1.0 SCOPE
This procedure covers the Pre commissioning Test for Switchgears
2.0 PURPOSE
This procedure is prepared to carry out various pre- commissioning tests to be conducted in
systematic manner for Switchgears to ensure the healthiness and performance of the Switchgear.
3.0 PRE-REQUISITES
3.1 SYSTEM REQUIREMENTS
1. Relevant Drawings and layouts.
2. 415 V AC, 3 Ph power supply is available for Testing.
3. All Cables pertaining to switch gear were laid & terminated.
4. Make sure that the Switchgear erected is as per approved drawings & Layouts.
5. Check the Name Plate & Rating Plate Of the Switchgear.
ANNEXURE – I
Details of Switchgear
LOA No. :
Make :
Type: :
Sl. No. :
Year of manufacture:
Operating Voltage:
Feeder details :
Control Voltage:
ANNEXURE – II
Post Installation check list
ANNEXURE – III
Operation Pole
R Y B
Closing Time (msec)
Opening Time (msec)
Close-open Time (msec)
Description Resistance in s
Closing Coil
Trip Coil
iv) Contact Resistance Measurement –
v) Mechanical Checks –
Description Remarks
CB rack in / out operation
CB rack in / out indications
Manual spring charging operation
Spring charged Indication
Manual ON / OFF operation
CB ON / OFF indication
Emergency Trip operation
Power contact alignment with panel contacts
Description Remarks
Spring Charging operation time (Secs)
Test / Service position switch
ON / OFF operation in Local / Remote
Spring charged Indication
CB ON / OFF indication
Lamp Indications
ANNEXURE – IV
Metering / Protection CT Test Report
CT Serial No.
R Ph Y Ph B Ph
(In Ms)
Description R Ph Y Ph B Ph
Primary to Earth
Primary to Secondary Core-1
Primary to Secondary Core-2
Secondary Core-1 to Earth
Secondary Core-2 to Earth
Secondary Core-1 to Core-2
(In s)
Description Terminal Nos. R Ph Y Ph B Ph
Secondary Core-1 1S1-1S2
Secondary Core-2 2S1-2S2
Secondary Core-2
CT Check List
ANNEXURE – V
PT Test Report
PT Serial No.
R Ph Y Ph B Ph
(In Ms)
Description R Ph Y Ph B Ph
Primary to Earth
Primary to Secondary Core-1
Primary to Secondary Core-2
Secondary Core-1 to Earth
Secondary Core-2 to Earth
Secondary Core-1 to Core-2
Secondary
Core-2
PT Check List
ANNEXURE – VI
INSULATION RESISTANCE TEST FOR BUSBAR
a)Phase to earth:
b)Phase to Phase:
ANNEXURE – VII
CONTACT RESISTANCE MEASUREMENT
ANNEXURE – VIII
HIGH VOLTAGE TEST
Circuitry/Operational Checks