MEGA/CONS/STNS/N‐S/PKG‐4B
Construction Of Elevated Metro Rail Stations – Five (5) Numbers Including Viaduct
Portion Within The Stations And Transition Spans On Either Side Of The Stations
(Motera, Sabarmati, Aec, Sabarmati Railway Station And Ranip) For Pkg – 4B
(Package-4b) Of North-South Corridor For Ahemadabad Metro Rail Project Phase-I
METHOD STATEMENT
For
REVISION CONTROL:
Current
Revision Number R0
1
METHOD STATEMENT – VERTICAL PILE LOAD TEST
MEGA/CONS/STNS/N‐S/PKG‐4B
Construction Of Elevated Metro Rail Stations – Five (5) Numbers Including Viaduct
Portion Within The Stations And Transition Spans On Either Side Of The Stations
(Motera, Sabarmati, Aec, Sabarmati Railway Station And Ranip) For Pkg – 4B
(Package-4b) Of North-South Corridor For Ahemadabad Metro Rail Project Phase-I
Contents
1. PREAMBLE:......................................................................................................................................2
2. SCOPE OF WORK:............................................................................................................................3
3. DEFINITIONS:..................................................................................................................................3
5. RESPONSIBILITY & AUTHORITY:................................................................................................3
6. ORGANISATION CHART:...............................................................................................................4
7. EQUIPMENTS:..................................................................................................................................4
8. METHODOLOGY FOR VERTICAL PILE LOAD TEST................................................................5
9. HEALTH, SAFETY AND ENVIRONMENT....................................................................................8
10. QUALITY ASSURANCE AND QUALITY CONTROL................................................................9
11. ENCLOSURES.................................................................................................................................9
2
METHOD STATEMENT – VERTICAL PILE LOAD TEST
MEGA/CONS/STNS/N‐S/PKG‐4B
Construction Of Elevated Metro Rail Stations – Five (5) Numbers Including Viaduct
Portion Within The Stations And Transition Spans On Either Side Of The Stations
(Motera, Sabarmati, Aec, Sabarmati Railway Station And Ranip) For Pkg – 4B
(Package-4b) Of North-South Corridor For Ahemadabad Metro Rail Project Phase-I
1. PREAMBLE:
This method statement provides the details of the test procedure adopted for Carrying out vertical pile
load test.
2. SCOPE OF WORK:
The scope includes conducting Vertical load test at Sabarmati station building (By Cyclic method).
3. DEFINITIONS:
4. REFERENCES:
1 Contract Documents
2 Specification for Road and Bridge Works (MORTH)
3 IS-2911 (Part IV) - 2013
4 Approved Design Calculations
5 Quality Assurance Plan
6 Safety, Health and Environment (SHE) Plan
Following are the responsibilities and reporting structure of personnel involved in the scope of the
procedure:
3
METHOD STATEMENT – VERTICAL PILE LOAD TEST
MEGA/CONS/STNS/N‐S/PKG‐4B
Construction Of Elevated Metro Rail Stations – Five (5) Numbers Including Viaduct
Portion Within The Stations And Transition Spans On Either Side Of The Stations
(Motera, Sabarmati, Aec, Sabarmati Railway Station And Ranip) For Pkg – 4B
(Package-4b) Of North-South Corridor For Ahemadabad Metro Rail Project Phase-I
6. ORGANISATION CHART:
Project Manager
Site Engineer
7. EQUIPMENTS:
• Hydra Crane
• Hydraulic pump
• Hydraulic jacks- 500 T
• Pressure gauge
• Dial gauge
• Reaction frame
• Generator
Step 1
Installation of Test Pile: As per approved Bored Cast in Situ Pile Methodology.
Step 2
Installation of bored cast in situ reaction pile as test, it consists following:
1. Boring of 1200 mm dia. reaction pile having depth as per approved design drawing depth.
2. Lowering of reinforcement cage with the help of piling Rig/crane.
3. Thereafter, the tremmie pipes are lowered in position for concreting. Concreting of pile is
done by 200 mm dia. Tremie Pipes. The concrete shall either be pumped or poured in to the
hopper. The top of concrete in a pile shall be brought above the cut off level to permit removal
of all laitance and weak concrete to ensure good concrete at cut off level.
4. Load test shall be carried out after on achieving 100% strength in test pile/anchor pile.
Step3
Pile head shall be prepared after chipped off of top concrete head and top is prepared
smooth & horizontal. A plate of 32 mm thick shall be placed over the pile head.
Step 4
Hydraulic Jacks, Distance Pieces, Datum Bar and test assembly will then be erected as shown
in drawing.
Step 5
Alternate loading & unloading shall be carried out at each stage. Load shall be increased, each
increment being about 20 % of design load on pile after 15 mins. of unloading. Reading shall
be taken immediately after unloading 15 mins. Later for each stage.
e) Load sequence:
1st 2nd 3rd 4th 5th 6th 7th 8th 9th 10th 11th 12th
0 0 0 0 0 0 0 0 0 0 0 0 0
20 20 20 20 20 20 20 20 20 20 20 20 20
0 40 40 40 40 40 40 40 40 40 40 40 40
0 60 60 60 60 60 60 60 60 60 60 60
40 80 80 80 80 80 80 80 80 80 80
20 60 100 100 100 100 100 100 100 100 100
0 40 80 120 120 120 120 120 120 120 120
20 60 100 140 140 140 140 140 140 140
0 40 80 120 160 160 160 160 160 160
20 60 100 140 180 180 180 180 180
0 40 80 120 160 200 200 200 200
20 60 100 140 180 220 220 220
0 40 80 120 160 200 240 240
20 60 100 140 180 220 250
0 40 80 120 160 200 240
20 60 100 140 180 220
0 40 80 120 160 200
20 60 100 140 180
0 40 80 120 160
20 60 100 140
0 40 80 120
20 60 100
0 40 80
20 60
0 40
20
0
6
METHOD STATEMENT – VERTICAL PILE LOAD TEST
MEGA/CONS/STNS/N‐S/PKG‐4B
Construction Of Elevated Metro Rail Stations – Five (5) Numbers Including Viaduct
Portion Within The Stations And Transition Spans On Either Side Of The Stations
(Motera, Sabarmati, Aec, Sabarmati Railway Station And Ranip) For Pkg – 4B
(Package-4b) Of North-South Corridor For Ahemadabad Metro Rail Project Phase-I
7
METHOD STATEMENT – VERTICAL PILE LOAD TEST
MEGA/CONS/STNS/N‐S/PKG‐4B
Construction Of Elevated Metro Rail Stations – Five (5) Numbers Including Viaduct
Portion Within The Stations And Transition Spans On Either Side Of The Stations
(Motera, Sabarmati, Aec, Sabarmati Railway Station And Ranip) For Pkg – 4B
(Package-4b) Of North-South Corridor For Ahemadabad Metro Rail Project Phase-I
1 0.00
2 104
3 208
4 312
5 416
6 520
7 624
8 728
9 832
10 936
11 1040
12 1144
13 1248
14 1300
Result Submission:
The analysis of result for skin friction and end bearing will be estimated as per procedure – outline in
IS Code 2911 – 1985 (appendix A)
8
METHOD STATEMENT – VERTICAL PILE LOAD TEST
MEGA/CONS/STNS/N‐S/PKG‐4B
Construction Of Elevated Metro Rail Stations – Five (5) Numbers Including Viaduct
Portion Within The Stations And Transition Spans On Either Side Of The Stations
(Motera, Sabarmati, Aec, Sabarmati Railway Station And Ranip) For Pkg – 4B
(Package-4b) Of North-South Corridor For Ahemadabad Metro Rail Project Phase-I
All site personnel shall be provided with helmet, boots and other personal safety devices. Working
area should be barricaded. Proper precaution and safety devices shall be used for activities like
fabrication, handling of electrically operated equipment’s etc. All site personnel shall follow the
approved health and safety plan.
Quality control and assurance shall be strictly followed as per the approved quality assurance plan
(QAP) / ITP I Check List I Approved Method Statement.
11. ENCLOSURES