Sub-Station A SCOPE
DAILY Progress Report
Contract. No.:
4400004656 Location: AL UQAIR SSA Daily Report No. 2018-04 Date: 21th March
2018
CAMPAIGN DETAILS
Al UQAIR 115/13.8 KV Sub Station A
TEAM DETAILS
1 1 0 9 2 0 0
A AREAS OF CONCERN
A.1 Crane diesel not provided on time which delayed SF6 bushing installation Nauman
A.2 HVAC team didn’t come today for finishing remaining duct works Al- Awad
A.3 Diesel for site office generator not provided on time Nauman
A.4 Surge counter (6 pcs) cable required-not available at site. Should be purchased. Lalit-Isolux
A.5 Site engineer availability at site after one week-Iqama expiry issue HR-Junaid
B.4 LCC Panel plate hole drilling for cable glanding in progress
B.6 Coal tar epoxy on boundary retaining wall- North and East side in progress
C.2 Coal tar epoxy coat north and east side boundary retaining wall
C.5
C.6
C.7
D.4 LCC Panel plate hole drilling for cable glanding in progress
Power Transformer T601-LCP panel LV cable unshielding and grounding in
D.5
progress
D.6 Coal tar epoxy on boundary retaining wall- East side in progress
E1 RFI STATUS
Electrical 0 0 0 0
Mechanical 0 0 0 0
Civil 0 0 0 0
F WORK STATUS