Tabel A.1

Properties Lumpur Pemboran Sumur “X-1”

Trayek
Mud Properties
36" 26" 17 1/2" 12 1/4" 8 1/2"
KCL KCL
Mud Sistem Gel Water Polimer Polimer OBM OBM
Kedalaman (m) ±40 ±350 ±1657 ±2467 ±3071
SG 1.03 - 1.04 1.05 - 1.17 1.17 - 1.26 1.2 - 1.88 1.21 - 1.8
Funnel Viscosity
(sec/quart) 40 - 43 46 - 49 45 - 56 63-130 62-132

PV (Cp) - 12 - 18 13 - 26 20 - 45 15 - 46
YP (lbf/100ft2) - 13 - 19 14 - 25 20 - 45 15 - 32
pH 9.5 9 - 9.5 8.5 - 9.5 - -
22000 - 35000 -
Chlorides (ppm) - 34000 52000 - -
Gel Strength 10
sec (lbf/100ft2) - 3-5 4-8 5 - 15 4 - 16
Gel Strength 10
min (lbf/100ft2) - 6 - 10 8 - 14 7 - 19 9 -30
Sand (%) - - 1 0.1 0.2
54

Tabel A.2

Properties Lumpur Pemboran Trayek 12 ¼”

Parameter Perencanaan Aktual


Mud Weight (ppg) 1.8 – 2 1.6 – 1.88
Funnel Viscosity (sec/qt) 90 – 130 63 – 130
Plastic Viscosity (cP) 30 – 43 25 – 45
Yield Point (lbs/100ft²) 15 – 25 18 – 45
Excess Lime (ppb) >3 2.6 – 2.86
Gel Strength 10’ (lbs/100ft²) 10 – 15 5 – 15
Gel Strength 10” (lbs/100ft²) 15 – 28 7 – 19

Tabel A.3

Aktual Biaya Material Lumpur Trayek 12 ¼”

Material Kapasitas Total Unit Harga (US$) Total Harga (US$)


Barite 100 lb/sax 18050 19.38 349.809
Geltone 50 lb/sax 201 132 26.532
Drilltreat 55 gal/drm 14 412 5.768
Primary 55 gal/drm 33 818.4 27.007,2
Secondary 55 gal/drm 19 941.6 17.890,4
H-Lime 25 kg/sax 160 12.88 2.060,8
Duratone 50 lb/sax 115 106.7 12.270,5
CaCl2 25 kg/sax 120 18.03 2.163,6
OMC 55 gal/drm 6 700 4.200
Total biaya material 447.701,5
Biaya material / bbl 148,5
55

Tabel A.4

Rincian Biaya Sewa Rig (NPT)

NPT Sewa/jam Biaya


Proses (jam) (US$) (US$)
Mixing lumpur naikkan SG dari 1.05 ke 1.88
5.0
sebanyak 200 bbls. 1546.87 7734.35
Cabut rangkaian casing 9-5/8” dari 1651 m. Spider
slip tidak dapat dibuka. Angkat 1 jts casing. 2.5
Laydown spider slip. NPT Indokaya Energi 2.5 jam. 1546.87 3867.175
Lanjut laydown 1 jts casing 9-5/8” + spider slip. 2.5 1546.87 3867.175
Cabut rangkaian casing 9-5/8” dari 1651 m sampai
16.5
577 m. 1546.87 25523.355
Lanjut cabut rangkaian casing 9-5/8” dari 577 m
9.0
sampai permukaan. 1546.87 13921.83
Ganti ram BOP 5”. Persiapan masuk rangkaian OE
3.0
DP 5”. 1546.87 4640.61
Masuk rangkaian OE DP 5” sampai 2473 m. 8.5 1546.87 13148.395
Sirkulasi kondisikan lumpur sambil turunkan gas
2.0
dan observasi dinamik loss. 1546.87 3093.74
PJSM. Penyemenan plug interval 2474 m – 2444 m.
1.5
Pressure test cementing line 3000 psi/ 5 menit. 1546.87 2320.305
Lanjut Penyemenan interval 2474 m – 2444 m.
Displace dengan 139.5 bbls lumpur, SG 1.88. Cabut 2.5
6 joints OE DP 5” sampai 2412 m. 1546.87 3867.175
Cabut rangkaian OE DP 5” dari 2412 m sampai
4.5
Casing shoe 13-3/8” @1656 m. 1546.87 6960.915
Geser drilling line 7 m. 1.0 1546.87 1546.87
TSK. 10.5 1546.87 16242.135
Masuk rangkaian OE DP 5” dari 1656 m sampai
3.5
2473 m. Tidak ditemukan top of cement. 1546.87 5414.045
Persiapan penyemenan plug ulang interval 2474 m
2.0
– 2424 m. 1546.87 3093.74
PJSM. Penyemenan plug ulang interval 2474 m –
2424 m. Pressure test cementing line 3000 psi/ 5 2.0
menit. 1546.87 3093.74
Sirkulasi lurus 1x bottom up dengan GPM 300 SPP:
2.0
680 psi, observasi dynamic loss, baik. 1546.87 3093.74
Cabut rangkaian OE DP 5” dari 2324 m sampai
8.0
permukaan. 1546.87 12374.96
Persiapan dan masuk rangkaian PDC 12” + BHA
rotary sambil TSK. Jajak puncak semen @ 2420 m, 9.5
duduk 3 ton. 1546.87 14695.265
Bor semen dari 2420 m sampai 2431 m. 1.0 1546.87 1546.87
56

Tabel A.4
(Lanjutan)

Lanjut bor semen dari 2431 m sampai 2469 m. 5.0 1546.87 7734.35
Sirkulasi bersih sambil observasi dynamik loss,
baik. Swept out hi-vis 25 bbls. Observasi statik loss, 2.0
baik. 1546.87 3093.74
Cabut rangkaian PDC 12” + BHA rotary dari 2469 m
10.0
sampai permukaan. 1546.87 15468.7
Ganti BOP ram 9-5/8”. 2.0 1546.87 3093.74
PJSM. Persiapan masuk rangkaian Casing 9-5/8”. 2.0 1546.87 3093.74
Masuk rangkaian Casing 9-5/8” sampai 152 m. 3.0 1546.87 4640.61
Total Biaya Sewa Rig (NPT) 187171.27