2 Local materials
Brick 15 no
Sand 2000 m3
Agreegate 2100 m3
Gravel 1000 m3
Stone 1600 m3
3 Foraign materials
OPC cement 18 kg
PPC cement 17.5 kg
Rebar 90 kg
Binding wire 90 kg
Nails 100 m2
10 mm plyboard 915 m2
12 mm plyboard 1025 m2
19 mm plyboard 1350 m2
Sunmica 275 m2
Foremica 6 mm 850 m2
RATE ANALYSIS
Project: Gorkha Garden
Location: Gorkha
Item :- 20 mm thick cement sand plaster 1:3 ( For 100 m2)
Norms - Page
SN Description Unit Quantity Unit Rate Amount(NRs) Remarks
A Labour
1 Skilled Man/day 14.000 815.00 11410.00
2 Unskilled Man/day 19.000 580.00 11020.00
Sub total 22430.00
B Materials
1 Cement IS standard PPC kg 960.000 19.00 18240.00
2 Sand m3 1.950 2000.00 3900.00
3 Water ltr 576.000 0.20 115.20
4 Scafolding m2 100.000 130.00 13000.00
Sub total 35255.20
Equipment and plant l/s 1.000 1000.000 1000.00
Sub total 1000.00
Total 58685.20
15% Contractor overhead
C and profit 8802.780
Total without Vat 67487.980
D 13% Vat 8773.437
Grand total 76261.42
References :
District Rate 2074/2075 Chitawan
Norms
BOQ
Eco Builders Pvt. Ltd.
Khairahani, Chitwan
RATE ANALYSIS
Project: Gorkha Garden
Location: Gorkha
Supplying and applying of Water poofing SBR2 Polymer chemical (Double coat) with cement grouting of
25kg pressure at spots and necessary finishing as per specification and instruction of site engineer
References :
District Rate 2074/2075 Chitawan
Norms
BOQ
.
Remarks
per sft.