BILL OF QUANTTIES

Item Quantit
Description Unit Unit Rate Amount (RM)
No. y
1 EXCAVATION
Excavation of trench depth more then 4118.72
m3 68.76 RM59.90/m3
1.5m not exceeding 3.0 m

2 FILLING

Backfilling for footing m3 52.99 RM17.50/m3 927.25

3 FORMWORK

Sawn timber of 38 mm thickness m2 223.84 RM17.50 /m2 3917.25

4 CONCRETE WORK

Mass concrete,Grade 30 m3 30.32 RM246.67/m3 7479.77

5 LEAN CONCRETE
Lean concrete of 50mm for footing of
m2 19.523 RM11.48/m2 224.12
foundation
6 REINFORCEMENT

10mm diameter high steel kg 393.29 RM 2.537/kg 997.78

12mm diameter high steel kg 743.52 RM 2.537/kg 1886.32

16mm diameter high steel kg 339.79 RM 2.353/kg 799.54

20mm diameter high steel kg 61.14 RM 2.353/kg 143.85

6mm diameter mild steel kg 306.12 RM 2.537/kg 776.62

BRC A7,70.843m2 m2 69.31 RM9.20/m2 637.66

TOTAL AMOUNT (RM)


21908.90