Waterproofing Works Schedule for Salt water tanks

PROJECT NAME : AQUA(Myanmar Exhibit)


Contractor : Bright Far East Co.,Ltd..
2017
DEC JAN

data
Step /Item
21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21

Step 1 - Sandblasting schedule


for the water tanks and exhibit
tanks ( except main fish tank )

Step 2 -Rectification work for


concrete crack line repair with
SL-1400

Nippura should confirm all


concrete rebates for Acrylic
Panel settings.

Step 3 - Wall formtie grouting


work

Curing time for waterproofing


process
concrete cover Test

Step 4 - Special waterproofing


WP1,2,3,4