Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
Fig. 3—Sample models. The linear model represents common, Fig. 4—Qualitative description of formation and drilling
field-level understanding. tool dependencies.
Well NWS 2
Post-well analysis of the relationship between high SE levels in
shale-rich formations with dull PDC bits led to monitoring real-
time SE and formation evaluation data from the measurement
while drilling (MWD) tool for the next well in the program, NWS
2. This method had considerable potential because the GR sub on
the MWD tool was only 4 m behind the bit face. A new bit design
with the same IADC class as Bits B and C was used, and pore
pressures, casing setting point, mud system, and drillstring were
similar to NWS 1.
Fig. 12 presents the electric and mud log data for the interval
drilled, with Fig. 13 highlighting the relationship between SE and
GR. Note that the first significant rise in SE occurred at 3579 m.
This coincided with a hard sand stringer, and further monitoring of
the real-time GR and SE beyond this point revealed that the bit was
achieving an acceptable ROP. At 3647 m, the SE again began to
rise and peaked at approximately 500,000 psi at 3652 m, which
coincided with a shale-rich formation. The bit was not pulled at
this time because of an acceptable jump in the ROP immediately
after receiving the MWD data; however, inspection of the log
showed a gradual demise in the ROP and an increase in the SE
during the next 40 m. A delay in receiving the real-time MWD data
delayed deciding to pull the bit. However, the run was eventually
terminated at 3699 m when the SE exceeded 370,000 psi. A picture
of the dull bit is shown in Fig. 14. Hindsight again leads to the
conclusion that pulling the bit at approximately 3655 m would
have been the best form of optimization.
Well NWS 3
Fig. 7—Dull bit pictures from Well NWS 1. The benefits of monitoring real-time SE is also highlighted in Well
NWS 3. This well was drilled with a WBM system with an anti-
balling additive that allowed the same relationship to apply be-
a fair assumption (based on the SE and UCS levels) that Bit C was tween SE and wear. This bit run was of a similar design to those
in a similar condition as Bit B at 3683 m and that the bit should run in Wells NWS 1 and NWS 2.
have been replaced. Fig. 10 shows that Bit C broke through the The bit run in NWS 3 initially drilled through a long shale
shale cap into a sand (significantly softer than the sands drilled sequence that allowed for a good baseline SE value of 100,000 psi
earlier) at 3686 m, consequently improving the ROP dramatically, to be obtained when the bit was in a new condition (Figs. 15
as evident in Fig. 8. At 3764 m, the ROP dropped dramatically in and 16). There were two events between 3890 and 3906 m
a shale, the WOB increased to more than 40 thousand lb (klb) in that increased SE to values greater than 240,000 psi that could
an attempt to maintain the ROP, and the SE jumped to more than have indicated the bit was in a dull state. On both occasions,
500,000 psi and continued to rise. The bit was then pulled to however, the SE level quickly dropped to or lower than the base-
surface (Fig. 7). line level and remained constant through the shale interval. These
With the benefit of hindsight, it would have been better to put intervals also had low GR readings, indicating that the higher SE
a new bit in the hole at approximately 3683 m, where the ROP and value had more to do with the formation type (i.e., hard, silty sand)
SE had decreased and increased, respectively, on Bit C. Bit D was than bit wear. There was a gradual and extended increase in SE
run in hole and reamed for 6 hours to bring the undergauge hole between 3970 and 3988 m, with a maximum of 332,000 psi at
back to gauge before drilling could commence. After 53 m of 3986 m (GR at this depth was 147 API units). The bit was not
drilling with Bit D, SE again reached a level higher than 350,000 pulled during this interval because the GR sub on the FEWD was
psi in a shale-rich formation (Fig. 11). Because of the highly ∼9 m from the bit. This resulted in the bit breaking through to the
interbedded nature of the formation, the bit eventually broke sandier section at 3988 m, with the ROP increasing to more than
through into a more drillable sand and was left in the hole because 30 m/hr between 3988 and 4000 m. With such a large increase in
of acceptable progress. After another SE spike of greater than the ROP, it was extremely difficult to justify pulling the bit, and,
400,000 psi, the bit continued on, and at 3866 m, the SE again hence, it was left in the hole. Once the bit entered the next shale
began to rise as the bit drilled into a shale-rich section. Parameters sequence, the SE once again gradually climbed and was eventually
were altered to try to regain the ROP; however, this was unsuc- pulled at 4017 m when the SE value was 626,000 psi (Fig. 17).
cessful (SE was now greater than 700,000 psi). At 3881 m, the Hindsight once again leads to the conclusion that the bit should
ROP had dropped to less than 2 m/hr, with SE peaking at 1,350,000 have been pulled after the first increase in SE while drilling
psi, and a twist-off occurred in the drilling collars. The fished through a shale interval.
Results When applying this method in the field, it was observed that a
Monitoring real-time SE has been shown to benefit the decision to better understanding of the affect of a dull condition on SE values
pull a bit. It has also shown that it would have been more eco- was obtained with average meter-based data rather than instanta-
nomical to have pulled the bit as soon as the SE level increased to neous values. This is caused by one event, such as pipe squat,
a predetermined cut-off level, in this case 300,000 psi in shale skewing the data.
formations, instead of left in the hole to continue drilling ahead. In conjunction with these findings, one of the main hurdles that
These findings were confirmed by post-well analysis of the drilling must be overcome is the perception that a bit must be pulled in a
efficiency that showed values lower than 4% through intervals badly worn state to ensure best performance. It is clear from the
where the bits should have been or were pulled. values obtained in this field that a bit may continue drilling at an
To evaluate the resulting cost of the last example (NWS-3) by acceptable ROP but far less than the achievable maximum in com-
not pulling the bit when SE first rose to more than 300,000 psi, parison to a new bit.
an average of the ROP was taken for the interval from 3975
to 4017 m, including the fast ROP sand section, to determine Conclusions
the cost of drilling this section. Based on the real-time GR In the absence of catastrophic failure events, if a drilling operator
data received at surface from the interval at 3975 m, it is reason- is regularly pulling bits graded T4 to T8 and then running a new
able to assume that the earliest the bit could have been pulled was bit, it is likely adversely impacting the section drilling cost through
at 3988 m. Assuming a new bit has been run from 3988 m, a a poor ROP. An acceptable drilling practice is to finish a hard
conservative ROP estimate would have led to a savings of approxi- stringer before pulling out of the hole to start a new bit in a softer
mately U.S. $40,000. Fortunately, this bit did not go under gauge formation. However, to continue drilling with a bit as the ROP
after drilling the sand section (from 3989 to 3998 m), as occurred drops substantially will cost the operator accordingly and risk the
when Bit C was left in hole with NWS 1. associated reaming cost of an undergauge hole (e.g., the ROP
falling from 60 to 3 m/hr means that if the first meter cost U.S. first shale is encountered and use deviations from this value as an
$2,000, then the last meter cost $40,000). Historically, we have indication of relative bit wear. To drill most efficiently, bit changes
reduced the section cost by eliminating bit runs. Today, however, should be made where possible to maximize the shale drilled with
improved understanding of the effects of incremental bit wear and a sharp, new bit at higher WOB and moderate rpm. The SE values
the high ROP potential of new bit designs incites us to consider discussed herein are only relevant for this particular application—
adding a bit back into the plan to minimize the total well cost. formations, oil-based or nonballing muds, or PDC bits drilling on
It is well known that all bits have a floundering point. However, conventional rotary drilling systems in vertical wells. To obtain
we now realize that this point moves dramatically with a bit dull valuable results, benchmark specific applications when the bit goes
state. Monitoring real-time SE data in combination with MWD in the hole and observe trends away from the initial value.
data enhances deciding when to pull a bit. Having the GR sub
closer to the bit face in combination with accurate real-time sonic Nomenclature
data could further enhance this process. Bits that have sufficient a1 ⳱ exponent fit to observed field data
wear to be inefficient in shale-rich formations can still drill me-
ABIT ⳱ bit cross-sectional area, in.2
dium-strength sands (UCS of less than 9,000 psi) with acceptable
efficiencies. However, caution must be exercised to avoid an un- DBIT ⳱ bit diameter, in.
dergauge hole. A guide on applying this monitoring technique to DG ⳱ IADC dull grade
the field is attached in Appendix B along with a worked example. Ef ⳱ mechanical efficiency, %
Shale drilling performance can be used to gauge a bit’s dull Es ⳱ specific energy, psi
condition. The best procedure is to establish a benchmark when the Esmin ⳱ minimum specific energy, psi
Fig. 10—Illustration of Bit C breaking through shale cap into sand with an increasing ROP.
OASIS position with Woodside Energy as a drilling engineer Christensen based in Dubai, UAE. He joined HCC in 1995 as a
working on exploration and appraisal well designs throughout sales representative. After 5 years in sales covering Australia,
Australia, later transferring to Intl. Drilling Team to work on the New Zealand, and PNG, he became district engineer for the
Mauritania exploration project design and execution. Waugh- Australasian and South Asia district, including Indonesia and
man holds a BS degree in mechanical engineering from Pais- the Philippines. He held this position for 2 years before transfer-
ley U., Scotland. John V. Kenner is Director of Marketing Sys- ring to his current role in Dubai. Moore holds a BS in engineering
tems for Hughes Christensen Co., The Woodlands, Texas. He in manufacturing systems and a BA in marketing from the
joined HCC’s research department in 1991, returning to Hous- Queensland U. of Technology in Australia.
ton 4 years ago, after serving a 2-year term as District Manager
for HCC’s Australasia operations. Upon returning, he worked
another 2-year hitch in marketing as Roller Cone Product Man-
ager and then assumed responsibility for the business software/
systems efforts of HCC. His interests include product develop- Appendix A—Energy Input Into System via
ment, drilling economics, and drilling mechanics. Before join- Torsional and Axial Effort
ing HCC, he was a damage tolerance engineer for LTV Aircraft
Products Group, Dallas. Kenner holds a BS degree in aeronau- Specific Energy
冉 冊
tical engineering from Texas A&M U. and an MS degree in W NT 1 13.33 N
mechanical engineering from the U. of Texas at Austin. Ross A. Es = + 120 =W + . . . . . . (A-1)
Moore is a district engineer for the Middle East with Hughes ABIT ABIT * R ABIT DBIT * R
Coefficient of Friction
T T共ft − lb兲
=3 = 36 , . . . . . . . . . . . . . . . . (A-2)
DBIT * W DBIT共in.兲 * W共lb兲
Es min ≈ U
U
Ef = * 100. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . (A-3)
Es
Fig. 14—IADC 432—2:4:WT:S:X:I:CT:PR.
Worked Example
a) Specific Energy
Es =
W
ABIT
+ 120
NT
ABIT * R
=W
1
冉+
13.33 N
ABIT DBIT * R 冊
. . . . . . (B-1)