Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
No Edition
Manual Book
Luoyang LPDC 7269D201 SB-403/S1
Petrochemical Customer
Engineering requirements
Device Part design Detailed Page 1 of 12
Design,Co.,Ltd.
phase/stage Design
Sign Date
Prepared by
Checked by
Approved by
4
3
2
1 2016-8-31
Modify Description Date
The contents of this document are not allowed to be shared to the third party without the written consent of LPDC
Items No. Doc.No Edition
Manual Book
Luoyang LPDC 7269D201 SB-403/S1
Petrochemical Customer
Engineering requirements
Device Part design Detailed Page 1 of 12
Design,Co.,Ltd.
phase/stage Design
1. General
1.3 Except for fulfilling all requirements contained in both GB50128 standard and
Manual Book, users shall fulfill requirements on detail drawing.
The contents of this document are not allowed to be shared to the third party without the written consent of LPDC
Items No. Doc.No Edition
Manual Book
Luoyang LPDC 7269D201 SB-403/S1
Petrochemical Customer
Engineering requirements
Device Part design Detailed Page 1 of 12
Design,Co.,Ltd.
phase/stage Design
The contents of this document are not allowed to be shared to the third party without the written consent of LPDC
Items No. Doc.No Edition
Manual Book
Luoyang LPDC 7269D201 SB-403/S1
Petrochemical Customer
Engineering requirements
Device Part design Detailed Page 1 of 12
Design,Co.,Ltd.
phase/stage Design
3. Materials
The contents of this document are not allowed to be shared to the third party without the written consent of LPDC
Items No. Doc.No Edition
Manual Book
Luoyang LPDC 7269D201 SB-403/S1
Petrochemical Customer
Engineering requirements
Device Part design Detailed Page 1 of 12
Design,Co.,Ltd.
phase/stage Design
4. Manufacture
4.1. General Provisions
4.1.1 Before the storage tank is about to be constructed, the construction
unit shall develop feasible construction plan based on the design
requirements combined with their own construction equipment and
experience.
4.1.3 Construction unit shall first draw board layout based on the situation of
both site and materials, and shall first received confirmation for
design, before wall plate and tank bottom plate of storage tank are
welded.
4.2. Welded Joints
4.2.1 Before conducting weld-work for storage tank, construction unit shall
carried out welding procedure qualification based on national
standard number NB/T47014-2011(Welding procedure qualification
for pressure equipment) and number GB50128-2014. (Including the
welding of nozzle adapter and wall plate)
4.2.2 Welding procedure specification for storage tank may refer to national
standard of welding specification for pressure vessels number
NB/T47015-2011, blue print requirements and qualification of welding
procedure
4.2.3 Shell-to-bottom fillet welds of bottom ring plate and margin plate shall
use multi-pass welding, weld the inside part first then weld the outside
part. After first layer welding of the inner and outer corner completed,
magnetic particle or penetrant testing shall be carried out. In the
The contents of this document are not allowed to be shared to the third party without the written consent of LPDC
Items No. Doc.No Edition
Manual Book
Luoyang LPDC 7269D201 SB-403/S1
Petrochemical Customer
Engineering requirements
Device Part design Detailed Page 1 of 12
Design,Co.,Ltd.
phase/stage Design
connection joint between lower part of inside fillet weld and margin
plate materials shall be grinded to smooth the area.
5. Test
5.1. General Provisions
5.1.1 Regarding personnel for conducting Non-destructive test of welding
test, it is shall be carried out by personnel who has a competence that
is shown by certain certificate and the test result is issued by related
national department.
5.1.2. Non-destructive test shall be conducted based non standard number
NB/T47013-2015 (Nondestructive testing of pressure equipment),
Qualified grade of magnetic powder and penetrant testing are grade
II.
The contents of this document are not allowed to be shared to the third party without the written consent of LPDC
Items No. Doc.No Edition
Manual Book
Luoyang LPDC 7269D201 SB-403/S1
Petrochemical Customer
Engineering requirements
Device Part design Detailed Page 1 of 12
Design,Co.,Ltd.
phase/stage Design
The contents of this document are not allowed to be shared to the third party without the written consent of LPDC
Items No. Doc.No Edition
Manual Book
Luoyang LPDC 7269D201 SB-403/S1
Petrochemical Customer
Engineering requirements
Device Part design Detailed Page 1 of 12
Design,Co.,Ltd.
phase/stage Design
6.3 Each part of coating structure and material requirements are as follows:
The Minimum
Number Minimum Coating
Coating Coating Materials
Parts of Coating thickness of
Structure (Paints)
Coating thickness total layer (µm
of each )
Bottom layer
2 50
Coat (µm)
Surface
Intermedia Non carbon epoxy
Inside Tank 2 50
te Coat antistatic coating
Body 350
Surface
3 50
Coat
The contents of this document are not allowed to be shared to the third party without the written consent of LPDC
Items No. Doc.No Edition
Manual Book
Luoyang LPDC 7269D201 SB-403/S1
Petrochemical Customer
Engineering requirements
Device Part design Detailed Page 1 of 12
Design,Co.,Ltd.
phase/stage Design
Surface
No Device Mark Color Remarks
Color
1 Storage Tank Cream Bright Red
2 Beam, Pillar, support, davit Blue
6.4.3 The surface color requirement of the device shall be submitted along to
the manufacturer during purchase order,
The contents of this document are not allowed to be shared to the third party without the written consent of LPDC
Items No. Doc.No Edition
Manual Book
Luoyang LPDC 7269D201 SB-403/S1
Petrochemical Customer
Engineering requirements
Device Part design Detailed Page 1 of 12
Design,Co.,Ltd.
phase/stage Design
The contents of this document are not allowed to be shared to the third party without the written consent of LPDC
Items No. Doc.No Edition
Manual Book
Luoyang LPDC 7269D201 SB-403/S1
Petrochemical Customer
Engineering requirements
Device Part design Detailed Page 1 of 12
Design,Co.,Ltd.
phase/stage Design
Top of Tank
Angle Steel
Self Tapping Screw Fixing
Aluminium Skin
Weld Water-proof Eaves
Aluminium Skin
Tank Wall
Bending Bolt
Bearing Angle
Welded steel bar
Iron Wire
Insulation quilt placement
Connecting Wire
Asphalt Packing
Bending Bolt
Tank Bottom
Bending Bolt
Foundation
Bending Bolt
Figure 1
The contents of this document are not allowed to be shared to the third party without the written consent of LPDC
Items No. Doc.No Edition
Manual Book
Luoyang LPDC 7269D201 SB-403/S1
Petrochemical Customer
Engineering requirements
Device Part design Detailed Page 1 of 12
Design,Co.,Ltd.
phase/stage Design
Thickness of
Layer
Thermal
Insulation
Figure 2
The position of the welding bolt must be accurately calculated
according to the size of the exact location of the line, the weld bolt
and the wall of the vertical deviation shall be not more than 3mm,
authorized party can continue for the next step work after checking
result is qualified.
7.3.3 Insulation support ring welding, thermal insulation support ring are
attached one each other in bearing angle steel (see Figure 3); the
bearing angle length for thermal insulation layer thickness minus
5mm, level of each intervals are about 1.6m; vertical spacing for
insulation mat length plus about 30mm, the lower bearing angle from
the tank bottom is about 250mm.
The contents of this document are not allowed to be shared to the third party without the written consent of LPDC
Items No. Doc.No Edition
Manual Book
Luoyang LPDC 7269D201 SB-403/S1
Petrochemical Customer
Engineering requirements
Device Part design Detailed Page 1 of 12
Design,Co.,Ltd.
phase/stage Design
Figure 3
7.3.4 Regarding the welded joint vertical bar at the edge of bearing angle
(see fig.3), the total length of the vertical reinforcement is slightly less
than the total height of the insulation layer.
7.3.5 Bending bolt and insulation support ring after welding need to be
painted.
7.3.6 Cut Φ 1.4mm galvanized wire (standard number GB9972 of
Galvanized low carbon steel wires for general uses") into the
appropriate length, after being folded twist it tight onto the vertical
bar by the interval 200-300mm, The wire shall be fastened firmly,
and so the insulation layer will not be slide off (see Figure 1)
7.3.7 Place the upper end of thermal insulation felt hanged onto
bend bolt, and then placed from top to bottom, close the tank
wall and tighten. Insulation mat (quilt) and ring joints need to
use the same material so it can be placed well, to avoid of
being too loose or too tight.
The contents of this document are not allowed to be shared to the third party without the written consent of LPDC
Items No. Doc.No Edition
Manual Book
Luoyang LPDC 7269D201 SB-403/S1
Petrochemical Customer
Engineering requirements
Device Part design Detailed Page 1 of 12
Design,Co.,Ltd.
phase/stage Design
7.3.8 Conduct anti-moist treatment for the lower part of thermal insulation
materials, within the range of 250mm. The outer surface, top surface
and bottom surface of thermal insulation blanket used for this section
need to be shelled –out from hot asphalt.
7.4 Construction and requirements of protective layer
7.4.1 The aluminum skin rolls in two lines from front edge of the installation
and flushes out to the mounting bolt holes (On some case in different
construction requirement, can be implemented on-site), dimension of
aluminum skin can be determined based on reference size in figure 4
and table 1.
50
21.5
Figure 4
The contents of this document are not allowed to be shared to the third party without the written consent of LPDC
Items No. Doc.No Edition
Manual Book
Luoyang LPDC 7269D201 SB-403/S1
Petrochemical Customer
Engineering requirements
Device Part design Detailed Page 1 of 12
Design,Co.,Ltd.
phase/stage Design
Table. 1 (mm)
7.4.2 Take the aluminum skin vertical (short edge ring), adjacent to the two
aluminum skin corrugated line aligned bottom-up circle pavement, take the
mouth down, after the aluminum skin hanging on the bent bolt, and then
loaded on the 3mm thick rubber pad (diameter 20), ring (washer 8, GB95)
and tighten the hexagon nut (M8, GB41). When installing a fixed hole
available aluminum skin, not avoid strong bending through bolts, so as not
to damage the thread or the edge of the hole, which can't screw nut or bolt
thread on the aluminum skin torn, if damaged, must be modified by the
thread, shall not be forced to tighten the nut, so as not to wear.
The contents of this document are not allowed to be shared to the third party without the written consent of LPDC
Items No. Doc.No Edition
Manual Book
Luoyang LPDC 7269D201 SB-403/S1
Petrochemical Customer
Engineering requirements
Device Part design Detailed Page 1 of 12
Design,Co.,Ltd.
phase/stage Design
7.4.4 Regarding any protrusion from the tank wall, such as aluminum skin
layer of manhole, inlet and outlet pipeline, stairs, and others area,
According to the actual situation of the whole aluminum skin openings
into the sleeve, or cut open joint, and then re-expand aluminum skin
supplement, as shown in Figure 5
The contents of this document are not allowed to be shared to the third party without the written consent of LPDC
Items No. Doc.No Edition
Manual Book
Luoyang LPDC 7269D201 SB-403/S1
Petrochemical Customer
Engineering requirements
Device Part design Detailed Page 1 of 12
Design,Co.,Ltd.
phase/stage Design
with lead oil , to avoid rainwater fall down and enter the
insulation layer.
7.4.5 Insulation layer shall be placed tight with water-proof eaves, to avoid
rainwater fall down and enter the insulation layer.
Insulation Layer
Insulation Layer
Protection Layer
Protection Layer Tank wall
Tank wall Asphalt sand damp proof layer
Asphalt sand
Tank Bottom damp proof layer Tank Bottom Concrete Slope Protection
Ground
Thickness: 60mm
Ground
Figure 7
The contents of this document are not allowed to be shared to the third party without the written consent of LPDC
Items No. Doc.No Edition
Manual Book
Luoyang LPDC 7269D201 SB-403/S1
Petrochemical Customer
Engineering requirements
Device Part design Detailed Page 1 of 12
Design,Co.,Ltd.
phase/stage Design
7 Screw-nut M8 1800
The contents of this document are not allowed to be shared to the third party without the written consent of LPDC
Items No. Doc.No Edition
Manual Book
Luoyang LPDC 7269D201 SB-403/S1
Petrochemical Customer
Engineering requirements
Device Part design Detailed Page 1 of 12
Design,Co.,Ltd.
phase/stage Design
8.1 The structure of the waterproof coating on the edge of the tank and the
application of elastic waterproof coating to the alkali free glass cloth.
8.2 Firstly elastic cement shall be filled and pressed between the
tank wall and the outer edge plate of the tank to form a smooth
inclined surface; secondly, thickness of elastic cement shall not be
less than 3mm, shall make the thickness of surface coat is evenly
distributed.
8.3 The gap between the bottom plate and the tank foundation shall
be filled with elastic waterproof material.
8.4 The overlap joint of the glass cloth shall not be less than 50mm, and
shall not be creased.
9. Acceptance of work
9.2. Regarding completion data that are provided by construction unit, shall
provide the following information except as stipulated in GB50128-2014.
The contents of this document are not allowed to be shared to the third party without the written consent of LPDC
Items No. Doc.No Edition
Manual Book
Luoyang LPDC 7269D201 SB-403/S1
Petrochemical Customer
Engineering requirements
Device Part design Detailed Page 1 of 12
Design,Co.,Ltd.
phase/stage Design
The contents of this document are not allowed to be shared to the third party without the written consent of LPDC