REVIEW LEVELS

THERE ARE THREE REVIEW LEVELS AS PER THE CONTRACT VOLUME 2 SECTION VII CLAUSE 3.3.6 MONITORING AND IN CASE AN “ALARM LEVEL” IS REACHED OR LIKELY TO BE REACHED, ALL WORK SHALL BE SUSPENDED WITHIN 30 METRES (OR
REPORTING. AS REQUIRED) OF THE INSTRUMENT/OR AFFECTED PORTION OF THE WORKS. THE CONTRACTOR SHALL IMMEDIATELY
IMPLEMENT THE MEASURES AS DEFINED IN THE CONTINGENCY/EMERGENCY PLANS TO MAKE THERELATED PART OF THE
1. ALERT LEVEL
WORKS SAFE AND CONTROL THE SITUATION. THE CONTRACTOR SHALL PROVIDE A REPORT DETAILING THE FULL HISTORY OF
2. ACTION LEVEL MOVEMENTS (OR OTHER RELEVANT PARAMETERS) AND AN INTERPRETATION OF EVENTS TO THE ENGINEER. TO RESUME THE
SUSPENDED WORK, THE CONTRACTOR SHALL DEMONSTRATE TO THE SATISFACTION OF THE ENGINEER THAT IT IS SAFE TO
3. ALARM LEVEL DO SO. THE SUSPENDED WORK SHALL ONLY BE RESUMED BY THE CONTRACTOR AFTER A NOTICE OF NO OBJECTION HAS
BEEN OBTAINED FROM THE ENGINEER.

"ALERT LEVEL" SHALL INITIALLY BE SET AS 0.5 TIMES THE SERVICEABILITY LIMIT VALUE DEFINED FOR THE MONITORED
EBS/INSTRUMENT/PARAMETER FOR GEOTECHNICAL AND BORED TUNNEL WORKS/PARAMETER AND CONTROL PARAMETER
FOR NATM WORKS.

MINIMUM NUMBER OF MONITORING INSTRUMENTS FOR BUILDINGS AND STRUCTURES:


"ACTION LEVEL" SHALL BE SET AT 0.8 TIMES THE SERVICEABILITY LIMIT VALUE DEFINED FOR THE MONITORED
EBS/INSTRUMENT/PARAMETER FOR GEOTECHNICAL AND BORED TUNNEL WORKS/PARAMETER AND CONTROL PARAMETER MINIMUM NUMBERS OF INSTRUMENTS FOR STRUCTURES*
FOR NATM WORKS. BUILDING OPTICAL
TILT CRACK TAPE VIBRATIONS
DESCRIPTION SETTLEMENT METERS SURVEY
"ALARM LEVEL" SHALL INITIALLY BE SET AT THE SERVICEABILITY LIMIT VALUE DEFINED FOR THE MONITORED METERS EXTENSOMETERS SENSORS
MARKERS TARGETS
EBS/INSTRUMENT/PARAMETER FOR GEOTECHNICAL AND BORED TUNNEL WORKS/PARAMETER AND CONTROL PARAMETER
FOR BUILDING CLASSIFICATION II-B, II-C, III-B & III-C OR
FOR NATM WORKS.
CUT AND COVER HERITAGE BUILDINGS OR SPECIFIC SIGNIFICANCE SUCH 16 4 AS REQ. 4 4 8
EXCAVATION ZONE AS HOSPITALS, SCHOOL BUILDINGS,
THE SERVICEABILITY LIMIT MOVEMENT FOR A MONITORED ELEMENT WILL BE THE LESSER OF: TELEPHONE-EXCHANGE STRUCTURE, SPECIAL WATER
SUPPLY STRUCTURES.

FOR BUILDING CLASSIFICATION I-A, I-B, II-A 12 4 AS REQ. 2 2 2


a) CALCULATED DESIGN VALUE FOR THE SERVICEABILITY LIMIT, INCLUDING STRESSES AND DISPLACEMENT/MOVEMENT OF
GEOTECHNICAL, BORED TUNNEL AND NATM TUNNEL WORKS;
* THE NUMBER OF INSTRUMENTS INDICATED ON THE ABOVE TABLE IS ONLY INDICATIVE AND THE ACTUAL NUMBER OF INSTRUMENTS SHOULD BE
b) MONITORED ELEMENT MOVEMENT/DISTORTION WHICH WOULD THEORETICALLY CAUSE SERVICE DISRUPTION. DECIDED BASED ON THE SIZE OF THE BUILDING, AND THE CONDITION OF THE BUILDING.

c) FOR UTILITIES, THE VALUES OF SETTLEMENT/ROTATION THOSE ARE ACCEPTABLE TO THE RELEVANT
AGENCIES/AUTHORITIES AND/OR THE ENGINEER.

d) ALLOWABLE STRUCTURE OR GROUND LIMITS CORRESPONDING TO “SLIGHT” DAMAGE CLASSIFICATION. MONITORING FREQUENCY (MANUAL): MONITORING FREQUENCY (AUTOMATIC):

e) GROUNDWATER DRAWDOWN (A DROP OF WATER TABLE DURING CONSTRUCTION) BY ONE METRE BELOW THE LOWEST MINIMUM MONITORING FREQUENCY MINIMUM MONITORING FREQUENCY
RECORDED GROUNDWATER TABLE (THE LOWEST RECORDED GROUNDWATER TABLE SHALL BE CONSIDERED AS THE LOWEST INSTRUMENT PRIOR TO DURING EXCAVATION/ BACKFILLING AFTER INSTRUMENT PRIOR TO DURING EXCAVATION/ BACKFILLING AFTER
LEVEL OF GROUNDWATER TABLE AS RECORDED BY THE CONTRACTOR PRIOR TO CONSTRUCTION). EXCAVATION STRUT REMOVAL BACKFILLING EXCAVATION STRUT REMOVAL BACKFILLING
1) GROUND SETTLEMENT DAILY 1) BUILDING SETTLEMENT
WEEKLY WEEKLY MONTHLY CONTINUOUS REAL TIME
MONITORING POINT MARKERS (BSM)
2) STANDPIPE PIEZOMETER WEEKLY DAILY WEEKLY MONTHLY 2) TILTMETER CONTINUOUS REAL TIME
CHANGES MAY BE PROPOSED TO THE INITIAL VALUES SELECTED BASED ON THE SITE CONDITIONS AND REQUIREMENTS.
CHANGES TO ALERT AND ALARM LEVELS WILL BE JUSTIFIED ON THE BASIS OF OBSERVED PERFORMANCE AND WILL BE 3) VIBRATING WIRE PIEZOMETER WEEKLY DAILY WEEKLY MONTHLY
SUBMITTED FOR THE ACCEPTANCE OF THE DESIGNER. 4) INCLINOMETER/
EXTENSOMETER IN SOIL WEEKLY DAILY WEEKLY MONTHLY
5) INCLINOMETER IN SECANT PILES WEEKLY DAILY WEEKLY MONTHLY
6) CONVERGENCE WEEKLY WEEKLY
ON REACHING AN “ALERT LEVEL' AT ANY LOCATION, THE CONTRACTOR SHALL IMMEDIATELY SUBMIT A WRITTEN REPORT TO MEASUREMENTS DAILY MONTHLY
THE ENGINEER, REVIEWING ALL TOTAL AND DIFFERENTIAL MOVEMENTS/DISTORTIONS (OR THE RELEVANT PARAMETERS) TO 7) CRACKMETERS WEEKLY WEEKLY MONTHLY
DAILY
DATE, ASSESSING THE EFFECTS OF THE MOVEMENTS/DISTORTIONS (OR OF THE RELEVANT PARAMETERS) ON THE
MONITORED ELEMENTS AND PREDICTING FURTHER MOVEMENT (OR FURTHER DETERIORATION OF THE PARAMETER) AND
THEIR EFFECT ON MONITORED ELEMENTS BASED ON THE TREND TO DATE. WHERE IT IS CONSIDERED AND AGREED BY THE
ENGINEER THAT MOVEMENT (OR THE RELEVANT PARAMETER) TRENDS INDICATE THAT “ACTION LEVEL” MAY BE REACHED
DURING THE COURSE OF THE WORKS, THE CONTRACTOR SHALL BE REQUIRED TO SUBMIT PROPOSALS FOR REMEDIAL
MEASURES TO LIMIT FURTHER MOVEMENT (OR FURTHER DETERIORATION OF THE PARAMETER) FOR SEEKING THE NOTICE OF
VIBRATION MONITORING:
NO OBJECTION FROM THE ENGINEER. THE REMEDIAL PROPOSALS SHALL INCLUDE THE DETAILS OF THE REMEDIAL MEASURES
AND THEIR LIKELY EFFICIENCY. NOTWITHSTANDING THE ABOVE, A CHANGE BETWEEN CONSECUTIVE READINGS GREATER
THAN 5 MILLIMETRES (MOVEMENT) SHALL NECESSITATE THE IMPOSITION OF “ALERT LEVEL” STATUS REGARDLESS OF THE MAXIMUM PERMISSIBLE PEAK PARTICLE VELOCITIES
GLOBAL MOVEMENTS. AT EXISTING BUILDING STRUCTURES:
PEAK PARTICLE VELOCITES
S.NO TYPES OF EBS IN MM/SEC (MAX. ALLOWABLE)
ON REACHING AN ”ACTION LEVEL” AT ANY LOCATION, THE CONTRACTOR SHALL SUBMITAN UPDATED REPORT REVIEWING THE AT ADJACENT EBS
MOVEMENTS INCLUDING DIFFERENTIAL MOVEMENTS AND DISTORTION(OR THE RELEVANT PARAMETERS). THE REPORT SHALL 1 MOST STRUCTURES IN "GOOD" CONDITION 25
ASSESS THE EFFECTS ON MONITORED ELEMENTS AND PREDICT FURTHER MOVEMENT (OR FURTHER DETERIORATION OF THE 2 MOST STRUCTURES IN "POOR" CONDITION 5
PARAMETER) AND THEIR SUBSEQUENT EFFECT ON MONITORED ELEMENTS. THE REPORT SHALL ALLOW FOR REMEDIAL
3 MOST STRUCTURES IN "FAIR" CONDITION 12
WORKS THAT HAVE BEEN IMPLEMENTED AND SHOWN TO BE EFFECTIVE. WHERE IT IS CONSIDERED AND AGREED BY THE
ENGINEER THAT MOVEMENT (OR RELEVANT PARAMETER) TRENDS INDICATE THAT “ALARM LEVEL” MAY BE REACHED OR 4 WATER-SUPPLY STRUCTURES 5
EXCEEDED DURING THE COURSE OF THE WORKS, THE CONTRACTOR SHALL REASSESS THE DESIGN AND PROPOSE REMEDIAL 5 HERITAGE STRUCTURE/BRIDGE STRUCTURE 5
MEASURES(INCLUDING DESIGN MODIFICATIONS) FOR SEEKING THE NOTICE OF NO OBJECTION FROM THE ENGINEER. THE ABOVE LIMITS ARE MAXIMUM PERMISSIBLE, HOWEVER THIS MAY HAVE TO
CONTRACTOR SHALL PROPOSE A CONTINGENCY PLAN THAT SHALL BE IMPLEMENTED IN THE EVENT “ ALARM LEVEL” IS
RESTRICTED FURTHER IF REQUIRED TO AVOID DAMAGE TO THE ADJACENT EBS OR
REACHED OR EXCEEDED AND OBTAIN NOTICE OF NO OBJECTION FROM THE ENGINEER. THE CONTRACTOR SHALL ALSO
CAUSING DISCOMFORT TO THE OCCUPANTS.ALONG THE PROPOSED
DEVELOP AN EMERGENCY PLAN THAT SHALL BE IMPLEMENTED IN THE EVENT THE APPLIED CONTINGENCY MEASURES
CANNOT CONTROL THE SITUATION AND OBTAIN NOTICE OF NO OBJECTION FROM THE ENGINEER. IN ADDITION, A NEW SET OF ALIGNMENT,OTHER LIMITATIONS MAY BE IMPOSED AT ADJACENT EBS, SUCH AS
“ALERT LEVEL” AND “ACTION LEVEL” VALUES WHICH TAKE INTO ACCOUNT THE IMPLEMENTATION OF THE PROPOSED REMEDIAL HOSPITALS, SCHOOL BUILDINGS, TELEPHONE-EXCHANGE STRUCTURES, SPECIAL
WORKS SHALL BE PROPOSED BY THE CONTRACTOR FOR SEEKING THE NOTICE OF NO OBJECTION FROM THE ENGINEER WATER-SUPPLY STRUCTURE AND HERITAGE STRUCTURE ETC.. IN ADDITION
BEFORE WORK MAY BE ALLOWED TO CONTINUE . THE CONTRACTOR SHALL ALSO PROVIDE A REPORT AFTER THE REMEDIAL WORKING HOURS FOR SUCH EQUIPMENTS CAUSING VIBRATIONS MAY HAVE TO
MEASURES (INCLUDING THE DESIGN MODIFICATIONS) HAVE BEEN IMPLEMENTED, DETAILING THE FULL HISTORY OF RESTRICTED KEEPING THE CONVENIENCE AND COMFORT OF THE OCCUPANTS IN
MOVEMENTS (OR OTHER RELEVANT PARAMETERS) AND EFFECTS OF IMPLEMENTED REMEDIAL MEASURES IN RELATION TO MIND.
THE ACTUAL CONSTRUCTION WORK. THE REPORT SHALL ALSO CONTAIN THE REVIEW AND INTERPRETATION OF EVENTS
ALONG WITH A JUSTIFICATION TO PROCEED WITH THE WORK FOR SEEKING THE NOTICE OF NO OBJECTION FROM THE
ENGINEER. WORK SHALL ONLY BE RESUMED AFTER A NOTICE OF NO OBJECTION HAS BEEN RECEIVED FROM THE ENGINEER

MUMBAI METRO RAIL CORPORATION LTD.

CUFFE PARADE STATION


S220/X/XXXX/XXX/XXXX

INSTRUMENTATION & MONITORING


GENERAL NOTES
MUMBAI METRO LINE - 3
SHEET 2
L&T – STEC JV MUMBAI UGC-01-GEO-SCP-1100-002 A D
13-01-2018 AMO FIRST ISSUE PMO/NSE VSI NGU PMO/NSE VSI NGU
A

AS SHOWN AMO 13-01-2018 UGC-01-GEO-SCP-1100-001 _ 002-A.DWG