Work Detail Breakdown for Underground Hydrant Pipe Modification in TT-04 Area

Squence No. Work Description Duration


1 Pipe cutting in point 2 and 3 (See Figure No. 1). 3 hours
2 Dewatering pipeline 2 Hours
3 Butt Fussion jointing for elbow and spool pipe (See Figure No. 1). 4 hours
Joint quantity are 3 joints.
4 Pipe alignment at point 4 and point 1 (See Figure No. 1). 3 hours
5 Electrofussion Jointing started at point 1 after pipe has aligned 5 hours
Total 17 Hours

Figure No. 1

Prepared by;

Deluge Team