Sei sulla pagina 1di 10

Real-Time Specific Energy Monitoring

Enhances the Understanding of When To


Pull Worn PDC Bits
Robert J. Waughman, SPE, Woodside Energy Ltd., and John V. Kenner, SPE, and Ross A. Moore, SPE,
Hughes Christensen/Baker Hughes

Summary Field Observations


Knowing when to change dulled bits can significantly reduce Drilling off the remote North West Shelf of Australia requires the
costs, which can be particularly important in high-cost environ- use of semisubmersible rigs. The discovery of hydrocarbons in
ments. However, current techniques are based more on speculation 1973 in the Cretaceous sands of the Angel formation led a local
and hope rather than science. operator to drill an offset well, NWS 1 (Fig. 5), into a deeper
The concept developed to dramatically improve this inefficient horizon in January 1996 to investigate the possibility of gas-
decision process involved measuring the mechanical energy input bearing sands in the early Jurassic and Triassic formations. This
at the drill rig floor, calculating the drilling specific energy (SE), was the deepest well drilled by the operator in more than 5 years,
checking the current formation type with real-time downhole and offset information for the deeper part of the well was scarce.
gamma ray (GR) readings, comparing the SE with the bench- The operator chose a low-toxicity oil-based mud (LTOBM) for the
mark new-bit SE, and then using these values to assess the bit’s 121⁄4- and 81⁄2-in. hole sections to lessen the chances of differential
“dull” state. sticking and bit balling and to improve the chances of complete
This method has been proven to work in synthetic-based mud core recovery while coring overbalanced in the 121⁄4-in. section.
systems in which balling does not mask the bit’s dull condition. It Eliminating shale hydration with the oil mud also allowed the
was imperative that the operator proved that this process worked in operator to use heavy-set PDC bits while still minimizing the risk
water-based drilling fluids that had replaced earlier synthetic muds of bit balling.
because of environmental concerns, cost, and improved perfor- Fig. 6 shows the casing setting points with the pore pressures
mance in water-based mud (WBM). Recently, the operator estab- and mud weight used in the 1996 well. The majority of the PDC
lished that this process worked in water-based mud systems treated bits ringed out, and severe gauge wear was also a problem with
with antiballing chemicals. The case studies in which this meth- two runs, as shown in Table 1. A post-well analysis revealed
odology was developed are presented and discussed. the following.
1. All PDC bits were left in the hole too long, adversely af-
fecting the next bit run.
Introduction 2. Severe gauge wear resulted from excessive reaming with
Drilling performance is commonly analyzed by comparing a given new PDC bits before reaching bottom. This type of overloading in
run to the average of offsets. However, in offshore projects, offsets the bit shoulder area contributed to poor overall life and rate of
are fewer and learning must be accelerated because of the inherent penetration (ROP).
high cost. To reach a desired performance level, aggressive targets For future high-cost wells, a more precise method had to be
must be set and plans to achieve those must be developed and devised and used in deciding when to pull bits. Speculation rather
implemented.1 Using real-time drilling efficiency and GR data to than science was the determining factor in whether to change
monitor bit dull state is one approach refined and used by this a bit on the NWS-1 well or leave it in the hole. This decision-
operator in particularly troublesome areas. making process was extremely inefficient and did not further
To estimate the bit’s dull state from drilling efficiency data, the operator’s philosophy of continuous improvement.1 The pro-
understanding how incremental bit wear affects performance for cedure developed by analyzing drilling performance for NWS 1
different drilling conditions had to be improved. Galle2 and was then established.
Bourgoyne3 developed early mathematical models for approxi- • Check the current formation type with a downhole GR reading.
mating the effects of bit wear on drilling performance (Figs. 1 • Calculate the drilling SE5 [the amount of mechanical energy
and 2). Many performance models exist today, but they typically input at the rig floor per unit volume of material removed (Ap-
fail to capture the dependencies on formation hardness and pendix A)].
balling tendencies vs. the type of drilling tool used—PDC, • Establish a “new bit” shale benchmark SE for every run
Tungsten Carbide Insert, or Mill Tooth (Fig. 3). In a previous when possible.
work, we classified performance expectations across a range of • Compare the real-time SE to the benchmark new-bit SE.
tools and drilling conditions4 (Fig. 4) and now use this information • Estimate the wear by comparing the real-time SE with the
to interpret a dull state. The following field examples illustrate benchmark value.6
when a bit should have been pulled and the consequences on the The results of this procedure can be verified by a post-well
performance of subsequent bit runs and estimated cost impact of calculation of mechanical efficiency. The method’s foundation
not doing so. was based on the following principles.
• No rock is 200,000 psi strong, and, in fact, most rocks drilled
in the oil field are much less than 50,000 psi, with shales less than
20,000 psi (unconfined).
• SE levels in the field are often observed to be more than
Copyright © 2003 Society of Petroleum Engineers
1,000,000 psi.
This paper (SPE 81822) was revised for publication from paper SPE 74520, first presented • High-pressure laboratory drilling tests in shale have revealed
at the 2002 IADC/SPE Drilling Conference, Dallas, 26−28 February. Original manuscript
received for review 28 March 2002. Revised manuscript received 4 September 2002. Paper
drilling efficiencies with balled bits as low as 1% and optimized
peer approved 27 September 2002. efficiencies approaching 50%.7

March 2003 SPE Drilling & Completion 59


Fig. 1—Common mathematical wear models. (1) Galle and
Woods,2 and (2) Bourgoyne and Young.3

Fig. 2—Galle and Woods mathematical wear model for K-1.2


• Therefore, when accounting for drag losses in the wellbore,
we established the target real-time drilling efficiency for shale
as 25%. Bit B was replaced with an identical bit, C. The first 7 m drilled
by the new bit was weak shale with less strength than the forma-
Field Discussion tion finished with the previous dull bit. Despite these differences in
In Well NWS 1, Bit B was the only one pulled without a ring out the rock strength, the efficiency levels of the new bit vary between
(Fig. 7 and Table 1), and, therefore, this bit was used as a datum 50% initially and 7%. Very little weight on bit (WOB) is required
point for evaluating when a PDC bit was worn. It was agreed that to achieve these efficiency levels, and ROPs range from 10 to 25
for future wells, improved drilling efficiencies, although not en- m/hr compared to 3 m/hr for the dull bit. The benefits of putting a
tirely quantifiable, were possible by pulling bits before they suf- new bit in the hole are obvious.
fered this amount of wear. Formation evaluation while drilling Therefore, the challenge arises in picking the optimum point at
(FEWD) tools were already in use and proved valuable in access- which a worn bit should be pulled. The lithologies encountered in
ing real-time drilling performance. Toward the end of the section, the deep North West Shelf area consist of interbedded sands and
Bit B encountered a relatively homogeneous, dense shale section shales. Experience in the area has shown that drilling shale with a
with the following properties. dull bit, such as Bit B, leads to SE values in excess of 300,000 psi
• Depth range: 3475 to 3485 m. and that energy levels for new bits in similar formations generally
• GR range: 115 to 140 API units (FEWD real-time data). average 100,000 psi. This three-fold increase in SE for the same
• Sonic: (compression) 213 to 223 ms/m (not known in real time). formation was the key to assessing the level of wear on a bit.
Consider now that Bit C was left in the hole until it reached a depth
Well NWS 1 of 3767 m. All high SE values from the start of the run until 3667
Formation logs for the interval are shown in Fig. 8, with a more m are associated with hard sand stringers. Post-well analysis of the
focused graph highlighting the change in SE relative to GR ap- ROP and efficiency logs reveals an alarming trend in the rise of the
pearing in Fig. 9. The rock strength algorithm was used to compute SE (from 3600 to 3683 m) through this consistently shale-rich
the average strength of the formation and the drilling efficiency. section. Fig. 8 shows that at 3682 m, SE jumped to more than the
The efficiency of the dull bit in this section varied between 2.5 and 350,000-psi level and the ROP dropped to approximately 3.5m/hr.
4%. Note that the SE trend increases from 3450 m and jumps This interval had an unconfined compressive strength (UCS) of
dramatically as the shale content increases. approximately 6,000 psi. From the condition of Bit B, it would be

Fig. 3—Sample models. The linear model represents common, Fig. 4—Qualitative description of formation and drilling
field-level understanding. tool dependencies.

60 March 2003 SPE Drilling & Completion


Fig. 5—General location map.

Fig. 6—General lithology with casing and mud program.

March 2003 SPE Drilling & Completion 61


bottomhole assembly (BHA) and bit were retrieved, and all were
found to be under gauge.
Again, with the benefit of hindsight, it would have been better
to put a new bit in the hole at 3867 m, where Bit D showed clear
signs of being worn. This action would potentially have added a
new bit to the program with the associated cost of an extra trip and
bit; however, the overall ROP would have increased as well as
removing the amount of time spent reaming, fishing the BHA, and
changing BHA components.

Well NWS 2
Post-well analysis of the relationship between high SE levels in
shale-rich formations with dull PDC bits led to monitoring real-
time SE and formation evaluation data from the measurement
while drilling (MWD) tool for the next well in the program, NWS
2. This method had considerable potential because the GR sub on
the MWD tool was only 4 m behind the bit face. A new bit design
with the same IADC class as Bits B and C was used, and pore
pressures, casing setting point, mud system, and drillstring were
similar to NWS 1.
Fig. 12 presents the electric and mud log data for the interval
drilled, with Fig. 13 highlighting the relationship between SE and
GR. Note that the first significant rise in SE occurred at 3579 m.
This coincided with a hard sand stringer, and further monitoring of
the real-time GR and SE beyond this point revealed that the bit was
achieving an acceptable ROP. At 3647 m, the SE again began to
rise and peaked at approximately 500,000 psi at 3652 m, which
coincided with a shale-rich formation. The bit was not pulled at
this time because of an acceptable jump in the ROP immediately
after receiving the MWD data; however, inspection of the log
showed a gradual demise in the ROP and an increase in the SE
during the next 40 m. A delay in receiving the real-time MWD data
delayed deciding to pull the bit. However, the run was eventually
terminated at 3699 m when the SE exceeded 370,000 psi. A picture
of the dull bit is shown in Fig. 14. Hindsight again leads to the
conclusion that pulling the bit at approximately 3655 m would
have been the best form of optimization.

Well NWS 3
Fig. 7—Dull bit pictures from Well NWS 1. The benefits of monitoring real-time SE is also highlighted in Well
NWS 3. This well was drilled with a WBM system with an anti-
balling additive that allowed the same relationship to apply be-
a fair assumption (based on the SE and UCS levels) that Bit C was tween SE and wear. This bit run was of a similar design to those
in a similar condition as Bit B at 3683 m and that the bit should run in Wells NWS 1 and NWS 2.
have been replaced. Fig. 10 shows that Bit C broke through the The bit run in NWS 3 initially drilled through a long shale
shale cap into a sand (significantly softer than the sands drilled sequence that allowed for a good baseline SE value of 100,000 psi
earlier) at 3686 m, consequently improving the ROP dramatically, to be obtained when the bit was in a new condition (Figs. 15
as evident in Fig. 8. At 3764 m, the ROP dropped dramatically in and 16). There were two events between 3890 and 3906 m
a shale, the WOB increased to more than 40 thousand lb (klb) in that increased SE to values greater than 240,000 psi that could
an attempt to maintain the ROP, and the SE jumped to more than have indicated the bit was in a dull state. On both occasions,
500,000 psi and continued to rise. The bit was then pulled to however, the SE level quickly dropped to or lower than the base-
surface (Fig. 7). line level and remained constant through the shale interval. These
With the benefit of hindsight, it would have been better to put intervals also had low GR readings, indicating that the higher SE
a new bit in the hole at approximately 3683 m, where the ROP and value had more to do with the formation type (i.e., hard, silty sand)
SE had decreased and increased, respectively, on Bit C. Bit D was than bit wear. There was a gradual and extended increase in SE
run in hole and reamed for 6 hours to bring the undergauge hole between 3970 and 3988 m, with a maximum of 332,000 psi at
back to gauge before drilling could commence. After 53 m of 3986 m (GR at this depth was 147 API units). The bit was not
drilling with Bit D, SE again reached a level higher than 350,000 pulled during this interval because the GR sub on the FEWD was
psi in a shale-rich formation (Fig. 11). Because of the highly ∼9 m from the bit. This resulted in the bit breaking through to the
interbedded nature of the formation, the bit eventually broke sandier section at 3988 m, with the ROP increasing to more than
through into a more drillable sand and was left in the hole because 30 m/hr between 3988 and 4000 m. With such a large increase in
of acceptable progress. After another SE spike of greater than the ROP, it was extremely difficult to justify pulling the bit, and,
400,000 psi, the bit continued on, and at 3866 m, the SE again hence, it was left in the hole. Once the bit entered the next shale
began to rise as the bit drilled into a shale-rich section. Parameters sequence, the SE once again gradually climbed and was eventually
were altered to try to regain the ROP; however, this was unsuc- pulled at 4017 m when the SE value was 626,000 psi (Fig. 17).
cessful (SE was now greater than 700,000 psi). At 3881 m, the Hindsight once again leads to the conclusion that the bit should
ROP had dropped to less than 2 m/hr, with SE peaking at 1,350,000 have been pulled after the first increase in SE while drilling
psi, and a twist-off occurred in the drilling collars. The fished through a shale interval.

62 March 2003 SPE Drilling & Completion


Fig. 8—Formation logs of interval for Well NWS 1.

Results When applying this method in the field, it was observed that a
Monitoring real-time SE has been shown to benefit the decision to better understanding of the affect of a dull condition on SE values
pull a bit. It has also shown that it would have been more eco- was obtained with average meter-based data rather than instanta-
nomical to have pulled the bit as soon as the SE level increased to neous values. This is caused by one event, such as pipe squat,
a predetermined cut-off level, in this case 300,000 psi in shale skewing the data.
formations, instead of left in the hole to continue drilling ahead. In conjunction with these findings, one of the main hurdles that
These findings were confirmed by post-well analysis of the drilling must be overcome is the perception that a bit must be pulled in a
efficiency that showed values lower than 4% through intervals badly worn state to ensure best performance. It is clear from the
where the bits should have been or were pulled. values obtained in this field that a bit may continue drilling at an
To evaluate the resulting cost of the last example (NWS-3) by acceptable ROP but far less than the achievable maximum in com-
not pulling the bit when SE first rose to more than 300,000 psi, parison to a new bit.
an average of the ROP was taken for the interval from 3975
to 4017 m, including the fast ROP sand section, to determine Conclusions
the cost of drilling this section. Based on the real-time GR In the absence of catastrophic failure events, if a drilling operator
data received at surface from the interval at 3975 m, it is reason- is regularly pulling bits graded T4 to T8 and then running a new
able to assume that the earliest the bit could have been pulled was bit, it is likely adversely impacting the section drilling cost through
at 3988 m. Assuming a new bit has been run from 3988 m, a a poor ROP. An acceptable drilling practice is to finish a hard
conservative ROP estimate would have led to a savings of approxi- stringer before pulling out of the hole to start a new bit in a softer
mately U.S. $40,000. Fortunately, this bit did not go under gauge formation. However, to continue drilling with a bit as the ROP
after drilling the sand section (from 3989 to 3998 m), as occurred drops substantially will cost the operator accordingly and risk the
when Bit C was left in hole with NWS 1. associated reaming cost of an undergauge hole (e.g., the ROP

March 2003 SPE Drilling & Completion 63


Fig. 9—Focused graph of SE relative to GR for Well NWS 1.

falling from 60 to 3 m/hr means that if the first meter cost U.S. first shale is encountered and use deviations from this value as an
$2,000, then the last meter cost $40,000). Historically, we have indication of relative bit wear. To drill most efficiently, bit changes
reduced the section cost by eliminating bit runs. Today, however, should be made where possible to maximize the shale drilled with
improved understanding of the effects of incremental bit wear and a sharp, new bit at higher WOB and moderate rpm. The SE values
the high ROP potential of new bit designs incites us to consider discussed herein are only relevant for this particular application—
adding a bit back into the plan to minimize the total well cost. formations, oil-based or nonballing muds, or PDC bits drilling on
It is well known that all bits have a floundering point. However, conventional rotary drilling systems in vertical wells. To obtain
we now realize that this point moves dramatically with a bit dull valuable results, benchmark specific applications when the bit goes
state. Monitoring real-time SE data in combination with MWD in the hole and observe trends away from the initial value.
data enhances deciding when to pull a bit. Having the GR sub
closer to the bit face in combination with accurate real-time sonic Nomenclature
data could further enhance this process. Bits that have sufficient a1 ⳱ exponent fit to observed field data
wear to be inefficient in shale-rich formations can still drill me-
ABIT ⳱ bit cross-sectional area, in.2
dium-strength sands (UCS of less than 9,000 psi) with acceptable
efficiencies. However, caution must be exercised to avoid an un- DBIT ⳱ bit diameter, in.
dergauge hole. A guide on applying this monitoring technique to DG ⳱ IADC dull grade
the field is attached in Appendix B along with a worked example. Ef ⳱ mechanical efficiency, %
Shale drilling performance can be used to gauge a bit’s dull Es ⳱ specific energy, psi
condition. The best procedure is to establish a benchmark when the Esmin ⳱ minimum specific energy, psi

Fig. 10—Illustration of Bit C breaking through shale cap into sand with an increasing ROP.

64 March 2003 SPE Drilling & Completion


Fig. 11—Drilling with Bit D resulted in SE exceeding 350,000 psi.

K ⳱ constant set to fit field data References


N- ⳱ rotary speed, rpm 1. Bond, D.F., Scott, P.W., and Windham, T.M.: “Step Change Improve-
R- ⳱ ROP, ft/hr [m/hr] ment and High Rate Learning are Delivered by Targeting Technical
T ⳱ torque, ft·lb Limits on Subsea Wells,” paper SPE 35077 presented at the 1996
U ⳱ unconfined compressive strength IADC/SPE Drilling Conference, New Orleans, 12−15 March
W ⳱ WOB, lb 2. Galle, E.M. and Woods, H.B.: “Best Constant Weight and Rotary
␮ ⳱ coefficient of friction Speed for Rotary Rock Bits,” API paper 801-39J presented at the 1963
Spring Meeting of the Production Division of the American Petroleum
Inst., 21−23 May.
Acknowledgments
3. Bourgoyne, A.T and Young, F.S. Jr.: “A Multiple Regression Ap-
The authors wish to thank the management of Woodside Energy proach to Optimal Drilling and Abnormal Pressure Detection,” SPEJ
Ltd. and Hughes Christensen for permission to present this paper. (August 1974) 371.
4. Kenner, J.V., Waughman, R.J., and Windham, T.: “Alliance Yields
New Understanding of Bit Wear—Drilling Performance Relationship,”
paper presented at the 1998 Drilling Technology Symposium, Houston,
3 February.
5. Pessier, R.C. and Fear, M.J.: “Quantifying Common Drilling Problems
with Mechanical Specific Energy and a Bit-Specific Coefficient of
Sliding Friction,” paper SPE 24584 presented at the 1992 SPE Annual
Technical Conference and Exhibition, Washington, DC, 4−7 October.
6. Spaar, J.R. et al.: “Formation Compressive Strength Estimates for Pre-
dicting Drillability and PDC Bit Selection,” paper SPE 29397 presented
at the 1995 SPE/IADC Conference, Amsterdam, 28 February−2 March.
7. Pessier, R.C., Fear, M.J., and Wells, M.R.: “Different Shales Dictate
Fundamentally Different Strategies in Hydraulics, Bit Selection, and
Operating Parameters,” paper SPE 28322 presented at the 1994 SPE
Annual Technical Conference and Exhibition, New Orleans, 25−
28 September.

SI Metric Conversion Factors


°API 141.5/(131.5+°API) ⳱ g/cm3
ft × 3.048* E−01 ⳱ m
gal × 3.785 412 E−03 ⳱ m3
in. × 2.54* E+00 ⳱ cm
in.2 × 6.451 6* E+00 ⳱ cm2
lbm × 4.535 924 E−01 ⳱ kg
psi × 6.894 757 E+00 ⳱ kPa
*Conversion factor is exact.

Robert J. Waughman is currently a drilling engineer for Intl. Drill-


ing Team, Woodside Energy. He has worked as a field/district
engineer for Hughes Christensen, working in Asia, west Africa,
Fig. 12—Electric and mud logs of interval drilled for Well NWS 2. and the Middle East. He later transferred to Australia to take an

March 2003 SPE Drilling & Completion 65


Fig. 13—Focused graph of SE relative to GR for Well NWS 2.

OASIS position with Woodside Energy as a drilling engineer Christensen based in Dubai, UAE. He joined HCC in 1995 as a
working on exploration and appraisal well designs throughout sales representative. After 5 years in sales covering Australia,
Australia, later transferring to Intl. Drilling Team to work on the New Zealand, and PNG, he became district engineer for the
Mauritania exploration project design and execution. Waugh- Australasian and South Asia district, including Indonesia and
man holds a BS degree in mechanical engineering from Pais- the Philippines. He held this position for 2 years before transfer-
ley U., Scotland. John V. Kenner is Director of Marketing Sys- ring to his current role in Dubai. Moore holds a BS in engineering
tems for Hughes Christensen Co., The Woodlands, Texas. He in manufacturing systems and a BA in marketing from the
joined HCC’s research department in 1991, returning to Hous- Queensland U. of Technology in Australia.
ton 4 years ago, after serving a 2-year term as District Manager
for HCC’s Australasia operations. Upon returning, he worked
another 2-year hitch in marketing as Roller Cone Product Man-
ager and then assumed responsibility for the business software/
systems efforts of HCC. His interests include product develop- Appendix A—Energy Input Into System via
ment, drilling economics, and drilling mechanics. Before join- Torsional and Axial Effort
ing HCC, he was a damage tolerance engineer for LTV Aircraft
Products Group, Dallas. Kenner holds a BS degree in aeronau- Specific Energy

冉 冊
tical engineering from Texas A&M U. and an MS degree in W NT 1 13.33 ␮N
mechanical engineering from the U. of Texas at Austin. Ross A. Es = + 120␲ =W + . . . . . . (A-1)
Moore is a district engineer for the Middle East with Hughes ABIT ABIT * R ABIT DBIT * R

Coefficient of Friction

T T共ft − lb兲
␮=3 = 36 , . . . . . . . . . . . . . . . . (A-2)
DBIT * W DBIT共in.兲 * W共lb兲

where Eq. A-2 is simplified per Imperial units.


Mechanical Efficiency

Es min ≈ U
U
Ef = * 100. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . (A-3)
Es
Fig. 14—IADC 432—2:4:WT:S:X:I:CT:PR.

66 March 2003 SPE Drilling & Completion


Fig. 15—Electric and mud logs of interval drilled in Well NWS 3.

Fig. 16—Focused graph of SE relative to GR for Well NWS 3.

March 2003 SPE Drilling & Completion 67


Appendix B—Predicting PDC Bit Wear With Real-Time SE

Worked Example
a) Specific Energy

Es =
W
ABIT
+ 120␲
NT
ABIT * R
=W
1
冉+
13.33 ␮N
ABIT DBIT * R 冊
. . . . . . (B-1)

b) The mud loggers were able to calculate the SE instantaneously,


and it was averaged over meter intervals. An example of the cal-
culation is shown later for Well NWS 2 at 3652 m.
28,000 81 * 10,500
Es = + 120␲ = 532,816 psi. . . . . . . (B-2)
56.716 56.716 * 10.62
c) A line was spliced into the mud logging data by MWD person-
nel to enable real-time GR data to be viewed simultaneously with
the SE data.
d) When the PDC was in a new state and drilling a shale, SE values
would be averaged for a 5-m interval to obtain a baseline SE reading.
e) The GR data was interpreted to determine what type of forma-
tion was being drilled (shale or nonshale), and if a shale, the SE
value was compared to the baseline value previously agreed upon,
in this case 100,000 psi.
f) If the SE value increased by more than 200% greater than this
baseline value, the PDC was deemed to be in a worn state. At this
stage, consideration was given to pulling the bit based total well
cost savings. The factors considered include:
• Remaining section length.
• Expected ROP of the new PDC.
• Trip cost.
• Expected geology.
Fig. 17—Dull photograph of Bit E graded 2:4WT:S:X:I:CT:PR.

68 March 2003 SPE Drilling & Completion

Potrebbero piacerti anche