TAP PROJECT: ACS02 & ACS03

PIPING WORKS FLOWCHART

Check material against


certificates

Check ISO Drawings for availability of materials

Quality Control Documents .Final Shop inspection and


release to blast/paint shop or site

Quality Control Documents .Final inspection and


release to site

Quality Control Documents .Pipe erection complete,


release to blowing or blushing

Follow procedures, release to pressure test

Follow procedures, establish test certificate release to


drainage/blowing

Follow procedures, ITP

Follow procedures, ITP

Certify reinstatement complete, release for


painting/ heat tracing/insulation

Quality control documents, release for heat tracing /


insulation

Quality control documents


IF SPECIFIED

Quality control program