Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
PIPING DRAWINGS
T. N. GOPINATH
THE BASICS
The drawings are always considered as the paper by the use of which 3D representation
language of engineers. The machine of the pipelines can be prepared.
drawings and the geometrical drawings are 1.0 PLAN AND ISOMETRIC
taught in the basic engineering curriculum. PRESENTATION OF A PIPING
Piping Engineers derive basics from these to SYSTEM
represent the pipeline routing on the
The purpose of drawing is to give detailed
drawing. There are two types of views used
information so that the pipelines could be
in the piping drawings:
fabricated and erected to satisfy the process
a) Orthographic.- Plans and Elevations requirements. Prior to making the piping
b) Perspective. - Isometric Views drawings, the equipment layout drawings
Piping layout is developed in both plan view and plot plan are prepared and these
and elevation view and section / details are drawings are used as the basis for
added for clarity wherever necessary. These developing the piping drawing. Sometimes,
drawings are called the General preliminary piping study is made to fix the
Arrangement of Piping. To represent a three equipment co-ordinates. The other data
plane piping in two dimensions of the paper, required for the development of piping
certain symbols are followed. Most drawings are defined in the chapter on
commonly used symbols are in Table 1. “Equipment and Piping Layout”.
Orthographic symbols are available in
For presentation of unit piping layout, the
templates that are used for speeding up the
scale adopted usually are 1:25 or 1:331/3
manual drafting and also the symbol library
(1:33.33)and 1:100 for the pipe rack. There
for computer aided drafting.
are different sizes of drawing sheets
In complex piping systems, especially available for the preparation of the
within the unit/plant building where drawings. The sizes of the drawing sheets as
orthographic views do not illustrate the per ISO are as given below:
details of design fully, pictorial view in
SIZE OVERALL DIMENSIONS
isometric presentation is drawn for clarity.
in mm (Untrimmed)
Specially printed isometric sheets are
A0 - 841 x 1189
available with lines drawn vertically and at
A1 - 594 x 841
30o clockwise and 30o counter-clockwise
A2 - 420 x 594
respectively from the horizontal axis of the
A3 - 297 x 420
A4 - 210 x 297
Piping Drawings.doc 1
PIPING ENGINEERING CELL
Piping Drawings.doc 2
PIPING ENGINEERING CELL
Piping Drawings.doc 3
PIPING ENGINEERING CELL
Piping Drawings.doc 4
PIPING ENGINEERING CELL
Piping Drawings.doc 5
PIPING ENGINEERING CELL
Piping Drawings.doc 6
PIPING ENGINEERING CELL
Piping General Arrangement is normally 2.4 In-plant piping drawings are drawn to
drawn on A0 size sheet. If the area to be 1:331/3 scale and Pipe rack piping plan
covered is small, then A1 size sheet is also to 1:100 scale with junction details
used. Piping group produces a ‘KEY PLAN’, enlarged if necessary.
which is a plot plan on a small scale (1:500,
1:750 or 1:1000 or smaller), which can be 2.5 Equipment layout is reproduced on
accommodated above the title block, dividing the Piping GA to its scale and drawn
the total area into smaller areas which are on the reverse side in case of manual
covered in all the piping drawings. For drafting. In case of CAD, separate
identifying the relative location of the area layer is used for equipment layout.
covered in the plan the area covered in that The major primary beams and
particular drawing is hatched or shaded. secondary beams are also shown if
area covered is indoors.
The dimensional details of the title
block are developed based on the project 2.6 Pertinent background details which
requirement. The drawing sheet is divided govern piping routing, such as floor
along the length and the breadth in equal drains, HVAC ducting, electrical and
spaces and marked along the boundary. The instrument cable trays, etc. are also
longitudinal blocks are identified by alphabets drawn in faint on the reverse.
and those along the breadth numerically.
These co-ordinates are used to locate the area 2.7 Utility stations are also established so
on the drawing which the reviewer or a that the most convenient utility
discussion team wants to draw attention to. header routing can be carried out.
The direction of the north is taken either
towards the right or left on the top of the 3.0 DEVELOPMENT OF PIPING
drawing sheet. This direction is kept constant GENERAL ARRANGEMENT
in all the areas covered in the plant, so also is DRAWING
the scale of the drawing.
3.1 The piping drawings should be
2.0 HOW TO START THE PIPING GA? developed in such a way that all the
process requirements are met with.
2.1 Place the north arrow at the top left/right
hand corner of the sheet to indicate plant 3.2 It is not always possible for the piping
north. drawing to follow exactly the logical
arrangement of the P&IDs.
2.2 Do not plan drawing in the area above Sometimes, lines must be routed with
the title block of drawing, as this is different junction sequence and line
allotted for general notes, number and numbers and subsequently the list
title of reference drawings, brief may be changed.
description of changes during revision
and the bill of materials wherever 3.3 Performance and economics have to
applicable. be considered in parallel while
deciding the routing.
2.3 Process equipment and piping have
priority on the Piping GA. The piping 3.4 Piping is represented by single lines
drawings are started after fixing up to a size of 150 NB and double
positions of the equipments. lines for sizes 200 NB and above.
Piping Drawings.doc 7
PIPING ENGINEERING CELL
This is to save the time of drafting and to 3.14 Each line should be identified by line
avoid confusion. number and should also show the
insulation, tracing requirements, etc.
3.5 In single line representation, only the
centre line of the pipeline is drawn using 3.15 Lines, if required, shall be broken to
solid line and in the double line show the required details of hidden
representation, the actual size to scale is lines without drawing other views.
drawn with centre line marked in chain-
dotted lines. 3.16 Do not draw details that can be
covered by a note.
3.6 Line numbers are shown against each
line exactly in the same way as 3.17 Draw plan to a larger scale for any
represented in the P&I Diagrams. part needing more details and identify
it as “Detail ‘A’”, etc.
3.7 The change in specification should be
shown in line with P&I Diagram. This 3.18 Draw part isometric sketches or part
change is usually indicated immediately elevations to clarify complex piping
to the downstream of the valve, flange or or piping hidden in the plan view.
equipment.
3.19 Full sections through the plant may be
3.8 Valves should be drawn to scale with avoided if isometric drawings are
identification number from the P&ID drawn for the lines. Part sections,
marked thereon. where required, shall be shown to
clear the hidden details in plan.
3.9 Draw valve hand wheels to scale with
stem fully extended. If it is lever 3.20 Sections in the plan views are
operated, then the movement of handle identified by numbers, say 1-1, 2-2,
position should be marked. etc. and details by alphabets, e.g.
“Detail ‘A’”.
3.10 If a valve is chain operated, note the
distance of the chain from the operating
floor.
Piping Drawings.doc 8
PIPING ENGINEERING CELL
Piping Drawings.doc 9
PIPING ENGINEERING CELL
Piping Drawings.doc 10
PIPING ENGINEERING CELL
Piping Drawings.doc 11
PIPING ENGINEERING CELL
Piping Drawings.doc 12
PIPING ENGINEERING CELL
Piping Drawings.doc 13
PIPING ENGINEERING CELL
6.10 The horizontal nozzles on the equipment paved areas, it shall be the high point
shall be located from centre to flange of paving (HPP).
face in plan. For vertical nozzles show
Face of Flange elevation (FOF). 6.15 For foundation, the Top of Grout
(TOG) elevation is shown.
6.11 For valves, instruments and non -
standard equipment, show the 6.16 Show dimensions outside the drawn
dimensions from flange face to flange view - do not cut pictures.
face.
6.17 Draw dimension line unbroken with
fine line. Write dimension just above
the horizontal line. For vertical lines
write sideways.
Piping Drawings.doc 14
PIPING ENGINEERING CELL
6.20 Do not omit significant dimension other 7.1 Title of the drawing.
than fitting make up.
7.2 Orientation - North arrow against plot
plan.
Piping Drawings.doc 15
PIPING ENGINEERING CELL
7.17 Adequacy of clearance from civil 7.21 Details and section identification
structures, electrical apparatus and match.
instrument consoles.
7.22 “Matchline” provision and accuracy.
7.18 Floor and wall openings.
7.23 Presence of signatures and dates.
7.19 Accessibility of operation and
maintenance space and provision of drop 7.24 Accuracy of BOM in Isometrics.
out and handling areas.
7.25 Number of the issue and the revision.
7.20 Foundation drawings and vendor
equipment requirements.
****************
Piping Drawings.doc 16