Sei sulla pagina 1di 3

WG B1.

11
technical brochure 606
Upgrading & Uprating of Existing Cable Systems

Members
Frédéric LESUR, Convenor (FR), Christian ROYER, Secretary (CA), Pierre ARGAUT (FR),
Gregorio DENCHE (SP), Marc JEROENSE (SE), Didier LIEMANS (BE),
Roberto GASPARI (IT),Marco MARELLI (IT), Dietmar MEURER (GE),
Jan PELLIS (NL), Lars RASMUSSEN (DK)

Corresponding Members
Steve SWINGLER (GB), Jay A. WILLIAMS (US)

General
The assessment of the actual condition and performance of
The life expectancy of an underground cable system is the cable system is the first step of any upgrading process. A list of
usually more than thirty years. It makes difficult the prediction the main influent parameters is given for a thorough evaluation,
of the change in the cable environment or the evolution of the not only of the specific performance to be upgraded (usually
operation conditions. Meeting a higher demand raises a major transmitted power), but also of the many other aspects of the
issue. The replacement of a power link or the installation of an link that could be impacted by the upgrading process itself.
additional circuit requires a significant investment cost. Some
congested areas even prevent the operator from this extension. Increasing the transmitted power is the main part of the
The difficulties involved in obtaining planning permission report. The possible parameters to explore are the voltage
for new sites also favour the life extension of existing facilities, level, the current rating and the phase difference between
often with the goal of transmitting higher power, with higher voltage and current for AC systems. A fourth possible solution
reliability to minimise the duration of unavailability of assets. is also described, namely to convert a system from AC to
The challenge is to upgrade the existing cable system with DC. The techniques explore a panel of various solutions:
reasonable and relevant solutions. increasing the current rating by reassessing the current capacity
(overload conditions, new calculation procedures, temperature
“Upgrading” is generally the improvement of the equipment monitoring), by assessing lower losses, by improving heat
performance by the replacement of components independent transfer (ventilated tunnels, special backfill, hot spot smoothing,
of the current condition in order to meet new operation heat pipes, forced cooling, reconductoring , etc.).
requirements. But other solutions are discussed in this
Technical Brochure. In this way, transmitted power, service life, The purpose of the upgrading process extends to other aspects
environmental impact and safety can be improved. of performance. It covers environmental and safety topics.
The impact of existing transition compounds, audible noise,
“Uprating” applies a physical solution that allows the system electromagnetic fields, fluid leaks, etc. is discussed. Regarding
to be operated at a current level above its rated current, or applies safety issues, interesting solutions can be implemented to
a method or a calculation that leads to improve the assessment prevent from risk of fire or explosion, and fault containment is
of the performance of the system. In the Technical Brochure, also considered.
uprating is treated as a subset of upgrading.
Once upgrading solutions have been identified, it is highly
CIGRE B1.11 Working Group proposes a simple step-by-step recommended to assess the impact of the upgrade on other
methodology with flowcharts in order to guide the engineer systems functions, because the change in the existing cable
into the upgrading process. The steps are described, from the system may interfere with other parameters, technical or
definition of the target for upgraded situation, the assessment environmental.
of the existing situation and the identification of issues, up to
the selection of potential upgrading techniques, the evaluation To illustrate possible applications, a chapter describes
of their impacts and the decision making. interesting case studies of upgrading, ranging from a simple •••

No. 279 - April 2015 ELECTRA 51


WG B1.11
technical brochure 606

Fig 1: Step by Step Methodology

reassessment of a link current capacity to more complicated case Sometimes, the existing power network becomes insufficient
of forced cooling and retrofitting new cable in existing pipes. or inadequate. The replacement of a link or the installation of
Other examples can be found in the given bibliography. an additional circuit may require an important investment cost.
A reasonable solution may be to alter the existing line or its
Introduction of the Technical Brochure environment. In accordance with the electrical engineering laws,
transmission of more power implies increasing either the voltage
Engineers consider the design of underground cable systems level or the load current, or both.
with great care. Since the life expectancy of such a system is often
more than thirty years, its specification has to take into account Structure of the document
possible evolutions of the operating conditions of the power
link. The spread of urban areas, the establishment of industrial The Technical Brochure is divided into twelve main chapters.
estates, or the evolution of the customers’ expectations, may lead
to the need to transmit more and more power. Some operating After the introduction and a summary of the Working Group
rules require the redundancy of the circuits, in order to face the history in Chapter 1, the Chapter 2 reminds the main definitions
loss of a deficient line. In this case, the remaining systems must (Refurbishment, Upgrading, Uprating), then describes the basic
allow an emergency extra power to provide the reliability and concepts of upgrading versus refurbishment, and introduces the
availability of the global network. simplified methodology used in upgrading process together •••

No. 279 - April 2015 ELECTRA 53


WG B1.11
technical brochure 606

Fig 2: Ladder network as a thermal model (steady-state operation) Fig 3: Heat Transfers in Tunnel

with the thermal/electrical concepts that are detailed in the Environment, EMF and fluid leak detection are addressed.
Brochure. It is important to understand that upgrading an existing · In Chapter 7, the Risk of Fire or Explosion, Fault
system can be considered as the feasibility study of re-designing Containment issues and issues regarding induced voltages
the cable system, taking into account higher stress levels. This can and currents are covered.
result for example in replacement of components, modification
of the cable environment, or installation of monitoring device Chapter 8 deals with the assessment of the Impact of the
upgrading process of one parameter (usually transmitted
Chapter 3 is a list of the main parameters to be eventually power) or on all other parameters of the line.
assessed during the upgrading process.:
· Technical parameters Chapter 9 describes a detailed methodology used in the
· Environmental Characteristics upgrading process :
· Safety factors · Step 1: Defining target for upgraded situation
· Remaining life / economic value · Step 2: Assessment of existing situation
· Step 3: Selection of potential upgrading techniques
Chapter 4 is the main chapter and describes the techniques · Step 4: Evaluation of Impacts and decision making.
available to increase the transmitted power:
· Increase of voltage level Chapter 10 describes various interesting case studies of
· Increase of current rating by reassessing the current upgrading, ranging from a simple reassessment of a link current
capacity capacity to a more complicated case of forced cooling and
· Increase of current rating by assessing lower losses retrofitting a new cable in existing pipes.
· Increase of current rating by improving heat transfer
· Increase of current rating by forced cooling Chapter 11 is the conclusion of the Technical Brochure, and is
· Reconductoring followed by Chapter 12 which is a useful bibliography.
· Improving the phase difference between voltage and
current: compensation Conclusion
Chapter 5 describes how to increase performance by changing In conclusion, the Technical Brochure has been written by WG
from AC to DC. B1.11 to help the engineer to review the required assessments and
· Intrinsic Characteristics to guide him along the different steps of upgrading, with a panel
· Suitability of the existing cable and its components for of various solutions. Each case is specific and must be studied
DC operation with great care because of possible interference of parameters.
· Transmittable real power Some significant improvements can be found. However, it may
· Retrofitting of steel pipe appear rapidly that no upgrading is possible or that the effect of
upgrading one parameter is causing a negative effect on others.
Chapter 6 and 7 describe the application of the upgrading Cable system designers have to remind than the opportunity to
process to environmental or safety parameters. upgrade is more likely if the original design made provision for
· In Chapter 6, the Impact of Transition Compounds on such upgrading … 

No. 279 - April 2015 ELECTRA 55

Potrebbero piacerti anche