KONSORSIUM
PT. PATRA DRILLING CONTRACTOR - PT. ELNUSA
TABULATION OF REVISION
REVISION REVISION
PAGE REMARKS PAGE REMARKS
A B C 0 1 A B C 0 1
1 x
2 x
3 x
4 x
5 x
6 x
7 x
8 x
9 x
ATTACHMENT
Date : 21/03/2018 PROCEDURE FOR CONSTRUCTION SURVEY
Rev.
Section Page Company’s Comment
Code
Date : 21/03/2018 PROCEDURE FOR CONSTRUCTION SURVEY
TABLE OF CONTENTS
1. INTRODUCTION
1.1 Project Overview
PT Pertamina Gas and PT Perusahaan Gas Negara plans to build pipeline to support PT
Pertamina Refinery Unit II Program. RU II plans to convert the fuel for its power plant from oil to
natural gas, so that the oil production from the refinery can be increased to support national
demand. In the future, this gas infrastructure will also trigger industrial growth in Dumai.
The gas pipeline length will be 67 km from Trans Gas Indonesia (TGI) at Duri to PT Pertamina
Refinery Unit II at Dumai. This project also includes the construction of Four Line Break Control
Valve stations and Gas Metering Station at Dumai.
1.2 Scope
This work includes pipeline route surveys, elevations and areas to be worked out in accordance
with boundary markers and distances determined by the survey team and approved by PT.
Pertamina Gas and PT. Perusahaan Gas Negara.
1.3 Definition
1. QA/QC
2. HSE
3. SITE MANAGER
Date : 21/03/2018 PROCEDURE FOR CONSTRUCTION SURVEY
2. METHOD OF WORK
Bore Pile foundation is a type of deep foundation in the form of a tube, which serves to continue the burden of
the building structure above it from the surface of the soil to a layer of hard ground underneath. The foundation
of bore pile has the same function as foundation pile or other depth foundation. The difference between the two
is on how the execution of the installation. The service of bore pile foundation begins from making a hole in the
ground by drilling the ground first and then reinforcing the reinforcement into the hole followed by casting the
Figure 1. Preparation
There are various types of tools and ways to implement the making of bore pile foundation, including:
By using the tool / machine bore mini crane can be drilled with a diameter of 30 cm to 60 cm with a choice of
depth of 6 meters to 24 meters and even more. That is by using wash borring / wet drill. Wash borring requires
a lot of water to facilitate the implementation of bore pile work. High-rise buildings, bridges, towers and other
buildings that are build certainly require a solid foundation and sturdy.
What if the surface soil condition is not able to withstand the load of the building, the load must be continue to
the hard ground layer underneath using the foundation construction in the form of pile or bore pile. The pile
foundation is often use on large areas where the vibrations generated during the erection work do not disrupt
the surrounding environment. However, if the building is build in a location near the existing building, the
vibration generated will be an obstacle, because in the implementation very disturbing and can damage the
surrounding buildings. Under such condition, the use of bore pile foundation is the right choice of foundation.
Date : 21/03/2018 PROCEDURE FOR CONSTRUCTION SURVEY
Large projects where the means of transport support, in making bore pile is often used heavy equipment in the
form of cranes. However, for small projects especially if the means of transportation is less supportive, the use
of cranes often experience constraints because for the mobilization of funds required large enough, so the
• Easy In operation.
This is very important, especially for the preparation of foundations in urban areas where the building is quite
• Depth can be up to 24 meters or to a depth of hard ground in the area according to soundir data.
• Can be operate in two ways, wash borring system and dry drilling system.
• Work location (existing foundation, and other former installations on old buildings, etc.)
Date : 21/03/2018 PROCEDURE FOR CONSTRUCTION SURVEY
3. DRILLING PROCESS
1. Drilling with dry drilling system: Soil drill by using spiral drill bit. By rotating the drill bit and lifted each interval
2. Drilling with wet drill / wash borring system: Soil drill using drill bit cross ex design according to requirement,
which have rotation speed 375 rpm, and pressure +/- 200 kg. If the soil is easily collapse, it can be given a
temporary chasing first to avoid the wall slope of the drill hole. Soil erosion is aided by water shooting
through drill hole handlebar generated from the NS-80 pump. This cause the eroded soil to become mud
and push out of the hole. After reaching the depth of the plan, drilling is stopp, while the drill bit is allowed to
rotate but the pressure load is stopped and the circulating water keeps flowing until the ground debris is
pushed out of the entire hole. During this clearance, the reinforcing steel and tremic pipe are prepared near
the borehole. Once clean enough, the drill handlebar is lift from the drill hole. With the clean foundry hole
framework is lifted with the help of diesel and power winch in a position perpendicular to the borehole and
carefully lowered to avoid multiple contacts with the borehole. The reinforcing steel that has been inserted in the
drill hole is retaine with a cross section of the borehole. If the need for steel reinforcement more than 12 meters
can be done by tied with a concrete wire with a length of overlap 50-60 cm or according to the construction
drawing provided.
The fourth stage is the work of casting bore pile into the borehole.
Date : 21/03/2018 PROCEDURE FOR CONSTRUCTION SURVEY
1. To separate the concrete from the sewage sludge at the beginning of casting, use plastic bags filled with
concrete and tied with concrete wire and then hung on the inside of the tramhole one meter down from the
2. After the preparation of the casting is completed, slump concrete 18 ±2cm is accommodated in a tremi funnel
and retained by a plastic ball containing a concrete mixture after a sufficient full of plastic bag balls are
removed so that the concrete pushes the mud out of the tremi hole. Casting is done continuously to avoid
congestion on the tramway. With this trajectory system, the foundry starts from the bottom of the hole by
pushing the water / mud from the bottom out into the hole.
3. After the pipe is full and the end of the tremi pipe is embedd in concrete so that the concrete cannot flow
because there is pressure from below. To smooth the concrete in the pipe, it must be stomping on the pipe.
Tremic pipe should always be embedded in a concrete slab and the filling inside the funnel should be kept
4. Tremic pipe is removed every 3 meters but the pipe end inside must be in a state embedded in the concrete.
Stop casting after the concrete slab that had risen to the surface had been cleared of mud.
5. After the casting work is finished, all casting equipment is cleaned of concrete and mud residue and re-
Note: concrete slump for bored pile casting is 18 ±2cm so that the concrete can fill the hole maximally and to simplify
the process of bored pile or so the concrete is not stoped in the tremi pipe.