BILL OF QUANTITIES - CONSTRUCTION OF A VIP LATRINE BLOCK - BILL NO PAGE NO.


2 UNITS & SHOWER 5 1/1
ITEM DESCRIPTION QTY UNIT RATE (KES) TOTAL (KES)

(All costs are provisional)


-
Provide glazed ceramic tiles to shower floor and 1.5m above the
ground of size 300x300mm embeded in 30mm thick 1:4 cement 10.65 m2 -
1.1
mortar
-
Provide and fix towel rail 600mm long complete with brackets
1.2 fixed to wooden cleats with brass screws with concealed 1 Nr -
arrangement of approved colour
-
Supply and install shower outlet head assembly in 1/2" GI piping,
1.3 1 Nr -
gate valve pegler and stainless steel shower rose
-
Provide all materials and construct inspection chambers
1.4 size 600x600mm, 1200mm deep in masonryblocks plastered 2 Nr -
internally to smooth trowel finish. Rate 600x450mm.
-
Provide all materials and gulley trap chambers size
300x300mm, 600mm deep in masonry blocks and plastered
1.5 1 Nr -
internally to smooth trowel finish. Rate to include for 50mm
thick precast concrete cover, 300mm x300mm
-
Allow for testing the whole of the santary installation during
1.6 progress of works and again on completion and leave in perfect 1 Item -
conditions
-
Fabrication of steel casement (Extra over cost on handwashing
1.7 3 Nr
facilities)
-
GRAND TOTAL -