The object of equipping a roof drain with an IN ALL CASES, THERE IS NO USE OF GASKETS
adjustable top via its adjustable extension is to OR MASTIC COATINGS. THIS PRECLUDES THE
place the top or inlet of the drain at the right POSSIBILITY OF ANY LEAKAGE DUE TO BACK-
height above structural deck level to UP IN THE DRAINAGE SYSTEM AS A RESULT OF
accommodate various thicknesses of insulation. SURCHARGE OR BLOCKAGE.
This avoids the necessity of tapering or feathering On Promenade decks, a collar with a cam
the insulation layer down to the fixed body flange provides finite adjustment, with the collar being
level of the drain causing a loss of insulation value secured by three locking screws to the body of
at the drain location. MIFAB ACCOMPLISHES the roof drain. A similar system is used with the
THE ADJUSTMENT BY INSTALLING A DECK R1200-HC in IRMA (Inverted Membrane) systems.
FLANGE ONTO THE ROOF DECK AND You do achieve the precise height with MIFAB roof
SUPPORTING THE ROOF DRAIN BODY FLUSH drains with a minimum of effort. Moreover, MIFAB
OR SLIGHTLY BELOW THE MEMBRANE LEVEL roof drains provide flexibility in top height often
(ABOVE THE INSULATION) UTILIZING THE HS-3 necessary to overcome construction irregularities
HARDWARE SET. A DECK CLAMP (SUFFIX -U) IS impossible to compensate for with fixed extension
SECURED BENEATH THE DECK ON THE SAME drains.
HARDWARE TO ENSURE A RIGID
INSTALLATION.
LOCKING DOME COMBINED FLASHING CLAMP
Once in place stays in place to provide AND GRAVEL STOP
positive protection for the roof drain and Features a broad clamping area with ridges
drainage system entrance. The vertical that match grooves in the flange of the roof
perimeter openings provide sufficient free drain body to secure the membrane without
drainage area, in compliance with codes and the puncturing and troublesome wrinkling
standards, for prompt and efficient drainage often encountered with so-called locking type
of the roof while protecting the system clamps. The vertical gravel stop prevents
against entrance of potentially damaging rooftop surfacing gravel from washing into
objects. With the open or free area on top, the drainage system while permitting
which is merely for flood conditions, the drainage of roof through the V-type weirs.
dome has a total free area in excess of 136
square inches.
i B
MIFAB Roof Drain Selection Guide (Cont’d)
Roof drains and accessories combine to form the drain’s outside sump diameter, maintenance of
upstream or entrance terminals of the roof the actual opening size within the range cannot
drainage system and as such play a key role in always be assured. Therefore, a sump receiver,
the success or failure of the system. Sizing and sometimes called drain receiver should be
placement of roof drains are thoroughly covered specified with the drain to compensate for deck
in the next section of this catalog. However, prior opening irregularities and provide proper support
to sizing and placement of drains, there are for the drain. The sump receiver is simply a thin
certain basic roof design factors that must be steel ring with a wide, flat flange and depressed
considered when selecting and specifying the center opening into which the roof drain body
proper roof drains and accessories for the job. flange fits, supported by the lip of the opening. In
Even though all roofs serve the same basic addition to easing the deck opening tolerance
purpose of protecting the building and its requirements, the sump receiver helps to
contents from the elements, their design, distribute the weight of the drain over a broader
composition, construction and drainage surface of the deck. By placing the top of the
requirements do vary. Accordingly, when the drain flange at deck level where it should be,
specifications for the roof drains and accessories the sump receiver helps to avoid the dam-like
are developed, it is of vital importance that all effect created when the drain flange rests on
design factors of the roof be addressed and top of the deck opening. Specify Suffix –B
reflected in the products specified to ensure a
trouble free, successful installation. Also, ROOF DECKS
insistence upon compliance with the ROOF DRAIN SECURING UNDERDECK
specifications is essential, for departure therefrom CLAMPS
could result in a substandard roof drain Proper roof drain support having been resolved
installation potentially doomed to ultimate failure. through employment of the sump receiver, it
Basic roof design factors for consideration with becomes necessary to consider a practical
recommended drainage products follow. method of securing the drain to the deck. If the
drain is not in a “poured-in-place,” thus secured,
ROOF DECKS installation of an auxiliary securing means must
ROOF DRAIN SUPPORT SUMP RECEIVERS be provided. The most effective and positive
Roof decks, owing to the broad range of types means available in response to this requirement is
and materials of construction, provide perhaps the underdeck clamp
the greatest challenge to the specifier in his quest (suffix -U). With the drain
for the proper method of roof drain support for in place and the sump
installation in a given deck. Unless the drain is receiver on top of the
being installed in a deck, the underdeck
poured concrete deck SUMP RECEIVER
(SUFFIX -B) clamp of circular con-
with drain in place figuration, surrounding
UNDERDECK CLAMP
completely surrounded the drain and connected (SUFFIX -U)
and supported by the piping, is brought to bear
deck it will be necessary against the bottom of the deck and drawn tightly
to provide a deck opening in place with hardware provided. This in effect
in which to set the drain. It sandwiches the deck into a positive union with the
is when such openings drain. Thus secured into place, the roof drain
are required that drain becomes an integral component of the deck with
support becomes the foremost consideration. assurance of installation stability and optimum
Even though minimum deck openings are performance in its role as entrance terminal of the
recommended in this catalog for each drain and roof drainage system. Specify Suffix –U
maximum openings are stated based on the
ii A
MIFAB Roof Drain Selection Guide (Cont’d)
iii A
MIFAB Roof Drain Selection Guide (Cont’d)
the gravel layer with the flowing water. Roof drains to meet the code
equipped with ballast guards are ideally suited for requirement is install a completely separate with
this application and should be specified for external water dams (R1200-R) or internal
installation in all insulated roof membrane assembly standpipes (R1200-W). MIFAB has also
type roofs. There are basically two schools of developed a combination primary and secondary
thought as to the proper location of the dome on roof drain in one unit requiring a single deck
ballast guard equipped roof drains. One suggests it opening. Specify R1150 Series.
be in its normal position assembled to the flashing
clamp at structural deck level with the ballast guard ROOF DECKS
surrounding the dome making for a dome recessed GUTTER AND BALCONY DRAINAGE
drain assembly. The other option is to place the GUTTER DRAINS
dome and its retaining ring Drainage requirements for gutter and small roof
on top of the ballast guard areas, such as balconies and the like, are handled
at the surface of the by small compact roof drains referred to as gutter
aggregate gravel layer The drains. Such drains, owing to their compact size,
decision as to which type can readily be installed in confined locations
to specify remains with the which otherwise may not be properly drained.
engineer, as either type will Specify Series R1400 through R1420.
function satisfactorily for R1200-HC (ILLUSTRATED)
the purpose intended.
ROOF DECKS
ROOF DRAINS WITH WATER DAM
Sometimes, roofs are designed to contain a
predetermined amount, thus depth, of water at all
times for various reasons. Roof drains for
installation in such roofs are equipped with a
watertight open top collar either internal or
external of the dome, with its flood level at the
prescribed elevation above deck to serve as a
dam to retain and maintain the desired amount of
water on the roof. Excess
water, treated for drain
sizing purposes as
rainfall, floods over the
dam and is discharged
into the roof drainage
system in the normal
manner. Specify suffix -R R1200-R (ILLUSTRATED)
or -W.
iv A
MIFAB Roof Drain Selection Guide (Cont’d)
v A