METRADO
METRADO CONCRETO
CANTIDAD NUMERO DE ACERO POR POR
POR PISO PISOS ELEMENTO ELEMENTO
( kg )
( m3)
ELEMENTOS
COLUMA 1 ( 0.50 X0.25 X 2.90 M) 4 1.00 76.65 0.36
COLUMNA 2 ( 0.50 X 0.50 X 2.90 M ) 16 1.00 153.31 0.73
COLUMNA 3 ( 0.75 X0.50 X 2.9 M) 14 1.00 229.96 1.09
PLACA 1 ( 0.25 X 5 X 2.90) 4 1.00 326.11 3.63
PLACA 2 ( 0.25 X 6.25 X 2.90) 2 1.00 407.63 4.53
VIGAS Y-Y ( 0.25 X 0.50 X 2.50 ) 20.00 1.00 28.11 0.31
VIGAS Y-Y (0.25 X 0.50 X 5.25 M) 4.00 1.00 59.04 0.66
VIGAS Y-Y (0.25 X 0.50 X 5.50 M) 8.00 1.00 61.85 0.69
VIGAS X-X (0.25 X 0.50 X 4.0 M) 8.00 1.00 44.98 0.50
VIGAS X-X (0.25 X 0.50 X 4.25 M) 26.00 1.00 47.79 0.53
L1 LOSAS MACIZAS ( 53 M2) 2.00 1.00 581.83 10.60
L1 LOSAS ALIGERADAS ( 26 M2) 12.00 1.00 305.37 2.26
L2 LOSAS ALIGERADAS (12 M2) 12.00 1.00 140.94 1.04
METRADO 1
TOTALES
3.60 - - - - - - 1.45
4.80 - - - - - - 11.60
6.00 - - - - - - 15.23
29.00 - - - - - - 14.50
34.80 - - - - - - 9.06
2.63 - - - - - - 6.25
5.51 - - - - - - 2.63
5.78 - - - - - - 5.50
4.20 - - - - - - 4.00
4.46 - - - - - - 13.81
53.00 11.00 20.00 - 22.00 40.00 - 21.20
26.00 7.00 10.00 215.80 84.00 120.00 2589.60 27.14
12.00 7.00 3.50 99.60 84.00 42.00 1195.20 12.53
190.00 202.00 3784.80 144.90
2 3 4
- - -
( HORAS )
1 2 138.83
2 6
3 2
1 12 13.88339314
2 18
3 9
2 6
2 7
2 11
1 21
2 3
1 0
2 63
4 3
1 38
5 20
SECTOR 2
KG
ACERO DE COLUMNAS Y PLACAS
M2
ENCOFRADO DE COLUMNAS Y PLACAS
M3
CONCRETO DE COLUMNAS Y PLACAS
M2
ENCOFRADO DE VIGAS FONDOS (SOPORTE)
KG
ACERO DE VIGAS
M2
ENCOFRADO VIGAS COSTADOS
M2
ENCOFRADO DE LOSAS ALIGERADAS
M3
ENCOFRADO DE LOSAS MACIZAS
UND
LADRILLO DE TECHO
KG
ACERO DE LOSAS MACIZAS Y ALIGERADAS
M3
CONCRETO HORIZONTALES
KG
ACERO DE COLUMNAS Y PLACAS
M2
ENCOFRADO DE COLUMNAS Y PLACAS
M3
CONCRETO DE COLUMNAS Y PLACAS
M2
ENCOFRADO DE VIGAS FONDOS (SOPORTE)
KG
ACERO DE VIGAS
M2
ENCOFRADO VIGAS COSTADOS
M2
ENCOFRADO DE LOSAS ALIGERADAS
M3
ENCOFRADO DE LOSAS MACIZAS
UND
LADRILLO DE TECHO
KG
ACERO DE LOSAS MACIZAS Y ALIGERADAS
M3
CONCRETO HORIZONTALES
KG
ACERO DE COLUMNAS Y PLACAS
M2
ENCOFRADO DE COLUMNAS Y PLACAS
M3
CONCRETO DE COLUMNAS Y PLACAS
M2
ENCOFRADO DE VIGAS FONDOS (SOPORTE)
KG
ACERO DE VIGAS
M2
ENCOFRADO VIGAS COSTADOS
M2
ENCOFRADO DE LOSAS ALIGERADAS
M3
ENCOFRADO DE LOSAS MACIZAS
UND
LADRILLO DE TECHO
KG
ACERO DE LOSAS MACIZAS Y ALIGERADAS
M3
CONCRETO HORIZONTALES
Personal
Concreto de horizontales m3
8328.68
366.80
52.93
525.19
65.65
262.59
456.00
106.11
3784.80
9020.16
93.06
SEMANA 00
L M M J
METRADO TOTAL 17 18 19 20
8328.68
366.80
52.93
525.19
65.65
262.59
456.00
106.11
3784.80
9020.16
93.06
SEMANA 00
L M M J
TOTAL 17 18 19 20
8328.68
366.80
12
52.93
73
525.19
65.65
262.59
456.00
106.11
3784.80
9020.16
93.06
270
***
METRADO TOTAL
423.40
744.51
L M
SEMANA 0 SEMANA 1
05 06 07 08 09 10 01 02
V L M M J V L M
21 24 25 26 27 28 01 02
P1S1 P1S2
P1S1 P1S2
P1S1 P1S2
P1S1
P1S1
P1S1
SEMANA 0 SEMANA 1
V L M M J V L M
21 24 25 26 27 28 01 02
2377.8 2361.5
99.9 98.5
14.7 14.5
17.9
777.3
71.8
SEMANA 0 SEMANA 1
V L M M J V L M
21 24 25 26 27 28 01 02
P1S1 P1S2
P1S1 P1S2
P1S1 P1S2
P1S1
P1S1
P1S1
Ped Piso 1
Pedido 1
Pedido 1
****
***
***
SEMANA 1
L M
01 02
14.68 14.50
14.7 14.5
M J V S D L M M
SEMANA 1 SEMANA 2
03 04 05 06 07 08 09 10
M J V L M M J V
03 04 05 08 09 10 11 12
SEMANA 1 SEMANA 2
M J V L M M J V
03 04 05 08 09 10 11 12
SEMANA 1 SEMANA 2
M J V L M M J V
03 04 05 08 09 10 11 12
Pedido 2 Pedido 3
Pedido 2 Pedido 3
Pedido bomba
SEMANA 1 SEMANA 2
M J V L M M J V
03 04 05 08 09 10 11 12
SEMANA 3 SEMANA 4
11 12 13 14 15 16 17 18
L M M J V L M M
15 16 19 17 20 23 24 27
SEMANA 3 SEMANA 4
L M M J V L M M
15 16 19 17 20 23 24 27
SEMANA 3 SEMANA 4
L M M J V L M M
15 16 19 17 20 23 24 27
Pedido 4
Pedido 4
L M M J V L M M
15 16 19 17 20 23 24 27
Pedido 5 Pedido 6
Pedido 5 Pedido 6
Pedido bomba
SEMANA 4 SEMANA 5 SEMAN
J V L M M J V L
25 28 31 32 33 34 35 38
SEMANA 6 SEMANA 7
27 28 29 30 31 32 33 34
M M J V L M M J
39 40 41 42 45 46 47 48
SEMANA 6 SEMANA 7
M M J V L M M J
39 40 41 42 45 46 47 48
SEMANA 6 SEMANA 7
M M J V L M M J
39 40 41 42 45 46 47 48
Lleg Piso 8
Lleg Piso 8
Pedido 7
Pedido 7
SEMANA 6 SEMANA 7
M M J V L M M J
39 40 41 42 45 46 47 48
35
V
49
P8S4
V
49
23.5
V
49
P8S4
V
49
23.5
23.5
Listado de restricciones consolidado
0 Litros
Personal
Elaborado por:
Fecha que se debe realizar la Descripción de la
Fecha requerida en obra
actividad restricción
Aprobado por:
Responsable
Residente de obra
Residente de obra
Residente de obra
Residente de obra
Residente de obra
Residente de obra
Residente de obra
Residente de obra
Residente de obra
Residente de obra
Residente de obra
Residente de obra
Residente de obra
Metrado= 1/𝑅𝑒𝑛𝑑𝑖𝑚𝑖𝑒𝑛𝑡�× # 𝑐𝑢𝑎𝑑𝑟𝑖𝑙𝑙𝑎𝑠 × #�𝑏𝑟𝑒𝑟�𝑠 𝑐/𝑐𝑢𝑎𝑑𝑟𝑖𝑙𝑙
SEMANA
DESCRIPCIÓN UNIDAD L M
01 02
METRADO DIARIO KG 538.07 521.77
SEMANA
DESCRIPCIÓN UNIDAD L M
01 02
METRADO DIARIO M2 47.10 45.70
SEMANA
DESCRIPCIÓN UNIDAD L M
01 02
METRADO DIARIO M2 52.80 52.80
SEMANA
DESCRIPCIÓN UNIDAD L M
01 02
METRADO DIARIO M3 5.98 5.80
SEMANA
DESCRIPCIÓN UNIDAD L M
01 02
METRADO DIARIO M3 8.70 8.70
SEMANA
DESCRIPCIÓN UNIDAD L M
01 02
METRADO DIARIO KG 777.31 729.52
SEMANA
DESCRIPCIÓN UNIDAD L M
01 02
METRADO DIARIO M2 142.09 139.02
SEMANA
DESCRIPCIÓN UNIDAD L M
01 02
METRADO DIARIO KG 2,255.04 2,255.04
SEMANA
DESCRIPCIÓN UNIDAD L M
01 02
METRADO DIARIO M2 946.20 946.20
SEMANA
DESCRIPCIÓN UNIDAD L M
01 02
METRADO DIARIO M3 24.18 23.03
SEMANA 1 SEMANA 2
M J V L M M
03 04 05 07 02 03
521.77 538.07 538.07 521.77 521.77 538.07
SEMANA 1 SEMANA 2
M J V L M M
03 04 05 07 02 03
45.70 47.10 47.10 45.70 45.70 47.10
SEMANA 1 SEMANA 2
M J V L M M
03 04 05 07 02 03
40.80 34.80 52.80 52.80 40.80 34.80
SEMANA 1 SEMANA 2
M J V L M M
03 04 05 07 02 03
5.80 5.98 5.98 5.80 5.80 5.98
SEMANA 1 SEMANA 2
M J V L M M
03 04 05 07 02 03
6.53 5.44 8.70 8.70 6.53 5.44
SEMANA 1 SEMANA 2
M J V L M M
03 04 05 07 02 03
669.01 718.27 777.31 729.52 669.01 718.27
SEMANA 1 SEMANA 2
M J V L M M
03 04 05 07 02 03
139.02 141.98 142.09 139.02 139.02 141.98
SEMANA 1 SEMANA 2
M J V L M M
03 04 05 07 02 03
2,255.04 2,255.04 2,255.04 2,255.04 2,255.04 2,255.04
RILLO DE TECHO
SEMANA 1 SEMANA 2
M J V L M M
03 04 05 07 02 03
946.20 946.20 946.20 946.20 946.20 946.20
MANA 2 SEMANA 3
J V L M M J
04 05 07 02 03 04
47.10 45.70 45.70 47.10 47.10 45.70
MANA 2 SEMANA 3
J V L M M J
04 05 07 02 03 04
5.98 5.80 5.80 5.98 5.98 5.80
MANA 2 SEMANA 3
J V L M M J
04 05 07 02 03 04
8.70 8.70 6.53 5.44 8.70 8.70
MANA 2 SEMANA 3
J V L M M J
04 05 07 02 03 04
777.31 729.52 669.01 718.27 777.31 729.52
MANA 2 SEMANA 3
J V L M M J
04 05 07 02 03 04
2,255.04 2,255.04 2,255.04 2,255.04 2,255.04 2,255.04
MANA 2 SEMANA 3
J V L M M J
04 05 07 02 03 04
946.20 946.20 946.20 946.20 946.20 946.20
SEMANA 4
V L M M J V
05 07 02 03 04 05
45.70 47.10 47.10 45.70 45.70 47.10
SEMANA 4
V L M M J V
05 07 02 03 04 05
5.80 5.98 5.98 5.80 5.80 5.98
SEMANA 4
V L M M J V
05 07 02 03 04 05
6.53 5.44 8.70 8.70 6.53 5.44
SEMANA 4
V L M M J V
05 07 02 03 04 05
669.01 718.27 777.31 729.52 669.01 718.27
SEMANA 4
V L M M J V
05 07 02 03 04 05
2,255.04 2,255.04 2,255.04 2,255.04 2,255.04 2,255.04
SEMANA 4
V L M M J V
05 07 02 03 04 05
946.20 946.20 946.20 946.20 946.20 946.20
SEMANA 5 SEM
L M M J V L
07 02 03 04 05 07
47.10 45.70 45.70 47.10 47.10 45.70
SEMANA 5 SEM
L M M J V L
07 02 03 04 05 07
5.98 5.80 5.80 5.98 5.98 5.80
SEMANA 5 SEM
L M M J V L
07 02 03 04 05 07
8.70 8.70 6.53 5.44 8.70 8.70
SEMANA 5 SEM
L M M J V L
07 02 03 04 05 07
777.31 729.52 669.01 718.27 777.31 729.52
SEMANA 5 SEM
L M M J V L
07 02 03 04 05 07
2,255.04 2,255.04 2,255.04 2,255.04 2,255.04 2,255.04
SEMANA 5 SEM
L M M J V L
07 02 03 04 05 07
946.20 946.20 946.20 946.20 946.20 946.20
SEMANA 6 SEMANA 7
M M J V L M
02 03 04 05 07 02
45.70 47.10 47.10 45.70 45.70 47.10
SEMANA 6 SEMANA 7
M M J V L M
02 03 04 05 07 02
5.80 5.98 5.98 5.80 5.80 5.98
SEMANA 6 SEMANA 7
M M J V L M
02 03 04 05 07 02
6.53 5.44 8.70 8.70 6.53 5.44
SEMANA 6 SEMANA 7
M M J V L M
02 03 04 05 07 02
669.01 718.27 777.31 729.52 669.01 718.27
SEMANA 6 SEMANA 7
M M J V L M
02 03 04 05 07 02
2,255.04 2,255.04 2,255.04 2,255.04 2,255.04 2,255.04
SEMANA 6 SEMANA 7
M M J V L M
02 03 04 05 07 02
946.20 946.20 946.20 946.20 946.20 946.20
- - -
242.78 242.78 242.78
4,248.69 4,491.47 4,734.25
SEMANA 7
M J V
03 04 05
- - -
- - -
150.80 150.80 150.80
2,669.68 2,820.48 2,971.27
SEMANA 7
M J V
03 04 05
- - -
- - -
348.40 348.40 348.40
6,096.99 6,445.39 6,793.79
SEMANA 7
M J V
03 04 05
- - -
- - -
467.83 467.83 467.83
8,272.15 8,739.97 9,207.80
SEMANA 7
M J V
03 04 05
- - -
- - -
- 3.12 - 3.12 - 3.12
- 54.65 - 57.77 - 60.90
SEMANA 7
M J V
03 04 05
- - -
- - -
32.93 32.93 32.93
582.92 615.85 648.77
SEMANA 7
M J V
03 04 05
- - -
- - -
198.36 198.36 198.36
3,475.21 3,673.57 3,871.94
SEMANA 7
M J V
03 04 05
- - -
- - -
13.87 13.87 13.87
243.23 257.10 270.96
SEMANA 7
M J V
03 04 05
- - -
- - -
401.33 401.33 401.33
7,023.33 7,424.66 7,825.99
SEMANA 7
M J V
03 04 05
- - -
- - -
536.06 536.06 536.06
9,381.12 9,917.18 10,453.25
SEMANA 7
M J V
03 04 05
- - -
- - -
537.41 537.41 537.41
9,404.64 9,942.05 10,479.46
SEMANA 7
M J V
03 04 05
- - -
- - -
- 67.92 - 67.92 - 67.92
- 1,189.67 - 1,257.59 - 1,325.51
Metrado= 1/𝑅𝑒𝑛𝑑𝑖𝑚𝑖𝑒𝑛𝑡�× # 𝑐𝑢𝑎𝑑𝑟𝑖𝑙𝑙𝑎𝑠 × #�𝑏𝑟𝑒𝑟�𝑠 𝑐/𝑐𝑢𝑎𝑑𝑟𝑖𝑙𝑙
SEMANA 1
DESCRIPCIÓN UNIDAD L M
01 02
METRADO DIARIO KG 538.07 521.77
SEMANA 1
DESCRIPCIÓN UNIDAD L M
01 02
METRADO DIARIO M2 47.10 45.70
SEMANA 1
DESCRIPCIÓN UNIDAD L M
01 02
METRADO DIARIO M2 52.80 52.80
SEMANA 1
DESCRIPCIÓN UNIDAD L M
01 02
METRADO DIARIO M3 5.98 5.80
SEMANA 1
DESCRIPCIÓN UNIDAD L M
01 02
METRADO DIARIO M3 8.70 8.70
SEMANA 1
DESCRIPCIÓN UNIDAD L M
01 02
METRADO DIARIO KG 777.31 729.52
SEMANA 1
DESCRIPCIÓN UNIDAD L M
01 02
METRADO DIARIO M2 142.09 139.02
SEMANA 1
DESCRIPCIÓN UNIDAD L M
01 02
METRADO DIARIO KG 2,255.04 2,255.04
SEMANA 1
DESCRIPCIÓN UNIDAD L M
01 02
METRADO DIARIO M2 946.20 946.20
SEMANA 1
DESCRIPCIÓN UNIDAD L M
01 02
METRADO DIARIO M3 24.18 23.03
SEMANA 1 SEMANA 2
M J V L M M J V
03 04 05 07 02 03 04 05
521.77 538.07 538.07 521.77 521.77 538.07 538.07 521.77
SEMANA 1 SEMANA 2
M J V L M M J V
03 04 05 07 02 03 04 05
45.70 47.10 47.10 45.70 45.70 47.10 47.10 45.70
SEMANA 1 SEMANA 2
M J V L M M J V
03 04 05 07 02 03 04 05
40.80 34.80 52.80 52.80 40.80 34.80 52.80 52.80
SEMANA 1 SEMANA 2
M J V L M M J V
03 04 05 07 02 03 04 05
5.80 5.98 5.98 5.80 5.80 5.98 5.98 5.80
SEMANA 1 SEMANA 2
M J V L M M J V
03 04 05 07 02 03 04 05
6.53 5.44 8.70 8.70 6.53 5.44 8.70 8.70
SEMANA 1 SEMANA 2
M J V L M M J V
03 04 05 07 02 03 04 05
669.01 718.27 777.31 729.52 669.01 718.27 777.31 729.52
SEMANA 1 SEMANA 2
M J V L M M J V
03 04 05 07 02 03 04 05
139.02 141.98 142.09 139.02 139.02 141.98 142.09 139.02
SEMANA 1 SEMANA 2
M J V L M M J V
03 04 05 07 02 03 04 05
2,255.04 2,255.04 2,255.04 2,255.04 2,255.04 2,255.04 2,255.04 2,255.04
LADRILLO DE TECHO
SEMANA 1 SEMANA 2
M J V L M M J V
03 04 05 07 02 03 04 05
946.20 946.20 946.20 946.20 946.20 946.20 946.20 946.20
SEMANA 3 SEMANA 4
L M M J V L M M
07 02 03 04 05 07 02 03
45.70 47.10 47.10 45.70 45.70 47.10 47.10 45.70
SEMANA 3 SEMANA 4
L M M J V L M M
07 02 03 04 05 07 02 03
5.80 5.98 5.98 5.80 5.80 5.98 5.98 5.80
SEMANA 3 SEMANA 4
L M M J V L M M
07 02 03 04 05 07 02 03
6.53 5.44 8.70 8.70 6.53 5.44 8.70 8.70
SEMANA 3 SEMANA 4
L M M J V L M M
07 02 03 04 05 07 02 03
669.01 718.27 777.31 729.52 669.01 718.27 777.31 729.52
SEMANA 3 SEMANA 4
L M M J V L M M
07 02 03 04 05 07 02 03
2,255.04 2,255.04 2,255.04 2,255.04 2,255.04 2,255.04 2,255.04 2,255.04
SEMANA 3 SEMANA 4
L M M J V L M M
07 02 03 04 05 07 02 03
946.20 946.20 946.20 946.20 946.20 946.20 946.20 946.20
SEMANA 6 SEMANA 7
M M J V L M M J
02 03 04 05 07 02 03 04
45.70 47.10 47.10 45.70 45.70 47.10 - -
SEMANA 6 SEMANA 7
M M J V L M M J
02 03 04 05 07 02 03 04
5.80 5.98 5.98 5.80 5.80 5.98 - -
SEMANA 6 SEMANA 7
M M J V L M M J
02 03 04 05 07 02 03 04
6.53 5.44 8.70 8.70 6.53 5.44 - -
SEMANA 6 SEMANA 7
M M J V L M M J
02 03 04 05 07 02 03 04
669.01 718.27 777.31 729.52 669.01 718.27 - -
SEMANA 6 SEMANA 7
M M J V L M M J
02 03 04 05 07 02 03 04
2,255.04 2,255.04 2,255.04 2,255.04 2,255.04 2,255.04 - -
SEMANA 6 SEMANA 7
M M J V L M M J
02 03 04 05 07 02 03 04
946.20 946.20 946.20 946.20 946.20 946.20 - -
3.00
1.00
0.05
0.05
- 0.00
-
- 59.76
- 1,165.39
V
05
-
10.00
1.00
0.05
0.05
- 0.00
-
- 108.40
- 2,135.93
V
05
-
3.00
2.00
1.05
1.22
- 0.17
-
- 256.92
- 5,009.95
V
05
-
3.00
2.00
1.05
1.09
- 0.04
-
- 59.30
- 1,167.19
V
05
-
1.00
3.00
0.485
1.00
- 0.52
-
- 97.67
- 1,904.53
V
05
-
1.00
3.00
0.485
0.69
- 0.20
-
- 48.07
- 947.23
V
05
-
7.00
2.00
1.700
1.87
- 0.17
-
- 363.79
- 7,100.93
V
05
-
5.00
1.00
0.05
0.06
- 0.01
-
- 272.08
- 5,316.70
V
05
-
7.00
2.00
0.900
0.95
- 0.05
-
- 206.31
- 4,023.15
V
05
-
12.00
1.00
0.05
0.05
- 0.00
-
- 78.34
- 1,527.55
V
05
-
22.00
4.00
0.870
0.89
- 0.02
-
- 691.39
-13,482.14
V
05
-
2.00
3.00
1.100
2.38
- 1.28
-
- 954.81
-18,632.76
CONCLUSIONES
El rendimiento del personal, es una clave importante en la programacion, debido
1
control de las actividades y poder identificar los inconvenientes que se presente
Por la duracion del proyecto que es de 50 dias, solo tendriamos un dia para cada
2
8 pisos. No se podria considerar 2 dias de trabajo para cada actividad, por eso se
El tiempo de curado de 6 días para las losas es una restricción que debería trata
3
a que restringe el avance de las demas actividades.
en la programacion, debido a que esto ayudara al
venientes que se presente en obra.
ndriamos un dia para cada actividades, ya que son
a cada actividad, por eso se ha considerado 1 dia.
stricción que debería tratarse de disminuir, debido