Sei sulla pagina 1di 6

Troubleshooting vacuum systems

Case histories of refinery vacuum tower problems solved are gleaned from
five decades of experience

NORMAN LIEBERMAN
Process Improvement Engineering

T
he objectives of operating Steam
a refinery vacuum tower
are typically to produce No.1 jet
T1
asphalt of proper viscosity or Steam
to minimise the heavy virgin Vacuum P1
gas oil content of the vacuum tower
LVGO P/A
residue going to the delayed
coker feed or to industrial fuel LVGO
No.2 jet
oil. In many cases, the ability
to achieve these objectives is HVGO P/A Steam
the largest factor in determin- HVGO
ing refinery profitability.
Principally, the main objective Wash oil
packing
of the refinery operator is to No.3 jet
Crude tower
restore the degraded vacuum bottoms
in the vacuum tower flash zone
(see Figure 1). The following
case histories illustrate the Quench
problem that occurs in many, if
not most refineries at the start Resid.
of every summer. The problem
is that both ambient air and Figure 1 Vacuum system
plant cooling water tempera-
tures increase. This results in afternoons starting in July the ejector was being overloaded
the first stage ejector surging, a first stage ejector began to with light virgin naphtha
step change degradation in surge and continued to do so components originating in the
vacuum, and vacuum tower until the late evening when crude – that is, in the vacuum
pressure instability. ambient temperatures declined. tower feed from the crude
An analysis of the off-gas from atmospheric tower bottoms.
Increase in vacuum tower top the third stage ejector (see Apparently, the recovery of
temperature Figure 1) indicated a high light naphtha in the crude
In one 40 000 b/d crude unit at concentration of both iso- and tower from the atmospheric
an East coast US refinery, n-pentanes. As the C5 olefin residue was poor. In cooler
producing delayed coker content remained low, we weather, when the LVGO
vacuum resid, during most concluded that the first stage pumparound return was also

www.digitalrefining.com/article/1001321 Revamps 2016 1


discharge pressure. An
From top of
vacuum tower elevated pressure at the
discharge of the first stage jet
10mmHg will cause the jet to lose its
460ºF 250ºF 240ºF 300ºF ‘sonic boost’.1 Alternatively, the
(skin) (skin) (skin) (skin)
30 barg jet loses that portion of its
Motive steam compression ratio due to being
(dry)
210ºF forced out of its critical mode
Steam Throat
(skin) of operation by excessive back
nozzle 125ºF 195ºF
(skin) (skin)
170ºF
(skin)
pressure at P1.
Vapour To correct this problem,
118ºF
through a trial and error proce-
(skin)
190mmHg
dure, we found that reducing
110ºF
the motive steam pressure to
(skin) the second stage jet, from 180
Liquid
psig to 140 psig, lowered the
first stage jet discharge pres-
Figure 2 Excellent performance of the first stage ejector in a Mexican vacuum sure at P1. This restored the
tower sonic boost to the first stage jet
and hence reduced the vacuum
cool, the tower top temperature was only employed as needed tower top pressure. This
(T1 in Figure 1) was cold for several hours on hotter permitted the asphalt product
enough to absorb most of the days. viscosity to be restored to meet
lighter virgin naphtha Note that the fundamental paving grade asphalt
components. problem, which has yet to be specifications.
However, at higher ambient corrected by the refiner, is poor Note that the design motive
temperatures, the LVGO pump- stripping tray efficiency on the steam pressure to all three ejec-
around trim air cooler was bottom six trays of the crude tors was 180 psig. The reason
unable to suppress the vacuum atmospheric tower. Likely, the why the performance of the
tower top temperature suffi- trays are upset as the observed second stage ejector improved,
ciently to condense out enough pressure drop across the trays as the steam pressure was
of the virgin pentanes and was extremely low. reduced to 140 psig, was due
hexanes to avoid overloading to:
the first stage ejector. High first stage ejector exhaust • The steam nozzle (see Figure
To correct the problem pressure 2) inside the second ejector had
on-stream, we improved the On another 35 000 b/d crude become loose
operation of the LVGO cooler unit, the viscosity specification • The nozzle itself was
by: tightening slipping fan for the paving grade asphalt constructed from 316 stainless
belts; increasing the fan blade product of about 10 000 b/d steel
pitch; adding water mist could not be achieved. The • The body of the ejector was
nozzles to humidify and cool problem again was a step carbon steel
the air to the tube bundle (we change loss in vacuum during • The motive steam was wet
did not spray water on the periods of increased cooling (which in itself is a problem)
tubes themselves); brushing off water temperature. The cooling • Galvanic corrosion then
the underside of the tubes with water was drawn from a local caused the threads in the ejec-
a broom; and adding vane tip river. Hence the problem tor body (but not the nozzle
seals to reduce air persisted, even at night when itself) to erode
recirculation. ambient temperatures dropped. • Motive steam then partially
Adding water mist nozzles A field pressure survey indi- bypassed the steam nozzle.
should be minimised since cated that the pressure at P1 After the summer, when this
actually wetting the tubes will (see Figure 1) was 20 mm Hg failure was corrected in the
corrode the fins. This measure above the design critical autumn turnaround, the design

2 Revamps 2016 www.digitalrefining.com/article/1001321


180 psig motive steam pressure fix was to blow the seal legs condenser at a plant in Texas.
to the second stage ejector was out with steam. Steam flow from the discharge
found to be optimum. To of the stronger ejector flowed
partly avoid this problem in Loose steam nozzles backwards through the weaker
the future, Teflon tape was The steam nozzles at a plant in ejector into the suction of the
wrapped around the threads of Louisiana became loose where stronger ejector, which was
the steam nozzle, which may they screw into the body of the then overloaded.
retard the rate of galvanic steam ejector. Sometimes this The problem usually
corrosion. was due to corrosion of the involved hardness deposits in
There are many other exam- carbon steel ejector (the nozzle the throat of the weaker ejector
ples of vacuum system itself is stainless) and some- steam nozzle. A temporary fix
problems, in both vacuum times the nozzle just came is to block in the process side
towers and condensing steam loose without any apparent of the weaker steam nozzle.
turbine surface condensers. We corrosion.
have assembled a summary of The correction was to wrap Leaking condenser channel
malfunctions which represent the steam nozzle threads with head pass partition baffle
the most common problems we Teflon tape, use larger washers Closure between the channel
have seen over a period of five to maintain proper spacing head tube sheet and pass parti-
decades in troubleshooting and between the steam nozzle and tion baffle in the first stage
retrofitting refinery and petro- diffuser inlet, and tighten the condenser was eroded out by
chemical plant steam ejector nozzle forcefully up against the sand in the cooling water at
vacuum systems. spacers. The back end exten- this plant in Alabama. Water
The general lessons that we sion of the ejector body should then by-passed the condenser
have learned are that conven- be stainless and not carbon tubes.
tional descriptions as to how steel. Correction involved using
converging-diverging steam A temporary fix was to silicon sealer along the edge of
ejectors function do not always reduce motive steam pressure the channel head pass partition
correspond with the actual below the design motive steam baffle.
operation of vacuum tower pressure. And a temporary fix was to
ejectors. This is based on inject shredded fibreglass into
observed external temperatures Plugged steam nozzle the cooling water to the
along the jet. Most vacuum Moisture carry-over from local condensers.
system malfunctions originate waste heat kettle boilers at a
with problems external to the plant in South Africa contained Excessive cracked gas
ejectors and with the ejector silicates that then deposited in production in the vacuum
steam nozzles. the throat of the steam nozzles, tower boot
restricting steam flow through Most of the cracked gas over-
Seal drum sludge the nozzles. loading the ejectors at this
This problem at a plant in The correction was to employ plant in Louisiana was due to
Wyoming involved sludge a lower level in the waste heat cracking in the vacuum tower’s
accumulation when the seal boilers. There is a clean-out boot. Correction involved
drum covers the bottom of the plug in the back of the ejector. reducing the boot temperature
seal legs. The condensers then A temporary fix is to unscrew by 20°F by increasing the flow
could not drain properly and the plug and wire brush out of boot quench (or installing
filled with condensate. The the steam nozzle. This cannot boot quench if none exists).
standard design for the seal be done with the ejector in A temporary fix was to
drum is to have the bottom of operation. convert the vacuum tower
the legs 4in (10 cm) above the bottom pumps to suction pres-
bottom of the seal drum. Reverse flow of motive steam sure control rather than level
The correction here was to Reverse flow only occurred control and/or lower the boot
cut off the bottom 12in (30 cm) when discharging dual parallel level until the vacuum tower
of the seal legs. A temporary ejectors to a common bottom pump slips.

www.digitalrefining.com/article/1001321 Revamps 2016 3


Excessive cracked gas condenser air baffle and the Corroded diffuser
production due to high peak inside of the shell was leaking HCl had corroded a hole in the
temperature in the vacuum at an Aruba refinery. This middle of the diffuser body
heater allowed steam to bypass the and caused an air leak at a
Most cracking and gas flow to condenser and overload the Louisiana refinery. The solu-
the ejectors occurs inside the downstream ejector. A correc- tion was to wrap the diffuser
heater tubes – typically two or tion was to employ at least body with duct tape. We have
three tubes from the outlet, due three pairs of 316 stainless steel found that wear on the diffuser
to peaking of temperature (not copper) flexible leaf seal body does not noticeably
inside the tubes. strips extending ¼-½in beyond alter ejector performance
The correction at this plant in the shell’s I.D. A temporary fix unless there is an air leak.
California was to increase the is to feed cold water into the We consider the use of duct
diameter of the last few heater inlet of the condenser if extra tape to be a semi-permanent
tubes to reduce delta P. A seal drum water flow can be repair.
temporary fix is to increase tolerated, and spray water onto
velocity steam to the heater the exterior of the condenser Lack of LVGO pumparound
passes. shell and process inlet line. heat removal
Excessive tower top tempera-
Excess saturated gas flow to Leaking seal leg ture could only be controlled
ejectors Air drawn into the first stage with more HVGO pumparound
Seal drum off-gas had excess condenser seal leg caused heat removal at plants in
amounts of saturated hydrocar- condensate back-up and Alabama and Oklahoma. The
bon components (C3, n-C4) increased temperature and gas result is less LVGO production
rather than olefins (C3=, C4=) at flow to the downstream ejector and reduced absorption effi-
a plant in Alberta, Canada. The at an Oklahoma plant. ciency in the LVGO product
stripping trays in the upstream The carbon steel seal leg was with more vapour flow to the
atmospheric tower bottom replaced with stainless. first stage ejector.
towers were redesigned. A Temporarily, the air leak was We tightened the slipping
temporary fix would be to located by finding a cold spot LVGO pumparound air cooler
check for leaking boot quench on the seal leg, which was then belts and shut off the LVGO
vs crude exchanger (crude leak- wrapped with duct tape. trim cooler for 15 minutes to
ing into the vacuum tower sublime off ammonia salts, then
boot), use more atmospheric Incorrect spacing between reduced the HVGO pumpa-
tower stripping steam, and steam nozzle and diffuser inlet round flow.
employ lower pressure in the The distance between the tip of
atmospheric tower. the steam nozzle and the inlet Excess gas flow from pre-
to the diffuser body is critical condenser
Wet motive steam to develop correct vacuum. In Effluent from the pre-condenser
The motive steam was very this case, a refinery in Denver, contained excessive amounts of
wet (5%+ moisture) at a St Colorado, the two ¼in spacer light naphtha boiling range
Croix plant. Small amounts of rings had been left off. The components, which were over-
moisture did not hurt the ejec- solution was to shut down the loading the first stage ejector at
tor’s performance noticeably. A ejector and install the two a refinery in Louisiana. The
temporary fix was to wrap the missing spacers, although a correction was to improve
steam line with steam tracing temporary improvement is stripping tray efficiency in the
coil and/or electric heat trace available by changing the crude tower bottoms, with a
line and/or reinsulate the motive steam pressure. temporary fix option to raise
steam supply line. (Note: the maximum discharge the vacuum tower top tempera-
pressure to avoid jet surging ture to distill over more heavier
Leaking condenser air baffle can be increased by advancing naphtha boiling range compo-
leaf seals the steam nozzle position nents that act as an absorption
The seal between the top of the slightly.) oil.

4 Revamps 2016 www.digitalrefining.com/article/1001321


Partly plugged pre-condenser Oversized condenser Excessive use of stripping in
and first stage condenser impingement plate crude tower bottoms
Often condensers are Excessive ejector discharge The jets were overloaded with
purchased as follows: pressure caused surging at an too much light hydrocarbons at
• Fixed Tube-Sheet asphalt plant in San Francisco, a plant in Alberta, Canada. Lab
• ¾in tubes California. The problem was analysis indicated that most of
• Triangular pitch excessive pressure drop in the the gas was not cracked gas
• 15/16in tube pitch. downstream condenser, but virgin hydrocarbons from
Such condensers can never corrected by reducing the the crude charge. Increasing
be effectively cleaned as the diameter of the condenser the crude tower bottom strip-
bundle cannot be extracted impingement plate to slightly ping steam flow increased the
from the shell side. Delta P larger than the inlet nozzle, crude tower flash zone pres-
eventually becomes excessive. with a temporary fix of sure and made the problem
The solution for a plant in reduced motive steam worse in the vacuum tower.
Louisiana was to purchase an pressure. The solution was to add
exchanger with these features: more crude tower overhead
• Pull-through bundle Condensate back-up in condenser capacity, with a
• 1in tubes pre-condenser temporary fix of cleaning the
• Rotated square pitch Condensate backed up into the underside of the forced draft,
• 1½in tube pitch. pre-condenser and covered the air-cooled overhead condenser
A temporary fix is to circu- bottom edge of the vapour finned tubes on the crude unit.
late toluene and HCl through baffle, greatly increasing
the shell but this is only condenser delta P. The seal High vacuum tower boot level
partially effective. drum at this Louisiana refinery The vacuum tower boot resi-
was found to be flooded. dence time was excessive at a
Excessive CO2 and N2 in off-gas The level indication was 60%, refinery in Corpus Christi,
Sample of off-gas from the seal when the actual level Texas, hence the bottoms
drum of a Missouri refinery was 100%+. The primary seal pumps were switched to
included 40% N2, 10% CO2 and drum pump was running suction pressure control.
no O2. Lack of O2 and 10% CO2 partly below its performance
indicates an air leak in the curve. High liquid level in
vacuum heater transfer line. A temporary solution was to pre-condenser
There is no temporary fix for turn on the spare seal drum The condenser boot level was
this. It is a very dangerous pump and run two pumps in excessive due to a faulty level
situation and requires immedi- parallel. indication at a plant in
ate shutdown. Louisiana. A leaking plug on
Excessive seal drum pressure top of the level control was
Erosion of steam nozzle Back pressure from the seal allowing atmospheric air pres-
The ejector surged and lost drum off-gas increased the sure to depress the level
vacuum when the cooling liquid levels in the condensers indication and so was
water temperature increased due to back-up from the seal tightened.
by 5°F at a plant in Louisiana. legs at this plant in New
The moisture content of the Orleans, Louisiana. The prob- Surprisingly excellent vacuum
steam had caused nozzle lem was high delta P through This article closes with a posi-
erosion after several years. The the waste gas burner in the tive experience from a recent
nozzle was replaced. A more vacuum heater. The burner troubleshooting assignment.
than 5% increase in nozzle needed to be cleaned. Figure 2 shows an approximate
throat diameter is excessive. Temporarily, part of the seal exterior temperature profile for
A temporary fix is to reduce drum off-gas was diverted to the first stage ejector on a
motive steam pressure below the gas compressor or to the medium sized vacuum tower
design to reduce steam load to flare. However, flaring H2S rich in a refinery in Mexico. In 50
the downstream condenser. gas is no longer legal. years of troubleshooting refin-

www.digitalrefining.com/article/1001321 Revamps 2016 5


Troubleshooting checklist temperatures shown were skin
temperatures obtained with an
infrared gun. The ejector was
• Clean steam inlet nozzle throat.
• Check nozzle tip-to-diffuser inlet distance is set correctly. quite long (about 20ft, 6m) and
• Check if steam nozzle is loose. small in diameter (about 12in,
• Check if the diffuser body is leaking.
• Renew insulation on motive steam line to jets. 30cm). The motive steam
• Lower boot level in vacuum tower. visually appeared to be dry.
• Lower boot temperature in vacuum tower.
• Check condenser’s pass partition baffle for cooling water by-passing inside channel head.
• Check LVGO pumparound fan belts for tightness. Summary
• Optimise ratio of LVGO vs HVGO pumparound duties. The complexity of refinery
• Shut off LVGO pumparound trim air coolers for 20 minutes to sublime or melt off deposits.
• Check the ratio of C3/C4 saturates to C3/C4 olefins and check for virgin crude components in vacuum system malfunctions
vacuum tower feed. could extend this list, based on
• Check for leaking vapour baffle leaf seal strips and whether the impingement plate in
the pre-condenser is too large.
the author’s experience, by an
order of magnitude. Not many
Table 1 months go by before a new and
unexpected type of vacuum
ery vacuum towers, this is the considering that only one of the system problem is encountered.
best compression ratio ever two ejector trains was in More so than other types of
observed: service. refinery process equipment,
• Suction = 10 mm Hg The external temperature troubleshooting vacuum
• Discharge = 190+ mm Hg. profile shows a normal temper- systems requires determination
Overall compression ratio: ature rise upstream of the and dedication as well as care-
• 190/10 = 19. diffuser throat (see Figure 2), ful field observations.
The ejector inlet pressure was and then a large temperature To end, here (see Table 1) is a
taken with an absolute Hg drop just before the diffuser troubleshooting list for a refin-
manometer. The delta P across throat (which, according to ery vacuum system.
the condenser was neglected. theory, is to be expected). Just
Reference
The condenser vapour outlet at the throat, there is a sudden 1 Lieberman N P, Troubleshooting
pressure was measured with an temperature jump. That is the Vacuum Systems, Wiley Publications.
ordinary 0-30in Hg gauge, effect of the gas being
which was checked for zero at compressed as the flow changes Norman Lieberman is a field
atmospheric pressure and read from sonic to subsonic (the troubleshooter for refinery process
22.1in Hg at the jet discharge. ‘sonic boost’). problems and has been instructing
refinery troubleshooting seminars since
The refinery was at sea level, Thereafter, the temperature
1983. His company provides retrofit
but the condenser was elevated rise continues in a normal
designs for refinery vacuum systems.
about 100ft (30.5m) above pattern. The observed tempera- He graduated with a degree in chemical
grade. ture drop between 250°F and engineering from Cooper Union for the
Typical first stage ejector 170°F (120°C and 75°C), accord- Advancement of Science and Art in New
compression ratios range from ing to vendor publications is York.
two (bad) to eight (excellent). normal. But the author has only
The ejector itself had been seen this before when the
made locally in Mexico and no motive steam has been wet. LINKS
curve was available. While the The conclusion is that the sort
tower flash zone temperature of external temperature profile More articles from the following
was only 380°C (716°F), and the observed is characteristic of an categories:
feed rate was only 60%-70% of ejector in good mechanical Crude and Vacuum Units
design, still the compression condition, running lightly Revamps and Turnarounds
ratio of 19 is impressive, loaded. Note that all the

6 Revamps 2016 www.digitalrefining.com/article/1001321

Potrebbero piacerti anche