0-100-0)
Transient Analysis 16 | P a g e
Combined Kholongchhu HEP & Chaplangchhu Diversion
Figure 5: Simulation Time history at Surge Shaft for Full Load Rejection followed by Sequential Load Acceptance (100-0-100)
Transient Analysis 17 | P a g e
Combined Kholongchhu HEP & Chaplangchhu Diversion
Figure 6: Simulation Time history at Turbine End for Load Acceptance followed by Full Load Rejection
Transient Analysis 18 | P a g e