Sei sulla pagina 1di 71

BCA-GeoSS Seminar on Use of Rapid Load Test for Pile Foundation

RAPID LOAD TESTING


- JAPAN EXPERIENCES -
Tatsunori MATSUMOTO
Kanazawa University, Japan

Contents
1. Introduction
2. History of RLT in Japan & Standards
3. RLT devices used in Japan
4. RLT cases including interpretation methods
5. Summary
1/
INTRODUCTION
Background (in 1990s)
Estimation of bearing capacity of piles has been mainly
based on empirical equations using SPT N-value in Japan .
Displacement (settlement) of a pile at working load is
scarcely considered in pile design, because a high factor of
safety, usually 3, is employed.
Situations in which bearing capacity and pile head stiffness
of piles having the same configuration vary widely even in a
narrow area, are often encountered.

In order to precisely estimate bearing characteristics of


many piles in a pile construction site, increase in the
number of pile load tests in the construction site is vital.

However, cost and time for the conventional static pile


load test have hindered such practice.
2/
Japanese experiences of
Statnamic test
 First Statnamic test May 1992
 69 Statnamic tests 39 sites until 1998

 Research Group 1993


 Research Committee in JGS 1997
 Standardization Committee in JGS 1998

3/
Research group in 1993
general contractors, piling contractors,
pile load test companies, pile
manufactures, academic
Objectives
 compile the existing knowledge
 examine basic characteristics and
applicability to Japanese soil
 establish interpretation methods

 research of 3 years, Final report Dec. 1996


4/
Research Committee
 Japanese Geotechnical Society in 1997

Research targets
 Definition of rapid load test
 Interpretation methods
 Testing manual
 Standard testing method

5/
Standardization Committee
(started in 1998 in JGS)
 Static compressive load test
 Static tensile load test

 Osterberg Cell method

 Dynamic load test

 Rapid load test

 Published in 2002

6/
7/
Methods for Rapid Load Test of Single Piles (JGS 1815-2002)
1. GENERAL 4. TEST EQUIPMENT
1.1 Scope 4.1 Composition of test equipment
1.2 Objectives of test 4.2 Loading devices
1.3 Terminology 4.3 Measurement devices
4.4 Reference points
2. BASIC PLANNING
2.1 Basic items 5. METHOD OF LOADING AND
2.2 Planner maximum load MEASUREMENTS
2.3 Planned loading duration 5.1 Loading pattern
2.4 Specification, number and 5.2 Items to be measured
location of test piles 5.3 Sampling periods and intervals
2.5 Method of loading and
measurements 6. EXECUTION OF TEST
6.1 Testing personnel
3. TEST PREPARATION 6.2 Tasks of the testing personnel
3.1 Preparation of execution plan 6.3 Commencement and completion
3.2 Design of test piles of the test
3.3 Installation and curing of test piles 6.4 Test record
3.4 Setting up test equipment and test
site 7. SUMMARY OF TEST RESULTS

8/
Definition of Rapid Load Test
The relative loading time Tr, which is an index for
classification in the rapid loading test, is defined as:

Pile head force


𝑇r = 𝑡L /(2𝐿/𝑐) ≥ 5
tL = the load duration,
L = the pile length,
c = the bar wave velocity

Loading duration, tL Time


If Tr ≥ 5,
 wave propagation phenomena in the pile is negligible.
 pile can be modelled as a single mass.
 simplified interpretation methods can be employd.

9/
Various pile load test methods Rapid load test (RLT)

Launching mass type:


Statnamic (Berminghammer, Canada & TNO, NL)

The first Statnamic test in Japan was carried out by Takenaka


Komuten Corp. in 1991.
More than 300 Statnamic tests have been carried out in Japan.

Falling mass type:


Dynatest (France), Psuedo-static (Fundex, NL)
Soft cushion, Spring hammer (in Japan).

10/
Dynatest Statnamic test Pseudo-static load test
(Gonin & Leonard 1984) (Bermingham & (Schellingerhout &
Janes 1989) Revoort 1996).

11/
Statnamic test in Kanazawa in 2001
Steel pipe pile for foundation of a bridge of Shinkan-sen (bullet) train
12/
Statnamic (video)
(Launching mass type)
13/
Sakoyama bridge

14/
Maizuru
thermal
power plant

15/
SpringHammer (Kanazawa Univ.) video
Falling mass type
16/
SpringHammer (Kanazawa Univ.) video
Falling mass type
17/
SPRING HAMMER TEST METHOD
Test device, and signal measuring and acquisition system

Loading and measuring system of SH rapid load test.


18/
SPRING HAMMER TEST METHOD
Test procedure

19/
SPRING HAMMER TEST METHOD
Non-linear Damping Interpretation Method

20/
Hybridnamic (Jibanshikenjo Co., Ltd.)
Falling mass type
21/
Hybridnamic (Jibanshikenjo Co.)
Falling mass type 22/
Hybridnamic (Jibanshikenjo Co.) Falling mass type (Video)
23/
Advantages of each rapid load test type

Launching mass type (Statnamic)


High loading capacity: 60 MN

Falling mass type


Repeatable blows with increasing applied load

24/
Advantages of the rapid load test over other test types
1. The test is quick and easily executed. Poulos (1998)
2. High loading capacity is available. 2nd STN Seminar

3. The loading is accurately centered and can be applied to both


single piles and pile groups.
4. The test does not require any pre-installation of the loading
and reaction equipment.
5. The test is quasi-static, and does not involve the development
of potentially damaging compressive and tensile stresses in
the test pile.
6. The test can be carried out on both uninstrumented and
instrumented piles.
7. The load is measured via a load cell and does not rely on pile
material and cross-section properties.

25/
Methods of Interpretation of RLT signals
Force (MN)
Unloading Point Method (ULP method) F u(max) F soil(max)
0 1 2 3 4 5
0
Frapid

Didsplacment, w (mm)
F soil
10

Pile mass, m
20
FstatF u
Soil spring,K Dashpot, C 30

(Fstat) (F dyn) w max


C v*
40
Unloading point
(v=0)
50

Frapid = ma + Fsoil = ma + Fdyn + Fstat


Fsoil = Fdyn + Fstat = Frapid - ma
m = pile mass
Fdyn = Cv a = pile acceleration:
v = pile velocity
Fstat = Frapid - ma - Fdyn
26/
Case 1 (1/5): Hybridnamic rapid load tests for cast-in-situ piles in sandy gravel soil
(Aoki et al., IS-Kanazawa 2012)

D = 1.0 m
L = 11.5 m

Site 1: Takaoka Site 2: Imizu D = 1.0 m


L = 16.5 m
Soil profile and test pile
27/
Case 1 (2/5): Hybridnamic rapid load tests for cast-in-situ pile in sandy gravel soil

D = 1.0 m
L = 11.5 m
Site 3: Oyabe

Soil profile and test pile

28/
Case 1 (3/5): Hybridnamic rapid load tests for cast-in-situ pile in sandy gravel soil

Hybridnamic (Jibanshikenjo Co., Ltd.)

29/
Case 1 (4/5): Hybridnamic rapid load tests for cast-in-situ pile in sandy gravel soil

Site 1: Takaoka Site 2: Imizu Site 3: Oyabe


L = 11.5 m L = 16.5 m L = 11.5 m
𝑇r = 𝑡L /(2𝐿/𝑐) = 12 𝑇r = 𝑡L /(2𝐿/𝑐) = 8 𝑇r = 𝑡L /(2𝐿/𝑐) = 12
30/
Case 1 (5/5): Hybridnamic rapid load tests for cast-in-situ pile in sandy gravel soil
F0,S0 Comparison of matching analysis and
F1,S1 sequential unloading point method
Site Analysis Static shaft Static toe
F2,S2 resistance resistance
(kN) (kN)
1. Takaoka Matching 4,398
Analysis
8,272
FN,SN
Sequential 3,202
U. P. M.
9,468
2. Imizu Matching 2,238
Analysis
12,121
Sequential 2,606
F0 F1 F2 FN
U. P. M.
11,753
3. Oyabe Matching 8,718
Analysis
13,042
S0 S1 S2 SN Sequential
11,773 9,987
U. P. M.
Sequential Unloading point method

The results from the Sequential Unloading Point method


are comparable to those from the wave matching analysis.

31/
Case 2 (1/5): Rapid load test for cast-in-place concrete pile sat on a thin bearing layer
(Kojima et al., IS-Kanazawa 2012)

N-value
0 10 20 30 40 50 60
OP+4.70m
5
first section
OP+2.46m

gravel
strain gauge
0
2 points

second section

23.2m
silt cohesive sandy
-5 OP-6.54m

clay
depth(OP-m)
strain gauge
2 points
test pile -10

soil
boring
-15 third section
OP-17.5m
cast-in-place concrete pile 1500 strain gauge

gravel
number=40/silo -20 4 points
φ1.5m

cohesive
soil
-25 strain gauge
accelerometer
-30

Side view of the petroleum coke silo,


Profiles of SPT N-values and soil
and plan view of pile arrangement
layers, together with the test pile
seating

32/
Case 2 (2/5): Rapid load test for cast-in-place concrete pile sat on a thin bearing layer
2,100mm

Frame

7,600mm
Hammer
mass
20 t Elastic rubber cushion
Computer, Laser projector
Conditioner
Load cell
Laser displacement sensor Test pile
7,000mm

Illustration of FT-Impact test device and measurement system


(Fugro Japan & Tama Blasting Co.)
33/
Case 2 (3/5): Rapid load test for cast-in-place concrete pile sat on a thin bearing layer

Force, Frapid (MN)


Force, Frapid (MN) 6 6
Blow No. 1 Blow No. 5
4 4

2 2

0 0
4 4

Disp., w (mm)
Disp., w (mm)

3 3

2 2

1 1

0 0
0.3

Velocity, v (m/s)
0.3
Velocity, v (m/s)

0.2 0.2
0.1 0.1
0.0 0.0
-0.1 -0.1
-0.2 -0.2
-0.3 -0.3
30 30

Acc., a (m/s )
20

2
20
Acc., a (m/s )
2

10 10
0 0
-10 -10
-20 -20
-30 -30
0 50 100 150 200 0.00 0.05 0.10 0.15 0.20
Time, t (ms) Time, t (ms)

Blow No.1, H = 0.3 m Blow No.5, H = 1.1 m


Examples of measured dynamic signals
34/
Case 2 (4/5): Rapid load test for cast-in-place concrete pile sat on a thin bearing layer

10000 10000
Frapid1 Frapidtoe1
Rsoil1 Rsoiltoe1
8000 8000

Axial force, Fa(kN)


Axial force, F(kN)

Frapid2 Frapidtoe2
Rsoil2 Rsoiltoe2
6000 Frapid3 6000 Frapidtoe3
Rsoil3 Rsoiltoe3
Frapid4 Frapidtoe4
4000 Rsoil4 4000 Rsoiltoe4
Frapid5 Frapidtoe5
Rsoil5 Rsoiltoe5
2000 RULP 2000 RULPtoe

0 0
0 1 2 3 4 5 6 0 1 2 3 4 5 6
Dispplacement, W(mm)
Displacement, w (mm) Displacement, W(mm)
Displacement, w (mm)

Load-displacement curves at Load-displacement curves at


pile head pile tip

35/
Case 2 (5/5): Rapid load test for cast-in-place concrete pile sat on a thin bearing layer
Axial force, F (MN)
The bearing capacity, Ru, of the
0 1 2 3 4 5 6 7 test pile was estimated from SPT
5 N-values using empirical
equations specified in
Depth from O.P. (m)

0 Recommendations for Design of


Building Foundations (AIJ, 2001)
as follows:
-5
1st End-bearing capacity
2nd Rp = 4,980 kN
-10 3rd
4th Shaft friction capacity
5th Rf = 5,391 kN
-15
Ultimate capacity
Ru = Rp + Rf = 10,371 kN
0 Axial
1000 force
2000 3000distributions
4000 5000 6000 7000
From the rapid load test, Rp = 1 MN and Rf = 5 MN.
Pile load test results are much more reliable then
codes or standards. 36/
Case 3: A Comparison between Static Load Test and Rapid Load Test for Steel
Pipe Pile Installed by Water Jet Vibratory Technique
(Hoshino., IS-Kanazawa 2012)

Sandy
silt

Sand
rock
Static load test equipment
Sand Steel pipe pile
rock D = 1.0 m
L = 15.5 m
tw = 14 mm
Soil property and test pile
37/
Case 3 (2/7): Comparison between SLT and RLT for SPP Installed by Water Jet
Vibratory Technique

Static load test


10000

8000

6000
Load :P(kN)

4000

2000

0
0 1 2 3 4 5 6 7 8
Time :t(hour)

Load step sequence Pile head load vs. displacement

38/
Case 3 (3/7): Comparison between SLT and RLT for SPP Installed by Water Jet
Vibratory Technique
Static load test
Water pressure (Mpa) Axial force P (kN) Shaft resistance τ (kN/m2)
0 5 10 15 0 2000 4000 6000 8000 10000 0 200 400 600 800
0 0 Water pressure (Mpa) 0 force P (kN)
Axial Shaft
0 5 10 15 0 2000 4000 6000 8000 10000 0 200
0 0 0

2 2 2

2 2 2

4 4 4

4 4 4

6 6 6

6 6 6

Depth (m)
DEpth (m)
8 8 8

Depth (m)
DEpth (m)
Depth (m)

8 8 8

Depth (m)
10 10 10

10 10 10

12 12 12

12 12 12

14 14 14

14 14 14
1000kN 2000kN 3000kN 4000kN 5000kN
16 16 16 6000kN 7000kN 8000kN 9000kN
1000kN 2000kN
16 16 16 6000kN 7000kN

18

18

Axial force and shaft resistance distributions


from SLT

39/
Case 3 (4/7): Comparison between SLT and RLT for SPP
8000

Rapid load test 7000 Section 1


Section 2
6000 Section 3
Section 4
5000 Section 5

Load (kN)
4000

3000

2000

1000

0
0.1 0.12 0.14 0.16 0.18 0.2 0.22 0.24
Time(sec)

Rapid load vs. time


12000

10000
Soil resistance Rsoil(kN)

8000

6000

4000
Hybridnamic 2000
(Jibanshikenjo Co., Ltd.) 0
0 10 20 30 40
Displacement (mm)

Load vs. displacement 40/


Case 3 (5/7): Comparison between SLT and RLT for SPP

SLT & RLT


10000

Static load test


Rapid load test
8000
Static soil resistance (kN)

6000

4000

2000

0
0 20 40 60 80 100
Displacement (mm)

Comparison of load vs. displacement from SLT and RLT

41/
Case 3 (6/7): Comparison between SLT and RLT for SPP

SLT & RLT


10000
10000

Static load test Static load test


Rapid load test Rapid load test
8000 8000
Static soil resistance (kN)

Static soil resistance (kN)


6000
6000

4000

4000
2000

0 2000
0 20 40 60 80 100
Displacement (mm)
0
0 20 40 60 80 100
Displacement (mm)

Comparison of load vs. displacement


from SLT and RLT

42/
Case 3 (7/7): Comparison between SLT and RLT for SPP

SLT & RLT


0 0

SLT
2 2
RLT
SLT
4 RLT 4

6 6
Depth (m)

8 8

10 10

12 12

14 14

0 2000 4000 6000 8000 10000 0 200 400 600 800


2
Axial force (kN) Shaft resistance (kN/m )

Distributions of the axial forces and the shaft


resistance from SLT and RLT

43/
Case 4 (1/3): A rapid load test for the long steel pipe pile installed into the soft
rock under the soft silty ground (Kato et al., 48JGS Conf. 2013)

A bridge of Tohoku-Chuo Highway, Japan


South North
Bridge section

Test pile (SPP) Soft soils


D = 800 mm
L = 86.5 m
Elevation (m)

Soft soils

Soft rock

Soil profile and test pile


44/
Case 4 (2/3): RLT for the long steel pipe pile on the soft rock under the soft silty
ground

Pile head load (kN)


Pile head displacement (mm)

Pile tip load (kN)

Hybridnamic
(Jibanshikenjo Co., Ltd.)

Pile tip displacement (mm)


45/
Case 4 (3/3): A rapid load test for the long steel pipe pile installed into the soft
rock under the soft silty ground
Axial force (MN) Shaft resistance (kPa)
0 5 10 15 0 100 200 300
0

20

40

Emprical design
Emprical
60 design

80
m

Axial forces Shaft resistance


46/
Case 4 (3/3): A rapid load test for the long steel pipe pile installed into the soft
Conducting (Rapid)
rock under load
the soft silty groundtest is very important.
Axial force (MN) Shaft resistance (kPa)
0 5 10 15 0 100 200 300
0

20

40

Emprical design
Emprical
60 design

80
m

Axial forces Shaft resistance


47/
Case 5 (1/3): Rapid load tests on steel pile having screwed wing plate
(Takano et al., 49JGS Conf. 2014)

9.7 m

D = 191 mm
Dw = 381 mm
L = 11.3 m

Hybridnamic
(Jibanshikenjo Co., Ltd.) Soil profile and test pile
48/
Case 5 (2/3): Rapid load tests on steel pile having screwed wing plate

Test pile No.1


Pile V1 RLT Pile V1 SLT & RLT
1200 1200

1000 1000
Pile head load (kN)

Pile head load (kN)


800 800
SLT
600 600 RLT

400 400

200 200

0 0
0 20 40 60 80 0 40 80 120 160 200
Pile head disp. (mm) Pile head disp. (mm)

RLT results Results of SLT and RLT

49/
Case 5 (3/3): Rapid load tests on steel pile having screwed wing plate

Test pile No.2


Pile V2 RLT Pile V2 SLT & RLT
1200 1200
RLT
1000 1000
Pile head load (kN)

Pile head load (kN)


800 800
SLT
600 600

400 400

200 200

0 0
0 20 40 60 80 0 40 80 120 160 200
Pile head disp. (mm) Pile head disp. (mm)

RLT results Results of SLT and RLT

Results from the SLTs and the RLTs were almost equal.

Performance of a new type of pile was successfully


estimated by RLT.
50/
Case 6 (1/4): Rapid load tests on steel pipe piles for foundation of a wharf
(Minami et al., 50JGS Conf. 2015)

D = 1.3 m CJV WJV D = 1.3 m


(Vibro-hammer with (Vibro-hammer with L = 21.0 m
L = 24.5 m cement milk jetting) water jetting)
t = 17 mm t = 19 mm

SPPs for foundation of a wharf


51/
Case 6 (2/4): Rapid load tests on steel pipe piles for foundation of a wharf

Hybridnamic
(Jibanshikenjo Co., Ltd.)
52/
Case 6 (3/4): Rapid load tests on steel pipe piles for foundation of a wharf
(Vibro-hammer with water jetting) (Vibro-hammer with cement milk jetting)
1200 1200
WJV CJV
1000 1000

Pile head load (kN)


Pile head load (kN)

800 800

600 600

400 400

200 200

0 0
0 5 10 15 20 25 30 35 0 5 10 15 20 25 30 35
Pile head disp. (mm) Pile head disp. (mm)

Pile head load vs pile head displacement from RLT

53/
Case 6 (4/4): Rapid load tests on steel pipe piles for foundation of a wharf

Axial force of pile (MN) Axial force of pile (MN)


0 2 4 6 8 10 0 2 4 6 8 10
5 5
WJV CJV

0 0 Although the
embedment length is
Depth from sea level (m)

Depth from sea level (m)


-5 -5
less for CJV pile, larger
shaft resistance can be
expected in CJV pile.
-10 -10

-15 -15

-20 -20

-25 -25
WJV CJV
Axial forces in piles
54/
Performances
Case 6 (4/4): Rapidof SPPs
load constructed
tests on byfordifferent
steel pipe piles foundationmethods
of a wharf were
successfully obtained from RLTs.
Axial force of pile (MN) Axial force of pile (MN)
0 2 4 6 8 10 0 2 4 6 8 10
5 5
WJV CJV

0 0
Depth from sea level (m)

Depth from sea level (m)


-5 -5

-10 -10

-15 -15

-20 -20

-25 -25
WJV CJV
Axial forces in piles
55/
Case 7 (1/10): Load tests on cast-in-place concrete piles for foundation of New
Nile Bridge at Jinja (Takano et al., 50JGS Conf. 2015)

Jinja Bridg e

Total length 525 m

Cable stayed bridge


56/
Case 7 (2/10): Load tests on cast-in-place concrete piles for foundation of New
Nile Bridge at Jinja (Takano et al., 50JGS Conf. 2015)

Pile

Soil profile at Pier No. 2


57/
Case 7 (3/10): Load tests on cast-in-place concrete piles for foundation of New
Nile Bridge at Jinja (Takano et al., 50JGS Conf. 2015)

RLT p
i
l
e
f
o
SLT pile r
S
L
SLT T

Pile arrangement at Pier No. 2


Piles at Pier No. 2 Piles at Abutment No. 1
Cast-in-place concrete pile Cast-in-place concrete pile
D = 2.0 m D = 1.5 m
L = 19.4 m L = 23.0 m
58/
Case 7 (4/10): Load tests on cast-in-place concrete piles for foundation of New
Nile Bridge at Jinja (Takano et al., 50JGS Conf. 2015)
D = 1.5 m
L = 23 m Hammer
D = 2.0 m
L = 19.4
Cushion
Load cel l Accel. meter
Strain gauge

Strain
gauge

Pile

Accel. meter
Strain gauge

Equipments for RLT

Pier No.2 Abutment No.1

Soil profile and test pile

59/
Case 7 (5/10): Load tests on cast-in-place concrete piles for foundation of New
Nile Bridge at Jinja (Takano et al., 50JGS Conf. 2015)

25
Pile head
Pile tip Pier No. 2
20

Pile head load (MN)


15

10

0
0 0.5 1.0 1.5 2.0 2.5 3.0 3.5 4.0
Pile head displacement (mm)

Load vs. displacement from RLT

RLT signals of pile at pier


60/
Case 7 (6/10): Load tests on cast-in-place concrete piles for foundation of New
Nile Bridge at Jinja (Takano et al., 50JGS Conf. 2015)

Axial force of pile (MN) Shaft resistance (kPa)


25
0 5 10 15 20 25 0 1000 2000
Pier No. 2 0
20
Pile head load (MN)

Depth from G.L. (m)


15 -5

10
-10

5 Emprical eq.
-15
0
0 0.5 1.0 1.5 2.0 2.5 3.0 3.5 4.0
Pile head displacement (mm) -20

Load vs. displacement from RLT Axial forces and shaft resistance
from RLT

61/
Case 7 (7/10): Load tests on cast-in-place concrete piles for foundation of New
Nile Bridge at Jinja (Takano et al., 50JGS Conf. 2015)

25 12

Pier No. 2
10 Abut. No. 1
20
Pile head load (MN)

Pile head load (MN)


8
15
6
10
4

5 2

0 0
0 1.0 2.0 3.0 4.0 5.0
0 0.5 1.0 1.5 2.0 2.5 3.0 3.5 4.0
Pile head displacement (mm)
Pile head displacement (mm)

Load vs. displacement from RLT

62/
Case 7 (8/10): Load tests on cast-in-place concrete piles for foundation of New
Nile Bridge at Jinja (Takano et al., 50JGS Conf. 2015)

35
30 Pile in Piear No.2
Load (MN)

25 Pile in Abut. No.1


20
15
10
5
0
0 20 40 60 80
Time (hour)
Loading steps employed in SLT

63/
Case 7 (9/10): Load tests on cast-in-place concrete piles for foundation of New
Nile Bridge at Jinja (Takano et al., 50JGS Conf. 2015)

35 9

8
30 Pile tip

Pile head load (MN)


Pile head load (MN)

7
25
6
Pile head
20 5

15 4

3
10
Pier No. 2 Abut. No. 1
2
5
1

0 0
0 2 4 6 8
0 1 2 3 4 5 6
Pile
Piledisplacement (mm)
head dsp. (mm) Pile head displacement (mm)

Load vs displacement from SLT

64/
Case 7 (10/10): Load tests on cast-in-place concrete piles for foundation of New
Nile Bridge at Jinja (Takano et al., 50JGS Conf. 2015)

35

30

Pile head load (MN)


25

20

15

10

0
0 1 2 3 4 5
Pile head disp. (mm)
Load vs displacement from SLT and RLT
65/
Case 8 (1/3): Statnamic tests on open-ended steel pipe piles for the foundation of
a bridge in Yangon, Myanmar (Tama Blasting Company, 2016)

P1 EL(m)
P2
0.0
EL(m)
0.0
Strain gauge D = 1.2 m Strain gauge D = 1.2 m
Acceleration
Acceleration
tw = 14 mm tw = 14 mm
SAND-Ⅰ
CLAY-Ⅰ
L = 48 m -10.0 N=0~10 L = 40 m
N=0~3

P2 40m
-10.0

Design capacity
P1 48m

CLAY-Ⅱ Design capacity -20.0 CLAY-Ⅱ


-20.0
N=5~50
= 13.5 MN
N=5~10
= 13.7 MN

SAND-Ⅱ
-30.0
-30.0 N=10~25
SAND-Ⅱ
N=20~50
-40.0 CLAY-Ⅲ
-40.0 N=25~50

CLAY-Ⅲ
N=20~50 -50.0
-50.0
SAND-Ⅲ SAND-Ⅲ
N=50 N=50
-60.0
-60.0

66/
Case 8 (2/3): Statnamic tests on SPP
P1_Top
for the foundation of a bridge in Yangon
25000
25
rapid (MN)

20000
20
P1
Force, FForce(kN)

15000
15
10000
10
5000
5
0

100
100
75
75
(mm)
Disp.(mm)

Wmax
50
50
Disp.

25
25
00

44
(m/s)

22
Velo.(m/sec)

00
Veloc.

-2
-4

400
400
Load vs displacement from ULPM
Acc.(m/sec2)
(m/s2)

200
200
P1
0
Acc.

-200
-200
D = 1.2 m
-400
-400
0.0
0 50 0.1
100 150 0.2
200 250 0.3
300
tw = 14 mm
Time(sec)
Time, t (ms)
L = 48 m
Design capacity = 13.5 MN
Measured dynamic signals of P1
67/
Case 8 (3/3): Statnamic tests on SPP for the foundation of a bridge in Yangon

P2

Load vs displacement from ULPM


P2
D = 1.2 m
tw = 14 mm
L = 40 m
Design capacity = 13.7 MN
Measured dynamic signals of P2
68/
Safety factors for piles in various countries (as in 2006)
Country S. F. S. F. S. F. Number of load tests required in a site and notes
w/o LT with SLT with DLT
Japan 3.0 2.7 2.7 not specified, number load tests is not taken into account.
Kazakhstan 1.5 1.2 ----- SLTs on 1% of constructed piles (2 SLTs at least in a site)
Mexico 3.0 2.0 2.0 to 2.5 Between 1% to 5% depending the project. Minimum 3 piles.
Netherelands 2.05 ----- pile design based on CPT
1.78 pile design based on CPT
1.71
Norway 1.6 1.4 1.4 not specified
Singapore 3.0 when there is less certainty of the value of the ultimate capacity.
2.0 where the ultimate has been determined by a number of loading
tests or where they may be justified by local experience.
Sweden 3.0 ?
1980 2.5 if 5% of piles are tested.
2.0 if 25% of piles are tested.
Sweden 2.0 if 25% of piles are tested.
2000 1.6 if 100% of piles are tested.
USA 3.0 theoretical or empirical prediction
ASCE 1996 1.6 to 1.9 1.7 to 2.0 in case of design capacity is 0.4 to 1.0 MN.
1.8 to 2.2 2.0 to 2.4 in case of design capacity is over 1.0 MN.
Vietanam not ≥2 2 2 tests at least, normally 1% of piles and maximum is 2% of piles.
specified

69/
Safety factors for piles in various countries (as in 2006)
Country S. F. S. F. S. F. Number of load tests required in a site and notes
w/o LT with SLT with DLT
Japan 3.0 2.5 2.5 not specified, number load tests is not taken into account.
Kazakhstan 1.5 1.2 ----- SLTs on 1% of constructed piles (2 SLTs at least in a site)
Mexico 3.0 2.0 2.0 to 2.5 Between 1% to 5% depending the project. Minimum 3 piles.
Netherelands 2.05 ----- pile design based on CPT
1.78 pile design based on CPT
1.71
Norway 1.6 1.4 1.4 not specified
Singapore 3.0 when there is less certainty of the value of the ultimate capacity.
2.0 where the ultimate has been determined by a number of loading
tests or where they may be justified by local experience.
Sweden 3.0 ?
1980 2.5 if 5% of piles are tested.
2.0 if 25% of piles are tested.
Sweden 2.0 if 25% of piles are tested.
2000 1.6 if 100% of piles are tested.
USA 3.0 theoretical or empirical prediction
ASCE 1996 1.6 to 1.9 1.7 to 2.0 in case of design capacity is 0.4 to 1.0 MN.
1.8 to 2.2 2.0 to 2.4 in case of design capacity is over 1.0 MN.
Vietanam not ≥2 2 2 tests at least, normally 1% of piles and maximum is 2% of piles.
specified

70/
Summary

Rapid load testing of falling mass type is widely used for


piles in Japan, as an alternative of the conventional
static load test.

Pile load tests are carried out to confirm the design


bearing capacity, and/or to obtain parameters for pile
design.

71/

Potrebbero piacerti anche