1.

) STRUCTURE EXCAVATION
F-1 WF-1
foundation = 6.48 cu.m. Area= 0.36 sq.m. H= 0.6 m.
wall footing01= 8.904 cu.m. H= 1 m. W= 0.4 m.
wall footing02= 11.352 cu.m. # of pcs.= 18 unit Perimeter = 37.1 m.
16.93 cu.m.
WF-2
H= 0.6 m.
W= 0.4 m.
Perimeter = 47.3 m.

2.) EMBANKMENT ( Vol. of excavation - Vol of structures)


F-1 WF-1
foundation = 6.48 cu.m. Vol.= cu.m. Vol.= 2.7825 cu.m.
wall footing= 6.1215 cu.m. # of pcs.= unit
slab on fill= 0 cu.m.
13.87 cu.m.

3.) REINFORCING STEEL BARS

6m commercial length/pc. factor K.G.


10 mm Ø RSB L= 2775.95 m. 463 pcs. 3.70 1714
12 mm Ø RSB L= 572.72 m. 95 pcs. 5.33 507

weight= ز x 0.00617 x Length


mm. m.

Note : tie wire factor is 1kg per 53m.

foundation= 2.55
wall footing= 4.82
column= 70.62
beam= 17.06
chb walls= 7.14
slab on fill=
TOTAL= 102.19 Kg.
foundation
F-1
Length = 0.6 m.
Width = 0.6 m.
# of bars L= 5 pcs.
# of bars W= 5 pcs.
# of footing= 18 pcs.
total= 108 m.

#16 G.I. tie wire used= 2.55 Kg.

Wall footing01
WF-1
Width of wall footing= 0.4 m.
Length of wall footing= 37.1 m.
no. of longitudinal length= 3 pcs.
Spacing of tie bars for wall footing= 0.3 m.
no. of tie bars for wall footing= 124.6667 pcs.
total length of longitudinal wall footing= 334 m.
total length of tie bars for wall footing= 50 m.
#16 G.I. tie wire used= 2.12 Kg.

Wall footing02
WF-2
Width of wall footing= 0.4 m.
Length of wall footing= 47.3 m.
no. of longitudinal length= 3 pcs.
Spacing of tie bars for wall footing= 0.3 m.
no. of tie bars for wall footing= 158.6667 pcs.
total length of longitudinal wall footing= 426 m.
total length of tie bars for wall footing= 63 m.

#16 G.I. tie wire used= 2.7 Kg.

Columns
C-1a C-1b
Height= 4.6 3.1 m.
no. of bars (vertical)= 4 4 pcs.
end hook used= 0.15 0.15 m.
# of column= 9 9 pcs.
total length of vertical column= 171 117 m.

column dimension (D1)= 0.25 0.25 m.


column dimension (D2)= 0.25 0.25 m.
length of lateral ties= 0.9 0.9 m.
spacing of ties= 0.2 0.2 m.
# of 50mm ties= 2 2
# of ties= 207 139.5 pcs.
total length of ties= 188 127 m.

#16 G.I. tie wire used= 42.19 28.43 Kg.

Beams
B-1 TB-1 B-3 LB-1
Length of beam= 37.1 6.48
# of beams= 1 1
# of continuous bars on top= 2 2
# of non continuous bars on top= 0 0 0 0
deformed web bars= 0 0 0 0
# of continuous bars on bottom= 2 2 2 2
# of non continuous bars on bottom= 0 0 0 0
length of contiuous bars on top= 74.8 13.56 0 0
length of non contiuous bars on top= 0 0 0 0
length of deformed web bars= 0 0 0 0
length of contiuous bars on bottom= 74.8 13.56 0 0
length of non contiuous bars on bottom= 0 0 0 0
total length of bars used= 149.6 27.12 0 0

width of beam= 0.2 0.2


depth of beam= 0.3 0.3
column width= 0.25 0.25
spacing of stirrups= 0.2 0.2
# of stirrups @ 50mm= 4 4 5 5
# of stirrups @ spacing= 186 32 #DIV/0! #DIV/0!
length of stirrups used= 0.9 0.9 -0.1 -0.1
total length of stirrups= 171 32 #DIV/0! #DIV/0!

#16 G.I. tie wire used= 14.34 2.72 #DIV/0! #DIV/0!

Masonry Wall
W-1 W-2
height of wall= 4 4 m.
Perimeter of wall= 37.1 47.3 m.
area of doors = 2.64 0 sq.m.
area of windows= 4.8 15.4 sq.m.
net area of wall= 140.96 173.8 sq.m.
factor= 4.4 4.4 m./sq.m.
length of bars for masonry wall= 620.23 764.72 m.

#16 G.I. tie wire used= 3.2 3.94 Kg.

4.) MASONRY WORKS


A.) W-1 W-1
height of wall= 3.6 3.6 m.
Perimeter of wall= 37.1 47.3 m.
area of windows= 4.8 15.4 sq.m.
area of doors= 2.64 0 sq.m.
breakage allowance= 5% 5%
net area of wall= 126.12 154.88
# of pcs. Of CHB= 1656 2033 pcs.

Note: default mixtures for mortar is Class B (1:3)


B.) Mortar for 4" CHB
Volume of Mortar= 5.51 6.76 cu.m.
# of 40Kg. Cement Bags= 67 82 pcs.
Volume of screened sand= 5.51 6.76 cu.m.

C.) Rough Plaster ( 0.0015 cu.m. plaster per 1 face of CHB )


Note: plastered on both face 16mm thk.)
Volume of Plaster= 9.4392 11.5881 cu.m.
# of 40Kg. cement bags= 114 140 pcs.
Volume of sand = 12.55414 15.41217 cu.m.

D.) Fine Finish


# of 40Kg. cement bags= 64 78 pcs.

5.) REINFORCED CONCRETE (class A)


Note: use Class A concrete mix (1:2:4)
foundation
F-1
length= 0.6 m.
width= 0.6 m.
thickness= 0.3 m.
# of foundation= 18 pcs.
Volume= 2.14 cu.m.
# of 40Kg. Cement bags= 19.26 pcs.
Volume of sand= 1.07 cu.m.
Volume of 3/4" gravel= 2.14 cu.m.
Wall footing
WF-1 WF-2
Perimeter of WF-1= 37.1 47.3 m.
Width of WF-1= 0.4 0.4 m.
Thickness of WF-1= 0.25 0.25 m.
Volume of WF= 4.09 5.21 cu.m.
# of 40Kg. Cement bags= 36.81 46.89 pcs.
Volume of sand= 2.045 2.605 cu.m.
Volume of 3/4" gravel= 4.09 5.21 cu.m.

Column
C-1A C-1B
Height of C-1= 4.6 3.1 m.
column dimension (D1)= 0.25 0.25 m.
column dimension (D2)= 0.25 0.25 m.
# of C-1= 9 9 pcs.
Volume of Column= 2.72 1.84 cu.m.
# of 40Kg. Cement bags= 24.48 16.56 pcs.
Volume of sand= 1.36 0.92 cu.m.
Volume of 3/4" gravel= 2.72 1.84 cu.m.

Beam
B-1 TB-01 B-3 LB-1
Length of B-1= 37.1 6.48
Widht of B-1= 0.2 0.2
Depth of B-1= 0.3 0.3
# of B-1= 1 1 1 1
Volume of Beam= 2.3373 0.40824 0 0
# of 40Kg. Cement bags= 21.0357 3.67416 0 0
Volume of sand= 1.16865 0.20412 0 0
Volume of 3/4" gravel= 2.3373 0.40824 0 0

Slab on fill
S-1
Area of S-1= 0 sq.m.
thickness S-1= 0.1 m.
Volume of Slab= 0 cu.m.
# of 40Kg. Cement bags= 0 pcs.
Volume of sand= 0 cu.m.
Volume of 3/4" gravel= 0 cu.m.