Appendix A

Sr. No. Owner Letter ref. Date of Letter Subject of letters


1 SFBR-0092-0 30/Jan/17Submission of Interim Extension of Time No.1
Engineer's concerns of Works progress & refusal to determine EOT
2 667620/18.2/31/44.1/47/129/Z 31/Jan/17 submission due to site progress concerns

3 SFBR-0092-1 1/Feb/17Repudiation of Engineer's refusal to assess interim EOT submission


Request for substantiation of cost for advance payment & actual
4 667620/18.2/31/44.1/47/133/Z 1/Feb/17 expenditure of site office maintenance
Acknowledgment in receipt of Meeting minutes & confirmation of
5 SFBR-0092-2 2/Feb/17 further meeting 05.02.17

6 667620/18.2/31/44.1/47/135/Z 4/Feb/17Request for full substantiation as discussed within progress meeting


Further copy of Clause 8.3 Revised Programme previously submitted
7 SFBR-0025-6 5/Feb/17 under Interim EOT 1 - Appendix D
Contractor's request for Engineers determination of the EOT without
8 SFBR-0092-3 20/Apr/17 further delay.
Request for Contractor to complete format providing justification of
9 667620/18.2/31/47/198/Z 17/May/17 Claims including Contract Clause references
Submission of Engineer's format - Contractor's justification for the
10 SFBR-0092-4 25/May/17 claim
11 SFBR-0092-5 27/Aug/17Submission of Interim Extension of Time No. 2
Confirmation of receipt of Contractor's Interim Extension of Time No.
12 667620/18.2/31/47/275/Z 11/Sep/17 2
Notice of breach of Contract- Engineer's failure to provide approval
13 SFBR-0092-6 10/Oct/17 of EOT 1 & 2
Engineer's letter confirming the Contractors Interim EOT 1 & 2 are
14 667620/18.2/31/47/291/Z 10/Oct/17 currently under review
Reminder of durations set out in Sub-Clause 20.1 for Engineers
15 SFBR-0092-7 11/Oct/17 approval
Notice for commencement of the DAB procedures, as per Sub-Clause
16 SFBR-0092-8 19/Oct/17 20.2 of the Contract
Engineer's request for Contractor's approval to extend the period
17 667620/18.2/31/47/299/Z 19/Oct/17 permitting to the Engineer to 09 November 2017
Agreement to delay referral of Interim EOT 1 & 2 to DAB as per
18 SFBR-0092-9 23/Oct/17 request of the Engineer
Contractor request for Engineers determination of Interim EOT 1 & 2
19 SFBR-0092-10 14/Nov/17 with or without Employers approval

Minutes of Meeting - No. 66 on Minute 6.0 highlight's the Contractor's EOT is still under review(no
20 07/12/17 10/Dec/17 detail provided despite Contractor's requests at each meeting).