ID Task Name Duration Predecessors Successors Start Finish Task Calendar 18 Mar '18

M
1 Half SD from 20/03/18 plan 172 hrs Tue 20-03-18 8:00 AM Tue 27-03-18 12:00 PM None
2 Power cutting and workpermit of VFK5 , VFK3, KS3 , 8 hrs 3,4 Tue 20-03-18 8:00 AM Tue 20-03-18 4:00 PM 12 Hrs Calender
Conveyor belts
3 CK#8 & 11 -Skirt board Ref. measurement 12 hrs 2 19 Tue 20-03-18 4:00 PM Wed 21-03-18 4:00 PM 12 Hrs Calender
4 VFK5 RPG gate removal 6 hrs 25 Tue 20-03-18 4:00 PM Wed 21-03-18 10:00 AM12 Hrs Calender
5 Blanking of Stream 3 2 hrs 46 Wed 21-03-18 10:00 AM Wed 21-03-18 12:00 PM 12 Hrs Calender
6 cleaning of stream 3 12 hrs 5 7,9,11 Wed 21-03-18 12:00 PM Thu 22-03-18 12:00 PM 12 Hrs Calender
7 Holding of Surge hopper segment 1 by Chain blocks 16 hrs 68 Thu 22-03-18 12:00 PM Fri 23-03-18 4:00 PM 12 Hrs Calender
8 Support welding of Surge hopper segment 2 by I beam 16 hrs 7 19 Fri 23-03-18 4:00 PM Sat 24-03-18 8:00 PM 12 Hrs Calender

9 VFK5 Hood removal 4 hrs 6 10 Thu 22-03-18 12:00 PM Thu 22-03-18 4:00 PM 12 Hrs Calender
10 VFK5 Receiving chute removal 2 hrs 9 12 Thu 22-03-18 4:00 PM Thu 22-03-18 6:00 PM 12 Hrs Calender
11 VFK5 Drive dismantling and lowering 3 hrs 6 12 Thu 22-03-18 12:00 PM Thu 22-03-18 3:00 PM 12 Hrs Calender
12 VFK5 Vibrofeeder removal and lowering 6 hrs 11,1013,14,15 Thu 22-03-18 6:00 PM Fri 23-03-18 12:00 PM 12 Hrs Calender
13 Vibrofeeder 5 refurbuishment 48 hrs 12 82 Fri 23-03-18 12:00 PM Tue 27-03-18 12:00 PM 12 Hrs Calender
14 VFK5 Discharge chute base reference measurement 1 hr 12 19,18 Fri 23-03-18 12:00 PM Fri 23-03-18 1:00 PM 12 Hrs Calender
15 VFK3 Drive dismantling and removal 2 hrs 12 16 Fri 23-03-18 12:00 PM Fri 23-03-18 2:00 PM 12 Hrs Calender
16 VFK3 Vibrofeeder removal 6 hrs 15 17,18 Fri 23-03-18 2:00 PM Fri 23-03-18 8:00 PM 12 Hrs Calender
17 Vibrofeeder 3 refurbuishment 24 hrs 16 80 Sat 24-03-18 8:00 AM Sun 25-03-18 8:00 PM 12 Hrs Calender
18 VFK3 Receiving chute removal 4 hrs 14,16 19 Sat 24-03-18 8:00 AM Sat 24-03-18 12:00 PM 12 Hrs Calender
19 Dummy activity for SD starting from 26/03/18 (24 Hrs 84 hrs 14,18,8,3 21 Thu 22-03-18 8:00 PM Mon 26-03-18 8:00 AM None
Calender)
20 MSD Surge hopper plan 570 hrs Mon 26-03-18 8:00 AM Thu 19-04-18 2:00 AM 24 Hours
21 Cleaning of stream 1 and stream 2 24 hrs 19 22 Mon 26-03-18 8:00 AM Tue 27-03-18 8:00 AM24 Hours
22 Workpermit and power cutting 8 hrs 21 34,37,23,28 Tue 27-03-18 8:00 AM Tue 27-03-18 4:00 PM 24 Hours
23 CK4 hood removal 8 hrs 22 24 Tue 27-03-18 4:00 PM Wed 28-03-18 12:00 AM24 Hours
24 CK4 belt removal 24 hrs 23 44,56,25 Wed 28-03-18 12:00 AM Thu 29-03-18 12:00 AM 24 Hours
25 CK4 drive removal and lowering 24 hrs 24 26 Thu 29-03-18 12:00 AM Fri 30-03-18 12:00 AM 24 Hours
26 CK4 drive refurbuishment 72 hrs 25 27 Fri 30-03-18 12:00 AM Mon 02-04-18 12:00 AM 24 Hours
27 CK4 drive installation 48 hrs 26 90 Mon 02-04-18 12:00 AM Wed 04-04-18 12:00 AM24 Hours
28 VFK 1 exciter gearbox removal to ground floor 8 hrs 22 29 Tue 27-03-18 4:00 PM Wed 28-03-18 12:00 AM24 Hours
29 VFK1 vibrofeeder removal and lowering with receiving 16 hrs 28 36,30,31 Wed 28-03-18 12:00 AM Wed 28-03-18 4:00 PM 24 Hours
chute
30 Vibrofeeder 1 refurbuishment 48 hrs 29 79 Wed 28-03-18 4:00 PM Fri 30-03-18 4:00 PM 24 Hours
31 VFK 2 exciter gearbox removal to ground floor 12 hrs 29 32 Wed 28-03-18 4:00 PM Thu 29-03-18 4:00 AM 24 Hours
32 VFK2 Vibrofeeder removal and lowering with receiving 12 hrs 31 33 Thu 29-03-18 4:00 AM Thu 29-03-18 4:00 PM 24 Hours
chute
33 Vibrofeeder 2 refurbuishment 48 hrs 32 78 Thu 29-03-18 4:00 PM Sat 31-03-18 4:00 PM 24 Hours
Task Rolled Up Milestone Inactive Task Manual Summary
Critical Task Rolled Up Progress Inactive Milestone Start-only

Project: MSProj11 Milestone Split Inactive Summary Finish-only


Date: Tue 13-03-18 6:58 PM Summary External Tasks Manual Task Progress
Rolled Up Task Project Summary Duration-only Deadline
Rolled Up Critical Task Group By Summary Manual Summary Rollup

Page 1
ID Task Name Duration Predecessors Successors Start Finish Task Calendar 18 Mar '18
M
34 Surge hopper Discharge chute part 1 middle position 8 hrs 22 35 Tue 27-03-18 4:00 PM Wed 28-03-18 12:00 AM24 Hours
removal
35 Surge hopper Discharge chute part 2 middle position 8 hrs 34 36 Wed 28-03-18 12:00 AM Wed 28-03-18 8:00 AM24 Hours
removal
36 Surge hopper Discharge chute part 3 middle position 8 hrs 35,29 55 Wed 28-03-18 4:00 PM Thu 29-03-18 12:00 AM 24 Hours
removal
37 VFK 4 hood removal 6 hrs 22 38 Tue 27-03-18 4:00 PM Tue 27-03-18 10:00 PM 24 Hours
38 Dribble chute bottom segment removal 6 hrs 37 39 Tue 27-03-18 10:00 PM Wed 28-03-18 4:00 AM24 Hours
39 VFK4 receiving chute removal 6 hrs 38 40 Wed 28-03-18 4:00 AM Wed 28-03-18 10:00 AM24 Hours
40 VFK4 RPG gate removal 6 hrs 39 41 Wed 28-03-18 10:00 AM Wed 28-03-18 4:00 PM 24 Hours
41 VFK4 Vibrofeeder removal and lowering 12 hrs 40 43,55,42 Wed 28-03-18 4:00 PM Thu 29-03-18 4:00 AM 24 Hours
42 VFK 4 refurbuishment 48 hrs 41 81 Thu 29-03-18 4:00 AM Sat 31-03-18 4:00 AM 24 Hours
43 Dribble chute position measurement 4 hrs 41 44 Thu 29-03-18 4:00 AM Thu 29-03-18 8:00 AM 24 Hours
44 Dribble chute pannel west side dismantling 8 hrs 43,24 45 Thu 29-03-18 8:00 AM Thu 29-03-18 4:00 PM 24 Hours
45 Dribble chute pannel north side dismantling 8 hrs 44 46 Thu 29-03-18 4:00 PM Fri 30-03-18 12:00 AM 24 Hours
46 Dribble chute pannel south side dismantling 8 hrs 45 47 Fri 30-03-18 12:00 AM Fri 30-03-18 8:00 AM 24 Hours
47 Dribble chute pannel east side dismantling 8 hrs 46 48 Fri 30-03-18 8:00 AM Fri 30-03-18 4:00 PM 24 Hours
48 Dribble chute pannel east side erection 16 hrs 47 49 Fri 30-03-18 4:00 PM Sat 31-03-18 8:00 AM 24 Hours
49 Dribble chute pannel south side erection 16 hrs 48 50 Sat 31-03-18 8:00 AM Sun 01-04-18 12:00 AM 24 Hours
50 Dribble chute pannel north side erection 16 hrs 49 51 Sun 01-04-18 12:00 AM Sun 01-04-18 4:00 PM 24 Hours
51 Dribble chute pannel west side erection 16 hrs 50 52 Sun 01-04-18 4:00 PM Mon 02-04-18 8:00 AM 24 Hours
52 welding of panels 24 hrs 51 53 Mon 02-04-18 8:00 AM Tue 03-04-18 8:00 AM24 Hours
53 alignment of dribble chute 16 hrs 52 54 Tue 03-04-18 8:00 AM Wed 04-04-18 12:00 AM24 Hours
54 Tiles fixing in dribble chute 72 hrs 53 81 Wed 04-04-18 12:00 AM Sat 07-04-18 12:00 AM 24 Hours
55 Surge hopper segment 3 levelling and measurement 6 hrs 41,36 56 Thu 29-03-18 4:00 AM Thu 29-03-18 10:00 AM 24 Hours
56 Surge hopper segment 3 removal and lowering 16 hrs 55,24 57,58 Thu 29-03-18 10:00 AM Fri 30-03-18 2:00 AM 24 Hours
57 Reference measurement of West and east side beam 4 hrs 56 59 Fri 30-03-18 2:00 AM Fri 30-03-18 6:00 AM 24 Hours
58 Liner removal from surge hopper inside 48 hrs 56 59 Fri 30-03-18 2:00 AM Sun 01-04-18 2:00 AM 24 Hours
59 Beam Shifting West side and east side by 400mm 8 hrs 58,57 60 Sun 01-04-18 2:00 AM Sun 01-04-18 10:00 AM 24 Hours
outwards
60 Surge hopper segment 1 west side and east side removal 8 hrs 59 61 Sun 01-04-18 10:00 AM Sun 01-04-18 6:00 PM 24 Hours
and lowering
61 Surge hopper segment 1 North side and South side 8 hrs 60 62 Sun 01-04-18 6:00 PM Mon 02-04-18 2:00 AM 24 Hours
removal and lowering
62 Surge hopper segment 2 west side and east side removal 8 hrs 61 63 Mon 02-04-18 2:00 AM Mon 02-04-18 10:00 AM 24 Hours
and lowering
63 Surge hopper segment 2 North side and South side 8 hrs 62 64 Mon 02-04-18 10:00 AM Mon 02-04-18 6:00 PM 24 Hours
removal and lowering
Task Rolled Up Milestone Inactive Task Manual Summary
Critical Task Rolled Up Progress Inactive Milestone Start-only

Project: MSProj11 Milestone Split Inactive Summary Finish-only


Date: Tue 13-03-18 6:58 PM Summary External Tasks Manual Task Progress
Rolled Up Task Project Summary Duration-only Deadline
Rolled Up Critical Task Group By Summary Manual Summary Rollup

Page 2
ID Task Name Duration Predecessors Successors Start Finish Task Calendar 18 Mar '18
M
64 Surge hopper segment 1 north and south side positioning 18 hrs 63 65 Mon 02-04-18 6:00 PM Tue 03-04-18 12:00 PM 24 Hours

65 Surge hopper segment 1 west side and east side 18 hrs 64 66 Tue 03-04-18 12:00 PM Wed 04-04-18 6:00 AM24 Hours
positioning
66 Surge hopper segment 2 North side and South side fixing 18 hrs 65 67 Wed 04-04-18 6:00 AM Thu 05-04-18 12:00 AM 24 Hours

67 Surge hopper segment 2 west side and east side fixing 18 hrs 66 68 Thu 05-04-18 12:00 AM Thu 05-04-18 6:00 PM 24 Hours

68 Beam west and east side positioning 16 hrs 67 69 Thu 05-04-18 6:00 PM Fri 06-04-18 10:00 AM 24 Hours
69 Alignment of Segment 1 and segment 2 24 hrs 68 70,71 Fri 06-04-18 10:00 AM Sat 07-04-18 10:00 AM 24 Hours
70 KS#1 Blanking 16 hrs 69 90 Sat 07-04-18 10:00 AM Sun 08-04-18 2:00 AM 24 Hours
71 Tiles fixing in segment 1 and segment 2 96 hrs 69 72 Sat 07-04-18 10:00 AM Wed 11-04-18 10:00 AM24 Hours
72 Surge hopper segment 3 fixing 36 hrs 71 73 Wed 11-04-18 10:00 AM Thu 12-04-18 10:00 PM 24 Hours
73 Surge hopper alignment checking 12 hrs 72 74,77,75 Thu 12-04-18 10:00 PM Fri 13-04-18 10:00 AM 24 Hours
74 Full welding of Surge hopper brackets 24 hrs 73 90 Fri 13-04-18 10:00 AM Sat 14-04-18 10:00 AM 24 Hours
75 CK4 belt erection 24 hrs 73 76 Fri 13-04-18 10:00 AM Sat 14-04-18 10:00 AM 24 Hours
76 CK4 hood erection 12 hrs 75 90 Sat 14-04-18 10:00 AM Sat 14-04-18 10:00 PM 24 Hours
77 RPG gate 4 and 5 fixing 16 hrs 73 82,81,83,84,86 Fri 13-04-18 10:00 AM Sat 14-04-18 2:00 AM 24 Hours
78 Vibfofeeder 2 erection 16 hrs 33 87,79 Sat 31-03-18 4:00 PM Sun 01-04-18 8:00 AM 24 Hours
79 Vibrofeeder 1 erection 16 hrs 30,78 83,80 Sun 01-04-18 8:00 AM Mon 02-04-18 12:00 AM 24 Hours
80 VF 3 erection 16 hrs 17,79 85,84 Mon 02-04-18 12:00 AM Mon 02-04-18 4:00 PM 24 Hours
81 VFk 4 erection 16 hrs 54,42,77 86,82,87 Sat 14-04-18 2:00 AM Sat 14-04-18 6:00 PM 24 Hours
82 Vibrofeeder 5 erection 16 hrs 77,13,81 84,85 Sat 14-04-18 6:00 PM Sun 15-04-18 10:00 AM 24 Hours
83 VFk1 receiving chute complete erection 32 hrs 79,77 90 Sat 14-04-18 2:00 AM Sun 15-04-18 10:00 AM 24 Hours
84 Vibrofeeder 5 receiving chute erection 32 hrs 82,80,77 85,88 Sun 15-04-18 10:00 AM Mon 16-04-18 6:00 PM 24 Hours
85 VFK 3 receiving chute erection 32 hrs 80,82,84 90 Mon 16-04-18 6:00 PM Wed 18-04-18 2:00 AM24 Hours
86 VFK4 receiving chute erection 32 hrs 81,77 87,89 Sat 14-04-18 6:00 PM Mon 16-04-18 2:00 AM 24 Hours
87 Vibrofeeder 2 receiving chute erection 32 hrs 86,78,81 90 Mon 16-04-18 2:00 AM Tue 17-04-18 10:00 AM24 Hours
88 VFK 5 hood erection 8 hrs 84 90 Mon 16-04-18 6:00 PM Tue 17-04-18 2:00 AM24 Hours
89 VFK 4 Hood erection 8 hrs 86 90 Mon 16-04-18 2:00 AM Mon 16-04-18 10:00 AM 24 Hours
90 Testing & Trial 88,89,87,85,83,76,74,70,27
24 hrs Wed 18-04-18 2:00 AM Thu 19-04-18 2:00 AM 24 Hours

Task Rolled Up Milestone Inactive Task Manual Summary


Critical Task Rolled Up Progress Inactive Milestone Start-only

Project: MSProj11 Milestone Split Inactive Summary Finish-only


Date: Tue 13-03-18 6:58 PM Summary External Tasks Manual Task Progress
Rolled Up Task Project Summary Duration-only Deadline
Rolled Up Critical Task Group By Summary Manual Summary Rollup

Page 3
25 Mar '18 01 Apr '18 08 Apr '18 15 Apr '18
T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F

Task Rolled Up Milestone Inactive Task Manual Summary


Critical Task Rolled Up Progress Inactive Milestone Start-only

Project: MSProj11 Milestone Split Inactive Summary Finish-only


Date: Tue 13-03-18 6:58 PM Summary External Tasks Manual Task Progress
Rolled Up Task Project Summary Duration-only Deadline
Rolled Up Critical Task Group By Summary Manual Summary Rollup

Page 4
25 Mar '18 01 Apr '18 08 Apr '18 15 Apr '18
T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F

Task Rolled Up Milestone Inactive Task Manual Summary


Critical Task Rolled Up Progress Inactive Milestone Start-only

Project: MSProj11 Milestone Split Inactive Summary Finish-only


Date: Tue 13-03-18 6:58 PM Summary External Tasks Manual Task Progress
Rolled Up Task Project Summary Duration-only Deadline
Rolled Up Critical Task Group By Summary Manual Summary Rollup

Page 5
25 Mar '18 01 Apr '18 08 Apr '18 15 Apr '18
T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F

Task Rolled Up Milestone Inactive Task Manual Summary


Critical Task Rolled Up Progress Inactive Milestone Start-only

Project: MSProj11 Milestone Split Inactive Summary Finish-only


Date: Tue 13-03-18 6:58 PM Summary External Tasks Manual Task Progress
Rolled Up Task Project Summary Duration-only Deadline
Rolled Up Critical Task Group By Summary Manual Summary Rollup