GENERAL

NOTES:
1. THIS DRAWING SHALL BE READ IN CONJUNCTION WITH UGC-01-GEO-SCP-1101-003 & 14. PRECISE SURFACE SETTLEMENT POINTS WILL BE INSTALLED IN HIGHWAY AND PAVEMENT AREAS IN 25. ALL EXISTING PEDESTRIAN / VEHICULAR BRIDGES (UNLESS NOTED OTHERWISE) IN THE
UGC-01-GEO-SCP-1101-004. ARRAY AT 90 DEGREES TO THE TUNNEL ALIGNMENT, THESE ARRAYS WILL EXTEND TO THE OUTER MONITORING ZONE SHALL BE MONITORED WITH:
EDGES OF THE 5 MILLIMETERS PREDICTED MOVEMENT CONTOURS LINES. SUITABLE MONITORING
2. THE INSTRUMENTATION AND MONITORING REQUIREMENTS SHOWN IN THESE DRAWINGS ARE POINTS WHICH CANNOT BE READILY DISTURBED WILL BE INSTALLED OVER OPEN/PARK AREAS. THE - MOVEMENT MONITORING POINTS. TYPE OF POINTS TO BE INSTALLED ON THE STRUCTURES
MINIMUM REQUIRED. LOCATION AND TYPE OF SUCH MONITORING POINTS WILL BE AGREED WITH THE EMPLOYERS'S MUST BE ACCEPTABLE TO THE RELEVANT AUTHORITY
REPRESENTATIVE. - PRISMS MOUNTED ON PIERS/SUPPORTS
3. INSTRUMENTATION TO ALL ADJACENT EXISTING BUILDINGS, STRUCTURES, UTILITIES, SERVICE, - TILT METERS
RAILWAY, PAVEMENTS, ROAD FURNITURE AND THE LIKE SHALL START AT LEAST 7 DAYS BEFORE 15. THE EMPLOYER'S REPRESENTATIVE WILL BE GRANTED FREE AND UNOBSTRUCTED ACCESS TO ALL
CONSTRUCTION COMMENCEMENT. INSTRUMENTS, INSTRUMENT DATA LOGGERS AND INSTRUMENT RECORD. 26. ALL INSTRUMENTATION AND MONITORING WORKS SHALL BE IN RIGOROUS ADHERENCE TO
ACCEPTED FIELD WORKS PROCEDURES.
4. ALL INSTRUMENTATION TO BE MAINTAINED THROUGHOUT CONSTRUCTION PERIOD AND 16. THE ARRAY CAN BE SUITABLY MODIFIED OR MORE INSTRUMENTS WILL BE INCLUDED AS PER SITE
IMMEDIATELY REPLACED/REINSTATED IF DAMAGED/DEFECTIVE OR UNREADABLE. CONDITIONS NEAR THE STATION AND BORED TUNNEL SECTIONS, IF REQUIRED. 27. ALL PRECISE LEVELING DATA SHALL BE CRITICALLY ANALYZED TO ELIMINATE SUPPLY OF
INCORRECT, CONFUSED OR CONFLICTING INFORMATION.
5. THE INSTRUMENT LOCATIONS AND MONITORING FREQUENCY SHOWN IN THE DRAWINGS ARE 17. THE MINIMUM MONITORING ZONE FOR THE BUILDINGS WILL EXTEND TO THE OUTER EDGES OF THE
INDICATIVE ONLY. THE FREQUENCY OF MONITORING WILL BE VARIED DEPENDING ON THE TYPE OF 5MM PREDICTED CONTOUR LINE. 28. THE MONITORING FREQUENCY SHALL BE DOUBLED DURING THE TBM INITIAL DRIVE. THE INITIAL
INSTRUMENT AND THE RELATIONSHIP BETWEEN THE INSTRUMENT AND AREAS OF CURRENT DRIVE DISTANCE IS FIRST 150 METERS OF TUNNELING.
ACTIVITY. THE LOCATION OF THE MONITORING INSTRUMENT AND MONITORING FREQUENCY WILL 18. ALL THE DATA FROM MONITORING INSTRUMENTS SHALL BE PROCESSED WITHIN 24HOURS AND
BE SUBJECT TO THE ACCEPTANCE OF THE DESIGNER AND EMPLOYER"S REPRESENTATIVE. MADE AVAILABLE TO THE RELEVANT AUTHORITY AND / OR THE EMPLOYER'S REPRESENTATIVE. 29. ALL INSTRUMENT LOCATIONS SHOWN ARE APPROXIMATE.

6. VIBRATION MONITORING WILL BE CARRIED OUT ON SELECTED STRUCTURES WHERE THE 19. THE FREQUENCY OF MONITORING WILL BE REVISED DEPENDING ON THE CONSTRUCTION ACTIVITY 30. ADJUST INSTRUMENTATION AND MONITORING POINT LOCATIONS, ELEVATIONS AND/OR DEPTH AS
CONSTRUCTION ACTIVITY IS LIKELY TO RESULT IN VIBRATIONS. THE VIBRATION WILL BE AND THE PACE OF WORK. REQUIRED AT THE TIME OR INSTALLATION TO AVOID EXISTING UTILITIES AND OTHER EXISTING
MONITORED FOR THE BUILDINGS WHICH ARE LOCATED DIRECTLY ABOVE THE TBM / NATM TUNNEL. THE FOLLOWING GUIDELINES WILL BE USED WHEN DECIDING ON THE FREQUENCY OF MONITORING: FEATURES. COMPLY WITH TEMPORARY AND PERMANENT LAND BOUNDARIES AND MINIMIZE
ADDITIONALLY VIBRATION MONITORING SHALL BE CARRIED OUT DURING PILING IN ROCK AND CONFLICT WITH CONSTRUCTION OPERATIONS TO SUIT ACTUAL SITE CONDITIONS.
EXCAVATION IN ROCK USING MECHANICAL OR BLASTING TECHNIQUES. THE VIBRATION - MONITORING WILL BE REPEATED ON THE SAME DAY IF READINGS WERE CONSIDERED
MONITORING WILL BE CARRIED OUT WHEREVER MIXED FACE CONDITIONS ARE ENCOUNTERED. INCONSISTENT BY THE RELEVANT AUTHORITY. 31. MAINTAIN AND PROTECT NEW AND EXISTING INSTRUMENTATION, PROVIDE ALL SUCH
THE VIBRATION MONITORING REQUIREMENT WILL BE ESTABLISHED DURING INITIAL STAGES OF - IF THE READINGS SHOW SIGNIFICANT CHANGE, THE FREQUENCY OF MONITORING WILL BE MAINTENANCE MARKERS, COVERS, LOCKS, GUARD BOLLARDS, BARRICADES AND OTHER
THE SPECIFIC CONSTRUCTION ACTIVITIES, WHICH CAUSE VIBRATION TO EXCEED THE INCREASED. PROVISIONS NECESSARY TO PREVENT DAMAGE, DISTURBANCE, VANDALISM & DETERIORATION
ACCEPTABLE LIMITS. - IF THERE IS AN UNDESIRABLE OCCURRENCE SUCH AS EXCESSIVE GROUND LOSS FOR BORED TO NEW AND EXISTING INSTRUMENTATION. REPLACE ALL DAMAGED INSTRUMENTS IN A TIMELY
TUNNELS OR BASE HEAVE OR BASE BLOW OUT IS DETECTED, THE FREQUENCY OF MONITORING MANNER AS REQUIRED BY THE DESIGNER.
7. SUFFICIENT NUMBER OF DEEP LEVELING DATUM SHOULD BE INSTALLED BEFORE THE START OF WILL BE INCREASED.
ANY MONITORING WORKS. THE LOCATION OF THE DEEP LEVELING DATUM SHOULD BE OUTSIDE 32. DO NOT REMOVE, DEMOLISH, BACKFILL, COVER OR RENDER ANY INSTRUMENTATION
THE ZONE OF INFLUENCE OF THE WORKS AND MUST BE ACCEPTED BY THE DESIGNER. PRECISE 20. MONITORING SHALL CONTINUE UNTIL ALL MOVEMENTS AND DISTORTIONS TO THE GROUND AND INACCESSIBLE AT ANY TIME WITHOUT PRIOR APPROVAL OF THE DESIGNER.
LEVELING EQUIPMENT COMPRISING PRECISE LEVELS AND INVERT STAFF WILL BE USED TO EBS, AND CHANGES TO THE GROUNDWATER TABLE THAT MIGHT BE ATTRIBUTED TO THE WORKS, AS
SHOWN BY THE MONITORING, HAVE EFFECTIVELY CEASED FOR A PERIOD OF THREE MONTHS. 33. BUILDING MONITORING POINTS SHALL BE MOUNTED AT THE EXTERNAL FACADES AND/OR
SURVEY THE DEEP LEVELING DATUM. THESE DEEP LEVELING DATUMS WILL BE MONITORED
STRUCTURAL ELEMENTS.
REGULARLY TO CHECK THEIR STABILITY.
21. THE FREQUENCY OF MONITORING FOR THE BORED TUNNELS WILL BE VARIED WITH RESPECT TO
THE LOCATION OF THE TBM. THE FOLLOWING INDICATIVE FREQUENCY REPRESENTS THE MINIMUM 34. LOCATIONS AND NUMBERS OF FULLY AUTOMATED MOTORIZED TOTAL STATIONS AND FIXED
8. PRIOR TO THE START OF ANY WORKS ON SITE, A SATISFACTORY SET OF BASE READINGS
REQUIRED. REFERENCE POINTS ARE NOT SHOWN ON THE DRAWINGS. LOCATION AND NUMBERS TO BE
COMPRISING THE MEAN OF AT LEAST THREE SEPARATE INDEPENDENT SURVEYS WILL BE
DEFINED BY THE CONTRACTOR AND SUBMITTED TO THE DESIGNER. POTENTIAL AUTOMATED
OBTAINED FOR ALL MONITORING POINTS, EACH SURVEY WILL BE TIED TO THE REFERENCE DEEP
- DAILY MONITORING WITHIN 50 METERS BEHIND THE TBM AND 25 METERS IN FRONT OF CUTTER TOTAL STATION INSTALLATION LOCATIONS INCLUDE BUILDING FACADES, POLES AND BUILDING
LEVELING DATUM.
HEAD ROOFS.
9. STRUT/GROUND ANCHOR MONITORING IS NOT SHOWN IN THESE DRAWINGS. AT LEAST 15% OF ALL - TWICE PER WEEK BETWEEN 50 TO 100 METERS BEHIND THE TBM
- WEEKLY 100M TO 300 METERS BEHIND THE TBM. 35. LOCATION OF FULLY AUTOMATED TOTAL STATIONS SHALL BE SUCH THAT THEY EITHER LIE
STRUTS AND GROUND ANCHORS WILL BE MONITORED FOR LOAD USING STRAIN GAUGES AND/OR
OUTSIDE THE INFLUENCE ZONE OF THE EXCAVATIONS OR CAN TAKE REFERENCE FROM A FIXED
LOAD CELLS. AT LEAST 25% OF THE STRUTS AND ANCHORS MONITORED USING STRAIN GAUGES
22. FOR SHAFT CONSTRUCTION, INSTRUMENTS WITHIN 25 METERS RADIUS OF THE SHAFT WILL BE BENCHMARK OUTSIDE THE INFLUENCE ZONE.
WILL ALSO BE MONITORED USING LOAD CELLS. WHERE STRAIN GAUGES ARE USED, A MINIMUM OF
MONITORED DAILY UNTIL 1 WEEK AFTER THE PERMANENT STRUCTURE IS CAST. SUBSEQUENTLY
TWO STRAIN GAUGES COUPLED WITH TEMPERATURE MONITORING WILL BE INSTALLED AT EACH
WEEKLY MONITORING WILL BE CARRIED OUT UNTIL 6 CONSECUTIVE READINGS SHOW NO CHANGE. 36. CONTRACTOR SHALL SUPPLY POWER AND CONTINUOUS ELECTRICAL BACKUP FOR ALL
MONITORING LOCATION. THE STRUT AND ANCHOR MONITORING LOCATION SHOULD BE SELECTED
INSTRUMENTATION.
SO THAT:
23. WHERE THE TUNNEL WILL PASS BENEATH EXISTING STRUCTURES, THE MONITORING OF THOSE
EXISTING STRUCTURES AND THE INSTRUMENTATION IN THESE AREAS WILL BE CARRIED OUT ON A 37. CONTRACTOR TO ADJUST INSTRUMENTATION MOUNTING DEVICES TO SUIT ACTUAL FIELD
- EACH STRUT/ANCHOR LEVEL AT THE SELECTED LOCATIONS IS MONITORED, AND;
6-HOURLY BASIS WHEN THE TUNNEL FACE IS WITHIN 25 METERS OF THESE STRUCTURES. CONDITIONS.
- THE STRUT/ANCHOR MONITORING LOCATION COINCIDES WITH TYPE B OR TYPE C MONITORING
ARRAY.
24. ALL BUILDINGS UNLESS NOTED OTHERWISE IF ANY PART OF A BUILDING FALLS WITH THE 38. CONTRACTOR SHALL VERIFY THE LOCATIONS OF THE EXISTING STRUCTURES PRIOR TO
MONITORING ZONE THAT BUILDING SHALL BE MONITORED WITH. INSTALLATION OF INSTRUMENTS.
10. ALL UTILITIES IN SERVICE IN THE MONITORING ZONE WHETHER SUPPORTED OR NOT WILL BE
MONITORED USING SETTLEMENT MOVEMENT MONITORING POINTS PLACED ON OR IMMEDIATELY
- BUILDING MOVEMENT MONITORING POINTS, ONE EACH AT THE CORNERS OF THE BUILDING. TYPE
ABOVE THE UTILITY AT INTERVALS NOT MORE THAN 25 METERS.
OF POINTS TO BE INSTALLED ON THE STRUCTURES SHALL BE ACCEPTABLE TO THE RELEVANT
11. JOINTS IN ELECTRICAL CABLES (>22 KV) AND FIBRE OPTIC CABLES WILL BE MONITORED FOR AUTHORITY. MOVEMENT MONITORING POINTS SHALL BE INSTALLED AT EVERY 25 METERS.
MOVEMENT ACROSS JOINTS. - PRISMS MOUNTED IN COLUMNS
- TILT METERS
12. ALL EXISTING RAILWAY STRUCTURES WILL BE MONITORED WITH THE SCHEME AND SCHEDULE - TAPE EXTENSOMETERS
AGREED WITH THE RAILWAY AUTHORITY AND THE EMPLOYER'S REPRESENTATIVE. - CRACKMETERS TO MEASURE EXISTING OR NEW CRACKS (TELL-TALE TYPE)

13. PRECISE LEVELING POINTS WILL BE PROVIDED ON MONUMENTS AT GROUND LEVEL AND EXTEND
THROUGHOUT THE AREA WHERE PREDICTED MOVEMENTS ARE EXPECTED TO EXCEED 5
MILLIMETERS

MUMBAI METRO RAIL CORPORATION LTD.

CUFFE PARADE STATION


S220/X/XXXX/XXX/XXXX

INSTRUMENTATION & MONITORING


GENERAL NOTES
MUMBAI METRO LINE - 3
SHEET 1
L&T – STEC JV MUMBAI UGC-01-GEO-SCP-1100-001 A D
13-01-2018 AMO FIRST ISSUE PMO/NSE VSI NGU PMO/NSE VSI NGU
A

AS SHOWN AMO 13-01-2018 UGC-01-GEO-SCP-1100-001 _ 002-A.DWG