Sei sulla pagina 1di 24

CONCRETE MIXTURE PROPORTION

MINIMUM REQUIRED
CEMENT
ULTIMATE COMPRESSIVE STRENGTH WATER
CLASS PROPORTION SAND GRAVEL STRENGTH [US Gallons / 94lbs USES
40KG 50KG CYLINDER CUBE (40kg) Cement]
(94lbs) (110lbs) [h=2h] [150mm X 150mm X
150mm]

AAA 1:1:2 Pre-Stressed and Post-Tensioned

AA 1 : 1.5 : 3 12 9.5 0.5 1 4000 2400 2800 Underwater retaining wall, shear wall
and elevator core walls

A 1:2:4 9 7 0.5 1 3500 2000 2400 5 Footings, pier, columns, girders, beams,
joists and slabs

B 1 : 2.5 : 5 7.5 6 0.5 1 3000 1600 2000 5.75 Slabs on fill and non-load bearing wall
or 4” CHB

C 1:3:6 6 5 0.5 1 2500 1300 1600 6.5 Concrete plant boxes and parapet walls

D 1 : 3.5 : 7 5 4 0.5 1 2000 1000 1200 7 Plant boxes, footpaths, walkway and
lean concrete

Portland Cement: hydraulic cement made by burning a mixture of clay and limestone in a rotary kiln and pulverizing the resulting clinker into a
CLASSIFICATION OF PORTLAND CEMENT
very fine powder, named for its resemblance to a limestone quarried on the Isle of Portland, England.

TYPE I Normal A Portland cement used for general construction, having none of the distinguishing qualities of the other types.

A Portland cement having a reduced content of tricalcium aluminate, making it more resistant to sulfates and causing it to generate less heat of hydration: used in
TYPE II Moderate general construction where resistance to moderate sulfate action is required or where heat buildup can be damaging, as in the construction of large piers and heavy
retaining walls.

A very finely ground Portland cement having an increased content of tricalcium silicate, causing it to cure faster and gain strength earlier than normal Portland cement:
TYPE III High Early Strength
used when the early removal of formwork is desired, or in cold-weather construction to reduce the time required for protection from low temperatures.

A Portland cement having a reduced content of tricalcium silicate and an increased content of dicalcium silicate, causing it; to generate less heat of hydration than
TYPE IV Low Heat
normal Portland cement; used in the construction of massive concrete structures, such as gravity dams, where a large buildup in heat can be damaging.

A Portland cement having a reduced content of tricalcium aluminate, lessening the need for gypsum, a sulfate normally added to cement to retard its setting time: used
TYPE V Sulfate Resisting
where resistance to severe sulfate action is required.

A Type I, Type II, or Type Ill Portland cement to which a small quantity of an air entraining agent has been inter-ground during manufacture; designated by the suffix A,
Air –Entraining Portland Cement
as in Type IA, Type IIA, or Type IllA.

A Portland cement produced from raw materials law in iron oxide and manganese oxide, the substances that give concrete its gray color; used in precast concrete work
White Portland Cement
and in the making of terrazzo, stucco, and tile grout.

● IMHOTEP©2015 ● Page 1 of 24 ●
MORTAR & PLASTER MIXTURE PROPORTION COMPUTATION FACTORS FOR CHB PLASTER

CEMENT MORTAR MORTAR


CLASS PROPORTION SAND CHB 1 SIDE / CHB 0.0023
FILL (cu.m.) LAY (cu.m.)
40 KG 50 KG
4”
A 1:2 18 14.5 1 0.0015 0.001016 1 SIDE / SQ.M. 0.029
[10x20x40]

B 1:3 12 9.5 1 6” REBAR WEIGHT Ø2 x 0.00617


[15X20X40] 0.0030 0.001524 PER METER (kg)
C 1:4 9 7 1 Ø2 / 162

D 1:5 7.5 6 1 8” # / 8 x 25.4


[20X20X40] 0.0045 0.002032 Ø REBAR (mm)
# x 3.125

12.5 pcs CHB / sq.m. # REBAR (Ø x 8) / 25.4

PERMISSIBLE SUMP CONSISTENCY MINIMUM THICKNESS OF NON-PRE-STRESSED BEAMS OR ONE-WAY SLABS


UNLESS DEFLECTIONS ARE COMPUTED (members are not supporting or attached to
DESCRIPTION MAXIMUM MINIMUM partitions or other construction likely to be damaged by large deflections)

DESCRIPTION SOLID ONE-WAY SLAB BEAMS / RIBBED ONE-


Slabs, beams, thin reinforced walls & bldg. columns 150mm (6”) 75mm (3”)
WAY SLAB
Reinforced foundation walls and footings 125mm (5”) 50mm (2”) Simply Supported L/20 L/16
Plain Footings, caisson, and substructure walls 100mm (4”) 25mm (1”) One End Continuous L/24 L/18.5
Pavements and floor laid on ground 75mm (3”) 25mm (1”) Both Ends Continuous L/28 L/21

Heavy mass construction 75mm (3”) 25mm (1”) Cantilever L/10 L/8

for Fy other than 415Mpa, the values shall be multiplied by (0.4 + Fy/700)

CONVERSION FACTORS

1 m2 1m 1 ft 1 m3 1 (US) gallon 1 kg 1 lb 1 ton (RT) 1 km 1 tin

10.7639 ft 2
3.2808 ft 0.3048 m 35.3147 ft 3
0.003785412m 3
2.205 lbs 0.4536 kg 12000 BTU 3280.8398 ft 4 gallons

1550.0031 in2 39.37 in 1000 L 3.785412 L 0.001 ton 0.0004536 ton 39,370.078 in 16 liters

264.1721 USG 0.13368055 ft3 64 quarts

231 in 3
256 pints

● IMHOTEP©2015 ● Page 2 of 24 ●
FORMULA CURING PERIOD FOR REMOVAL OF FORMS

PARTS OF STRUCTURE TIME REQUIRED


PYTHAGOREAN
BOARD FOOT VOLUME (Cylinder)
THEOREM FOOTINGS Massive Footing 1 day (24 hours)

[T(in) x W(in) x L(ft)] / 12 V = πr2h c = √a2 + b2 Cantilever Footing 5 days (120 hours)
(multiplied by pieces) (V = Area of Circle x Height)
Slab Footings 5 days (120 hours)
[T(in) x W(in) x L(in)] / WALLS & Massive walls, 1 day (24 hours)
144 PLASTERS 0.30m – 2.00m high Add 1 day (24 hours) per meter
(multiplied by pieces)
Thin walls 2 days (48 hours)
<0.30m – 2.00m high Add 1.5 days (36 hours) per meter
Cantilever walls, buttresses, Without Loads: SAME as Thin walls
Board foot Volume counter forts, diaphragms
(D – 4)2 x L
COLUMNS Ratio of Height to Least Ø 2 days (48 hours)
16 up to 4
Ratio of Height to Least Ø 2 days (48 hours) to 28 days (672 hours)
From 4 to 15 Add 1 day (24 hours) per meter of height
SOH CAH TOA SLABS 3 to 7ft spans 5 days (120 hours)
Sin = Opposite / Hypotenuse Cos = Adjacent / Hypotenuse Tan = Opposite / Adjacent Add ½ day (12 hours) per foot of span
Use when no A Use when no O Use when no H Over 7ft spans 7 days (168 hours) to 28 days (672 hours)
Add 1 day (24 hours) per foot of span
Angle = Sin-1 (O/H) Angle = Cos-1 (A/H) Angle = Tan-1 (O/A)
BEAMS & Sides 3 days (72 hours)
GIRDERS
O = H x sin Θ A = H x cos Θ O = A x tan Θ Bottoms (14ft max.) 14 days (336 hours) to 28 days (672 hours)
Add 1 day (24 hours) per foot span
H = O / sin Θ H = A / cos Θ A = O / tan Θ
ARCHES Spandrel Walls 7 days (168 hours)
Spandrel Arches 14 days (336 hours)
TWO WAY SLAB THICKNESS (T) 2-WAY 1-WAY Main Arches 21 days (504 hours)

T = PERIMETER / 180 W/L >0.5 W/L <0.5 BALUSTRADE Steel & Side forms 1 day (24 hours)
COPINGS, ETC.
T = [W(2) + L(2)] / 180 L/W <2 L/W > 2 R.C. PILES & Sides 3 days (72 hours)
R.C. POSTS
Bottom 14 days (336 hours)

● IMHOTEP©2015 ● Page 3 of 24 ●
USEFUL FORMULAS MINIMUM CONCRETE COVER

MEASUREMENT OF PLANE & SOLID FIGURES DESCRIPTION BAR CAST IN PRE-CAST PRE-
DIAMETER PLACE STRESSED
π (pi) 3.1416 (Non-Pre-stressed)
CIRCUMFERENCE Concrete cast
against and
circle π x diameter or πd PERMANENTLY 75mm 75mm
EXPOSED TO
circle π x ½ major axis + ½ minor axis EARTH
SURFACE AREA Concrete EXPOSED To Earth Or Weather
circle π x radius , or 0.7854 x diameter
2 2
wall panels, 16mm or
40mm 20mm
slabs, joists smaller
cone ½ circumference x slant height + area of base
25mm
20mm to 36mm 50mm 20mm
cylinder Circumference x length + area of 2 ends
45mm to 60mm - 40mm
ellipse Product of axes x 0.7854 (approx)
Other members 16mm or
parabola Base x 2/3 height 40mm 30mm
smaller
parallelogram Base x height 40mm
20mm to 36mm 50mm 40mm
pyramid ½ sum of base perimeter x slant height + area of base 45mm to 60mm - 50mm
Sector of circle (π x degrees arc x radius) / 360 Concrete NOT EXPOSED to earth or in contact with ground
Segment of circle Area of sector minus triangle walls, slabs, 16mm or
20mm 15mm
joists smaller
Sphere π x diameter
20mm
20mm to 36mm 20mm 15mm
Triangle ½ base x perpendicular height
45mm to 60mm 40mm 30mm
Triangle (equilateral) (side)2 x 0.433
beams, columns
VOLUME
Primary Db or 15mm
Cone Area of base x 1/3 perpendicular height
reinforcement 40mm (MIN.) to 40mm 40mm
(MAX.)
cylinder π x radius x height
2

Ties, Stirrups,
Pyramid Area of base x 1/3 height 40mm 10mm 25mm
Spirals
Sphere Diameter3 x 0.5236
Shells, folded 16mm or
12mm 10mm 10mm
plate smaller
Wedge Area of base x ½ perpendicular height
Db but not
20mm or larger 20mm 15mm
<20mm

● IMHOTEP©2015 ● Page 4 of 24 ●
BRANDS OF BUILDING MATERIALS (PHILIPPINES)

MECHANICAL ELECTRICAL PLUMBING ROOFING FLOORING WATER GLASS INSULATION PANEL


(AC) (LAMINATED) PROOFING

• IWATA • PHILFLEX (Wires) • FALCON (Fixtures) • PLEXIGLASS • HORNITEX • ABC • ARTES MEYER • BETAFOAM • EASTERN WIRE
• MIDEA • ATLANTA • RNW PACIFIC • KANOPY • KRONOTEX • EQUA SUPREME • CO BAN KIAT • EXCEL COIL • LATIMCO
• GREE (uPVC Moulding) (Pipes) • GI SHEETS • PUYAT • DR. SEAL HARDWARE COATING • MATIMCO
• SANYO • GARTIM (Lights) • WEIDA (Septic • GOOD LIFE • STEIGER • A-PLUS • CORSINI (Glass CORPORATION • MULTI-LINE
• KOPPEL • ROYU (Elec. Tanks; Storage • COLORSTEEL – • PRIMAFLOOR • CASTLE Rock Accent and • MACRO • PUYAT STEEL
• SUPER COOL Devices) Tanks) MVP • MULTI-LINE • DESTINY Decorative Wall INDUSTRIAL • ROOFSCAPE
• IDEC • MOLDFLEX • CREATIVE • WHISTLER (Bamboo Flooring) • DUROTECH Tiles) • PHILIPPINE •
• FEDDERS (uPVC Conduits) (Fixtures) • DN STEEL • ZETA • NOVSEAL • EPCO (Glass INSULATION
• DAIKIN • LUXPIA (Lights) • ALFAIDRO (Pipes • MEGA • MILAN • MORTABOND Façade) • PRIME PRODUCT
• CLIPSAL (Lights) & Fittings • APO • MGS • BESSER • JARO GLASS CONCEPTS
• CHORUS LUX • ANESCO (Fiber • BAYER • MULTIRICH • KENNETH & SPEACIALISTS
• PHELPS DODGE Glass) MAKROLON • INCRETE MOCK • THERMAC
(Wires) • SUPER TANK • ETERTON • KENT • LE GRAND • WAH PHIL
• DURAFLEX • SANIMOLD • DELOON • LELUX • WRIGHT
• COLUMBIA (Pipes) • ONDULINE ELECTRONICS •
(Wires) • POLYMUTAN • RIVIERA (Glass Break
• ECOSAN (Pipes & • K-PLAST Alarm)
Fittings) • METALPLAS • LEXTON
• BLUE MAGIC • COLENT(Polyc)
(Bathroom Glass
(Water Tanks) Shelf)
• XANLITE (Polyc)
• ATLANTA (Pipes & • TOTO (Bathroom
• TILE STAR
Fittings) Glass Shelf)
• POLYLITE
• LUCKY (Pipes &
• HEAT SHIELD
Fittings)
• GEBERIT
• ALASCO
• EMERALD
• NELTEX
• POWEREE
• RNW

BOARDS DOORS & WINDOWS ADHESIVE CEMENT TILES HAND TOOLS TANKS

• BORAL PERFORATED • POLY DOOR • BETONIT • RIZAL • MARIWASA • STANLEY • FIRSTANK


• RICHMOND • MIGHTY DOOR • COWPROY • REPUBLIC • J.K. (China) • LOTUS • SUPERTANK
• JARO • ABC GYPSUM PUTTY • LAFARGE • EURO TILES • C-MART TOOLS • BESTANK
• ACCENDO • FIBER-23 • VIBRO • LVP (China) • MASCOT • WEIDA
• TOTAL COAT • ZIRCONIO (Spain) • DAIKEN
• POWERBOND Floor • APO (Vinyl Tiles)
Adhesive (Puyat Steel) • XIONGDI GRANITE

● IMHOTEP©2015 ● Page 5 of 24 ●
PAINTS & STAINS

BRANDS BOYSEN DAVIES DUTCHBOY JOTUN NIPPON SPHERO

• ALTAMIRA (Min. Paint) • PERMACOAT • ELASTOGEL • NALCRETE • MAJESTIC • WEATHERBOND • CANADIAN


• A-PLUS • PERMATEX • FUSION • ROOFMASTER • STRAX EASY CLEAN • Q-SHIELD • HYPER TONE
• BOSNY • PLEXIBOND • LIQUID TILE • VERSATEX • JOTAPLAST • PROTECTIVE • MANOR
• BOYSEN • PRIMEGUARD • MEGACRYL • GLOSS MASTA • JOTASEALER 03 • FLEXISEAL • ROOF TUFF
• BRONCO • ROOFGARD • SUN & RAIN • CLASSIC • JOTASHIELD • ADVANCE • SPHERETITE
• DAVIES • WALLGUARD • BIO-FRESH • TEX-A-CRETE • JOTAROOF • ACRYLIC 5170 • SPHEREFLEX
• DECREA (Stone Coating) • COOL SHADES • CLEAN AIR • JOTASHIELD PRIMER • VINILEX • SHERTEX
• DESTINY • ECO PRIMER • STAY CLEAN • ULTRA PRIMER • EXPRESSKOTE • TUFF SEAL
• DR.SEAL (Putty Filler) • HEALTHY HOME • DA VINCI • CITO PRIMER 09 • INSULCOAT • VTEX
• DUTCH BOY • KNOXOUT • ACREEX • GARDEX • WEATHERBOND FLEX
• DYNATRON (Rubberized) • HUDSON • KERAMIFLOOR • WOODSHIELD • MOMENTO
• FLEXSEAL • VIRTUOSO SILK TOUCH • POWERFLOOR • FUNGICIDAL WASH • ODOURLITE
• FLINTKOTE • XYLADECOR • ROOFSHIELD
• GLOBECONSU • ACRYTEX • GLOSS-IT
• HUDSON (Top Coat) • ELASTI-KOTE • AQUA GLOSS-IT
• KONIG (Wood Stain) • ACQUA EPOXY • EPOXY ENAMEL
• MANOR • AQUASEAL • OIL WOODSTAIN
• NATION • CHALK CLOCKER • PONDO
• NIKKO (Spray Paints) • SKIMCOAT • MORTAFLEX
• RJ • DURAFILL • MONDO
• RUST-OLEUM • PERMAPLAST
• SPHERO • TILEWORKS
• TITAN (Elastomeric) • NATION DURA-ROOF
• UNIVERSAL • NATION DREAMCOAT
• WIN • TITAN SUPERFLEX
• ZAR (Wood Stain) • DECORE
• ZYNOLITE (Spray) • MARMORINO
• MATTE SHIELD

PAINT ROOF ROOF EFFECTIVE WIDTH ROOF ACCESSORIES


TYPE OF WALL SPREAD RATE ROOFING SIDE LAP EFFECTIVE EFECTIVE
STANDARD SIZE ACCESSORY
FINISH PER GALLON GI Sheet (Corrugations) WIDTH LENGTH
SPREAD RATE 25m2 to 40m2 Plain GI Sheet 0.90 x 2.40 2 1/2 0.60 Gutter 2.35
Coarse to Rough 2 Corrugated GI 0.80 x 1.50 to 3.60
30 m 1 1/2 0.70 Flashing 2.30
(Wooden Trowel Finish) Sheet
Fine to Coarse GI Sheet Gauge 14 to 30
35 m2 END LAP 0.25 to 0.30mm Ridge Roll 2.20
(Paper Finish)
Smooth to Fine Roofing Gauge 26
40 m2 Valley Roll 2.30
(Putty Finish)
Gutters &Valley Gauge 24
Hipped Roll 2.20
Rolls

● IMHOTEP©2015 ● Page 6 of 24 ●
UAP DOC 202 (OLD) SPP DOC 202 (NEW)
COMMUTATIVE ACTUAL MBF of COMMUTATIVE ACTUAL MBF of
PHASE / STAGE PHASE / STAGE
OPERATION PERCENTAGE PHP 1,000,000 OPERATION PERCENTAGE PHP 1,000,000
PRELIMINARY
Feasibility Study 5% 5% 50,000
MOBILIZATION
Feasibility Study 25,000 25,000 25,000

SCHEMATIC SCHEMATIC
DESIGN 15% 10% 100,000 DESIGN 15% 15% -25,000 125,000
Preliminary Design Preliminary Design
DESIGN DESIGN
DEVELOPMENT 35% 20% 200,000 DEVELOPMENT 40% 25% 250,000
Working Drawings Working Drawings
CONTRACT CONTRACT
DOCUMENT
Specifications / Contract 85% 50% 500,000 DOCUMENT
Specifications / Contract 90% 50% 500,000
Documents Documents
COMPLETION
Part Time Supervision 100% 15% 150,000
COMPLETION
Part Time Supervision 100% 10% 100,000

100% 1,000,000 100% 1,000,000

LIABILITY 10% LIABILITY 5%


SUPERVISION 5% SUPERVISION 5%

UAP DOC 203 UAP DOC 204 UAP DOC 205


SPECIALIZED ALLIED SERVICES CONSTRUCTION SERVICES POST-CONSTRUCTION SERVICES
Salary Basis Monthly
FULL TIME SUPERVISION
INTERIOR DESIGN 12% - 20% 1.0% - 1.5% MANAGEMENT FEE
QC, Documentation, Reports
Percentage of Gross Rentals 4.0% - 6.0%
CONSTRUCTION MANAGER UAP DOC 207
LANDSCAPE DESIGN 10% - 15% Present only DURING construction of the 1.5% - 3.0%
project DESIGN-BUILD SERVICES

ACOUSTICS, LIGHTING, PROJECT MANAGER


DESIGN-BUILD SERVICES
ENGINEERING SERVICES
10% - 15% Present BEFORE-DURING-AFTER 2% - 5% By Administration 7% + RDS Fee
construction of the project

DESIGN-BUILD SERVICES
With Guaranteed Maximum Project
10% + RDS Fee
Interest rate per annum
in case of incomplete / non-payment 2% Construction Cost

● IMHOTEP©2015 ● Page 7 of 24 ●
ARCHITECT’S MINIMUM BASIC FEE
50M 50M 100M 300M 500M 500M
GROUP TYPE MBF BUILDINGS Php 50M Php 50M to Php 100M Php 200M Php 500M Over Php
100M to 200M to 500M to1B 1B
1 SIMPLE 6% Armories Packaging & Processing Plants 6% 5% 4% 3% 2% 1%
Bakeries Parking Structures
Habitable Agricultural Structures Printing Plants
Freight Facilities Public Markets
Hangars Service Garages
Industrial Buildings Simple Loft-Type Buildings
Manufacturing / Industrial Plants Warehouses
2 MODERATE 7% Art Galleries Office Buildings / Office Condominiums 7% 6% 5% 4% 3% 2%
Banks, Exchange Parks, Playgrounds and
Financial Institutions Open Air Recreational Facilities
Bowlodromes Residential Condominiums
Call Centers Police Stations
Churches & Religious Facilities Postal Facilities
City/Town Halls & Civic Centers Private Clubs
College Buildings Publishing Plants
Convents, Monasteries & Seminaries Race Tracks
Dormitories Restaurants / Fast Food Stores
Exhibition Halls & Display Structures Retail / Wholesale Stores
Fire Sations Schools
Laundries & Cleaning Facilities Serviced Apartments
Libraries Shopping Centers
Malls / Mall Complexes Showrooms / Service Centers
Motels & Apartels Supermarkets / Hyper-markets
Multi-Storey Apartments Welfare Buildings
Nursing Homes Mixed-Use Buildings
3 EXCEPTIONAL 8% Airports / Wet & Dry Ports & Terminals Mental Institutions 8% 7% 6% 5% 4% 3%
Aquariums Mortuaries
Auditoriums Nuclear Facilities
Breweries Observations
Cold Storage Facilities Public Health Centers
Convention Facilities Research Facilities
Gymnasiums Stadia
Hospitals & Medical Buildings Telecommunication Buildings
Hotels Theaters & Similar Facilities
Laboratories / Testing Facilities Transportation Facilities & Systems
Marinas & Resort Complexes Veterinary Hospitals
Medical Arts Offices & Clinics
4 RESIDENTIAL 10% Single-Detached Row-houses or Shop-houses
Single-Attached or Duplex Small Apartment Houses and
Townhouses
5 MONUMENTAL 12% Exposition & Fair Buildings Museums
Mausoleums, Memorials & Monuments Specialized Decorative Buildings

6 REPETITIVE 100% (1st) Re-used Design & Contract Documents for the similar buildings without amending
80% (2nd) the drawings and the specifications
60% (3rd)
40% (4th)

● IMHOTEP©2015 ● Page 8 of 24 ●
ARCHITECT’S MINIMUM BASIC FEE
GROUP TYPE MBF BUILDINGS 50M 50M 100M 300M 500M 500M
7 HOUSING 100% (1st) Several Residential Buildings on a single site with the use of one (1) set of plans /
60% (2nd-10th) designs, specifications and related documents
30% (11th + )
8 EXTENSIVE DETAILING 15% Design for built-in components or elements, built-in equipment, special fittings,
screens, counters, Architectural Interiors, and Development Planning and / or
design
9 ALTERATIONS / RENOVATIONS 150% Alterations, renovations, rehabilitations, retrofit and expansion / additions to
existing buildings belonging to Groups 1 to 5
10 CONSULTATION / ARBITRATION PHP 200/hr The Architect is engaged to render opinion or give advice, clarifications or
for technical explanation on technical matters pertaining to architectural works
matters
PHP 500
as expert witness

ARCHITECT’S MINIMUM BASIC FEE


PHYSICAL PLANNING SERVICES (OLD SPP)
TYPE DESCRIPTION SCOPE BASIC FEE
Moderately Flat
Industrial Estates
1 Commercial Centers First 50 Hectares or less PHP 5,000 per Hectare
Sports Complexes
Resorts Over 50 Hectares up to 100 Hectares PHP 250,000 + PHP 4,500 per Hectare in excess of 50 Hectares
Tourist Centers
Amusement Parks
Educational Campuses Over 100 Hectares up to 200 Hectares PHP 475,000 + PHP 4,000 per Hectare in excess of 100 Hectares
Institutional & Government Centers
Site Planning of Complex Consisting of Several Structures within a Over 200 Hectares PHP 875,000 + PHP 3,000 per Hectare in excess of 200 Hectares
Contiguous Site
Subdivision Planning for housing on properties within Metro First 100 Hectares or less PHP 3,000 per Hectare
2 Manila, Cities, Regional Centers, and Provincial Capitals
Over 100 Hectares up to 200 Hectares PHP 300,000 + PHP 2,300 per Hectare in excess of 100 Hectares
Over 200 Hectares PHP 550,000 + PHP 2,000 per Hectare in excess of 200 Hectares
Subdivision Planning for housing on properties located on other First 100 Hectares or less PHP 2,000 per Hectare
3 localities beside those under Type 2
Over 100 Hectares up to 200 Hectares PHP 200,000 + PHP 1,500 per Hectare in excess of 100 Hectares
Over 200 Hectares PHP 350,000 + PHP 1,000 per Hectare in excess of 200 Hectares
Rugged with Steep Terrain Increase by 30%
Preparation of Detailed Engineering Drawings & Specifications on ROADS, 4% of Development Cost
DRAINAGE, SEWERAGE, POWER & COMMUNICATION

● IMHOTEP©2015 ● Page 9 of 24 ●
2010 SPP DOCUMENTS IRR OF RA 9266 CODE OF ETHICS (UAP DOC 200)
NO. DESCRIPTION CONTENTS A S TITLE

200 1 1
The 2006 Code Of Ethical Title, Policy Statement, Definition of
1-3 3 2 General Provisions
Conduct (UAP) Terms and Scope of Practice

SECTIONS
Professional Regulatory Board of The Architect’s Responsibility in
201 2 2

RULES
Pre-Design Services Architecture (PRBOA) 4 - 11 8 7
Relation to the PEOPLE
Organization, Powers and Function
The Architect’s Responsibility in
202 3 3
Examination, Registration and
Design Services 12 - 24 13 12
Licensure Relation to His / Her CLIENT
The Architect’s Responsibility in
203 Specialized Allied Services 4 Practice of Architecture 25 - 39 15 4 5
Relation to the CONTRACTOR

204A 5
Full Time Construction The Architect’s Responsibility in
Final Provisions 40 - 47 8
Services Relation to
5 2 MANUFACTURERS,
204B
Construction Management
Violation of IRR of RA9266 DEALERS & AGENTS
Services

PHP 100,000 – PHP 5,000,000


205 Post-Construction Services
6 months to 6 years
The Architect’s Responsibility in
Relation to His / Her
6 22 COLLEAGUES AND
Any HEAD OF GOVERNMENT AGENCY OR OFFICER(S) of a Private Firm / institution
206
Comprehensive Architectural
Services SUBORDINATES
who violates – sub-paragraph of RA. No. 8981

PHP 50,000 – PHP 500,000


207 Design-Build Services
6 months + 1 day to 6 years 7 1 Architect’s Credo

208 8
Architectural Design
Without first executing a written CONTRACT/SERVICE AGREEMENT 3 Miscellaneous Provisions
Competition (ADC)

Not less than PHP200,000


209
Professional Architectural
Violation of the Code
Consulting Services (PACS) Not exceeding 6 years

PHP 100,000 – PHP 5,000,000


301 General Conditions
6 months to 6 years

METHODS OF COMPENSATION APPLICATION METHODS OF SELECTION APPLICATION BASIS / PROCESS

Percentage of Project Construction Cost (%PCC) Used Worldwide Reputation


Recommendation of a Friend
Direct Selection Relatively Small Project Recommendation of Former Client
Multiple of Direct Personnel Expenses (MDPE) Non-Creative Work Recommendation of Another Architect

Professional Fee Plus Expenses (PFPE) Continuing Relationship (1) Invitation (4) Verification
Institutions, Corporations, Public (2) Pre- (5) Evaluation &
Comparative Selection Qualification Ranking
Lump Sum or Fixed Fee (LS/FF) Government Projects Agencies
(3) Interview (6) Negotiation
Per Diem, Honorarium Plus Reimbursable Expenses Personal Time (50km) Idea Competition
Architectural Design Competition (ADC) Civic or Monumental Projects Design Competition
Mixed Method of Compensation Design-Build Competition

● IMHOTEP©2015 ● Page 10 of 24 ●
SPP DOCUMENTS (201 – 209) SPP DOCUMENTS (201 – 209)
DOC DESCRIPTION SCOPE DOC DESCRIPTION SCOPE
Consultation Quality Control
201 204A
PRE-DESIGN SERVICES (12) FULL-TIME SUPERVISION
Pre-Feasibility Studies SERVICES Evaluation of Construction Work
Manner of Providing Services Feasibility Studies • Architect of Record (AoR) Preparation of Daily Inspection Reports
Methods of Compensation: Site Selection Analysis Filing of Documents
 MDPE (1.5 – 2.5) • Architect of Record (AoR) • Consulting Architect
• Consulting Architect for SDP Site Utilization and Land-Use Studies
 PFPE Architectural Research • Construction Supervision Group (CSG)
 LS/FF Architectural Programming Coordination and Supervision
204B
 PDHPRE Space Planning
CONSTRUCTION
 MMC MANAGEMENT SERVICES (4) Cost and Time Control
Space Management Studies Quality Control of Work
Value Management • Construction Manager (CM)
Keeping of Records
Design Brief Preparation
Promotional Services Building & Facilities Administration
205
POST-CONSTRUCTION
SERVICES (2) • Building Maintenance
Project Definition Phase
202
REGULAR DESIGN SERVICES • Grounds & Landscaping Supervision
(RDS) (6) Schematic Design Phase
• Building Equipment Maintenance
Design Development Phase
Methods of Compensation: Contract Document Phase • Business Development and Management
 PCC Manner of Providing Services Post-Construction Evaluation
Bidding or Negotiation Phase
 MDPE (1.5 – 2.5) • Architect of Record (AoR)
Construction Phase Pre-Design Services
206
 PFPE • Consulting Architect for SDP COMPREHENSIVE
 LS/FF ARCHITECTURAL SERVICES Regular Design Services (RDS)
 PDHPRE • Single Contract / Sub-consultant (5) Specialized Architectural Services
 MMC • Separate Contract Construction Services
Post-Construction Services

Design-Build Services by Administration


207
DESIGN-BUILD SERVICES
(DBS) (2) Design-Build Services on Guaranteed Maximum Cost
Architectural Interiors (AI) Services
203
SPECIALIZED
ARCHITECTURAL SERVICES Acoustic Design Services
Architectural Lighting Layout & Design • Project ADCs for actual Projects proposed for
208
(23) ARCHITECTURAL DESIGN
Site Development Planning (SDP) Services implementation
• Architect of Record (AoR) COMPETITION (ADC)
Site & Physical Planning Services • Ideas Competition of Competition of Ideas set as a design
• Consulting Architect for SDP
• Master Development Panning, planning exercise to elucidate the problem
• Subdivision Planning
Program / Project Conceptualization & Development
209
• Urban Design PROFESSIONAL
Comprehensive Development Planning (CDP) Services ARCHITECTURAL Technical Advice, Consultation and/or Counseling
Historic & Heritage Conservation and Planning CONSULTING SERVICES Schematic Design
Methods of Compensation: Teaching, Lecturing, Coaching, Mentoring
Security Evaluation & Planning
 Per Diem / Hourly (PACS) Research & Development
Building System Design
 Retainer Documentation
Facilities Maintenance Support
 ( Salary Cost x Manner of Providing Services Pre-Investment/Pre-Feasibility and Feasibility Studies
Building Testing & Commissioning
Multiplier) + Direct • Professional Consulting Architect (PCA) Marketing & Promotional Studies
Building Environment Certification
Cost / Reimbursable Land Use and Multi-Sectoral Development Planning,
Forensic Architecture
Expenses Development & Management
Building Appraisal
 LS/FF Site Selection, Analyses, Evaluation, Ranking &
Structural Conceptualization
 PCC Development
Preliminary Services
Contract Documentation and Review Services Construction
Post-Design Services Project / Construction Management and/or Administration
(Including Construction Services) Post-Construction Evaluation
Dispute Avoidance and Resolution Monitoring & Evaluation
Architectural Research Methods Training, Capability Building
Special Building/Facility Planning & Design Continuing Professional Education (CPE)
Building Components Capital Investment Programming
Management of Architectural Practices

● IMHOTEP©2015 ● Page 11 of 24 ●
LAWS AFFECTING THE PRACTICE OF ARCHITECTURE LAWS AFFECTING THE PRACTICE OF ARCHITECTURE
IN THE PHILIPPINES IN THE PHILIPPINES
LAWS DATE LAWS DATE

ARCHITECTURE LAWS RA9514 An Act Establishing A Comprehensive Fire Code Of December 19, 2008
The Philippines, Repealing Presidential Decree No.
RA9266 An Act Providing for a More Responsive and March 17, 2004 1185 And For Other Purposes
(34 ) Comprehensive Regulation for the Registration, “Revised Fire Code of the Philippines of 2008”
Licensing and Practice of Architecture, Repealing for
the Purpose Republic Act No. 545, as Amended, PD1185 Fire Code of the Philippines 1977
Otherwise Known as “An Act to Regulate the Practice of
Architecture in the Philippines,” and for Other Purposes RA9263 Bureau of Fire Protection and Bureau of Jail March 10, 2004
Management and Penology Professionalization Act
RA1581 Architecture Law of 1956 June 16, 1956
( 34 – Corporate Practice) BP344 Enhancing the Mobility of Disabled Persons Feb 25, 1983
IRR latest revision April 30, 2005
RA545 Architecture Law of 1950 June 17, 1950
On Housing and Funding
REGULATORY AND ENFORCEMENT LAWS
PD957 Condominium and Subdivision Buyers’ Protective July 12, 1976
RA8981 Professional Regulation Commission Modernization Act December 5, 2000 Decree

PD223 Creating the Professional Regulation Commission June 22, 1973 RA6552 Real Estate Buyers’ Protective Act August 26, 1972

LOI 1000 Letter of Instruction 1000 May 20, 1980 RA4726 The Condominium Act June 18, 1966
“…only PRC accredited bona fide professional organizations, and
their members to organize host, sponsor or represent the Filipino BP220 Standards for Economic and Socialized Housing March 25, 1982
professionals in national, regional and international forums, projects
conferences, conventions where the concerned professions are
involved, AND …all government agencies and any of its RA8763 Home Guarantee Corporation Act March 7, 2000
instrumentalities shall give priority to members of the accredited
EO538 Prescribing the Administration of the Home June 4, 1979
professional organizations in the hiring of its employees and in the Development Mutual Funds
engagement of professional services.”
EO90 Creating the Housing and Urban Development December 17, 1986
RA386 Civil Code of the Philippines June 18, 1949 Coordinating Council
EO546 Creating a Ministry of Public Works and a Ministry of July 23, 1979 RA3469 Allowing the Construction of Multi-Storey Tenement June 16, 1962
Transportation and Communications Housing Projects for the Poor and Homeless
RA7160 Local Government Code of the Philippines October 10, 1991 On Water and Plumbing

RA876 The Philippine Arbitration Law June 19, 1953 RA1378 National Plumbing Code of the Philippines January 28, 1959
latest revision December 21, 1999
DESIGN AND CONSTRUCTION REFERENCE LAWS
On Safety and Protection RA6234 Creating the Metropolitan Waterworks and Sewerage June 19, 1971
System
PD1096 Adopting A National Building Code Of The Philippines Feb 19, 1977
(NBCP) Thereby Revising R.A. No. 6541 RA9286 Latest Amendment to PD198 or Provincial Water April 2, 2004
Utilities Act of 1973
IRR latest revision April 30, 2005
PD1067 Water Code of the Philippines 1977
RA6541 An Act To Ordain And Institute August 26, 1972
A National Building Code Of The Philippines
National Building Code Of 1972

● IMHOTEP©2015 ● Page 12 of 24 ●
LAWS AFFECTING THE PRACTICE OF ARCHITECTURE UAP DOC 301 & NBCP (PD1096)
IN THE PHILIPPINES DAYS ACTION
LAWS DATE • after receipt of any instructions, contractor to inform architect of extra cost for extra work
On Environment Protection through written notice
• after expiration of certificate of completion, make good known defects
15 days
RA9003 Ecological Waste Management Program Law January 26, 2001 • after recognition of delay, contractor to issue a written notice
• from NTP, contractor to submit complete breakdown of work and corresponding value
RA3931 National Water and Air Pollution Control Commission June 18, 1964 • from Request of Payment, architect to issue or withhold certificate of payment
• from approval of Request for Payment & Issuance of payment, owner to pay certified amount
PD1586 Establishing Environmental Impact Statement System 1978
• from date of bidding, contractor to seek architect’s clarification
PD1152 Philippine Environmental Code June 6, 1977 • after request for payment, architect/owner fails to act, contractor may suspend or terminate
work
PD984 Pollution Control Decree 1976 • upon certification of the architect justifying owner’s action, owner to terminate contract
 contractor declares bankruptcy
PD772 Penalizing Squatting And Other Similar Acts 1975  disregard/violate provisions of contract documents / schedule
 fail to provide qualified people & materials
GOVERNMENT SERVICE AND ETHICS LAWS  fail to make payment to sub-contractors, workmen or dealers
• from payment of required fees, issuance of Building Permit
RA8293 Intellectual Property Code of the Philippines June 22, 1997 / • from receipt of advice of the non-issuance, suspension or revocation of permits, file an appeal
January 1, 1998 to the Secretary
PD49 Decree on Intellectual Property November 14, 1972
30 days • after award of arbitration, owner fails to pay contractor, contractor may suspend/terminate
(1 month) work
RA3019 Anti-Graft and Corrupt Practices Act 1961
• certificate of occupancy
RA8974 Law on Acquisition of Right-of-Way, Site or Location for November 7, 2000
• to make good of known defects after issuance of certificate of completion (expiration of
National Government Infrastructure Projects 60 days
(2 Months) performance & payment bond)
RA8439 Magna Carta for Scientists, Engineers, & Researchers December 22, 1997
in the Government 90 days • suspension of work through no act of contractor and employees or order of court
(3 Months) • retention (3 months after acceptance of work)
RA6713 Code of Ethical Conduct of a Public Official and 1972
Employees 120 days • building permit validity
(4 Months) • excavation shall not be left open without work being done
EO525 Responsibility of the Public Estate Authority on February 14, 1979
Reclamation Projects 180 days • suspension of construction exceeds 6 months, the fee for the remaining works shall be
(6 Months) doubled

UAP DOC 301 & NBCP (PD1096) 365 days • contractor’s guarantee bond effectivity
(12 months) • building permit validity if there was no
DAYS ACTION • Construction
• Changes, alterations and repairs may be made provided that in any 12- month period, the
5 days • after written notice, contractor agrees to make repairs to correct defective work value of the work does not exceed 20% of the value of the existing building, and provided that,
• from date of referral, C/M Fire Marshall shall submit recommendations to the BO such changes do not add additional combustible material, and do not, in the opinion of the
Building Official, increase the fire hazard;
7 days • from receipt of notice to proceed, computation of contract time

10 days • before date needed, contractor to make request on drawings & materials
• before beginning, suspending or resuming work, contractor to issue written notice
• before written notice, contractor’s insurance policy will not be cancelled
• before commencing excavation, notify owner of adjoining property

15 days • from date of change order, assertion of claims


● IMHOTEP©2015 ● Page 13 of 24 ●
UAP DOC 301 – GENERAL CONDITIONS IRR OF RA 9266
SIGNIFICANT NUMBER OF YEARS
ARCHITECT, OWNER & CONTRACTOR’S OBLIGATION
15 Years • Civil Liability on plans and specifications of Architect-of-Record under Article 1723 of the
Certificate Of Non Financial Obligation (BY After 65% completion of work, the contractor should (180 Months) Civil Code
CONTRACTOR) present 10 Years • PRBOA Member COR & PID validity qualification and active practitioner
ARCHITECT shall After 98% substantial completion of contract work (120 Months)
• Inspect the project and 5 Years • PRBOA Member should not be a faculty member (at least) prior to nomination
• Issue Certificate Of Completion after (60 Months)
certification 3 Years • Validity of PID
CONTRACTOR will (36 Months) • PRBOA Chairman to hold office
• Finish outstanding work during period of making
2 Years • Diversified Architectural Experience duly certified by RLA (3840 Hours)
good of all known defects of 60 days.
(24 Months) • 1 (one) PRBOA Member to hold office
Owner fails to implement the plan, architect has Architect is entitled to 90% of the Architect’s Fee 1 year • Credited as Diversified Architectural Experience with Master’s Degree
completed the Detail Design & Contract Document Phase (12 Months) • 1 (one) PRBOA Member to hold office

Payments  on work completed minus 10% retention


 When 50% of the contract has been accomplished,
IRR OF PD 1096
NO RETENTION shall be made
 No payment in excess of 65% unless notarized FINES
statement is submitted PHP 5,000 • Light Violations
Performance Bond 15% of contract amount PHP 8,000 • Less Grave Violations
(Guarantee to execute work)
PHP 10,000 • Grave Violations
Payment Bond 15% of Contract amount
(Guarantee to pay obligations)  valid until replacement of Guarantee Bond PENALTIES (Without Building Permit)
10% of Building • Excavation for Foundation
Guarantee Bond 30% of contract amount
Permit Fees
(Guarantee to quality of materials and workmanship) valid up to 1 yr from date of acceptance
25% of Building • Construction of foundation (including pile driving and laying of reinforcing bars)
Overruns and underruns Not to exceed 5% Permit Fees
50% of Building • Construction of superstructure up to 2.00 meters above established grade
If CONTRACTOR’s work is found defective Defray all expenses
Permit Fees
100% of Building • Construction of superstructure above 2.00 meters
If CONTRACTOR’s work is found satisfactory Actual cost of labor and materials plus 15%
Permit Fees

 Estimate and acceptance in lump sum 25% Surcharge • Failure to pay the annual inspection fee within 30 days from prescribed date
Value of EXTRA WORK
 Does not exceed 20% of original contract price PENAL PROVISIONS
 Actual direct cost plus 15%
PHP 20,000 • Any person, firm or corporation who shall violate any of the provisions of the Code and/or
Damage from fire or earthquake, typhoons or any Provided that, the cost of such repair shall not exceed 20% 2 Years or Both commit any act hereby declared to be unlawful
fortuitous event may be repaired, using the same kind of of the replacement cost of the building or structure.
materials of which the building or structure was originally
constructed,

● IMHOTEP©2015 ● Page 14 of 24 ●
IRR OF RA 9266 IRR OF RA 9266
CONTENTS CONTENTS
Rule I 3 01 Title 33 Ownership of Plans, Specifications, t and Other Contract Documents
Title, Policy Rule IV 34 Non-Registered Person Shall Not Claim Equivalent Service
Statement, Definition 02 Statement of Policy Practice of
Positions in Government Requiring the Services of Registered and Licensed
of Terms and Scope Architecture 35
03 Definition of Terms Architects
of Practice (Sundry Provisions)
36 Collection of Professional Fees
Rule II 8 04 Creation and Composition of the Professional Regulatory Board
Professional Limitation to the Registration of a Firm, Company, Partnership, Corporation or
05 Qualification of Members of the Professional Regulatory Board 37
Regulatory Board of Association
06 Term of Office
Architecture (PRBOA) 38 Coverage of Temporary / Special Permits
Organization, Powers 07 Powers and Function of the Board
Liability Insurance of A Person or Entity Allowed to Practice Under Temporary /
and Function Administrative Supervision of the Board, Custodian of its Records, Secretariat & 39
08 Special Permit
Support Services
Rule V 8 40 Integration of the Architecture Profession
09 Grounds for Suspension or Removal of Members of the Board Final Provisions 41 Implementing Rules and Regulations
10 Compensation and Allowances of the Board
42 Appropriations
11 Annual Report
43 Act Not Affecting Other Professionals
Rule III 13 12 Examination Required
44 Enforcement of the Act
Examination, 13 Qualification of Applicant Examination
Registration and 45 Separability Clause
14 Subjects for Examination
Licensure 46 Repealing Clause
15 Rating in the Licensure Examination
47 Effectivity
16 Report of Ratings (within 30 days)
17 Oath
18 Issuance of Certificate of Registration and Professional Identification Card PD 1096 NATIONAL BULDING CODE OF THE PHILIPPINES
19 Roster of Architects
CONTENTS
Rule III 20 Seal, Issuance and Use of Seal (Prescribed by the Board)
Rule I 6 101 01 Title
Examination, Indication of Certificate of Registration / Professional Identification Card and
21 General Provisions 102 02 Declaration of Policy
Registration and Professional Tax Receipt
Licensure 22 Refusal o Issue Certificate of Registration and Professional Identification Card 103 03 Scope and Application
Suspension and Revocation of Certificate of Registration, Professional 104 04 General Building Requirements
23
Identification Card or the Special / Temporary Permit
105 05 Site Requirements
Re-Issuance or Replacement of Revoked or Lost Certificate of Registration,
24 106 06 Definitions
Professional Identification Card or the Special / Temporary Permit
25 Registration of Architects Required Rule II 13 201 07 Responsibility for Administration and Reinforcement
Rule IV 15
Practice of Administration and 202 08 Technical Staff
26 Vested Rights. Architects Registered When This Law Is Passed
Architecture Reinforcement
27 Reciprocity Requirements 203 09 General Powers and Function of the Secretary
(Sundry Provisions)
28 Continuing Professional Development (CPD) 204 10 Professional and Technical Assistance
29 Prohibition in the Practice of Architecture and Penal Clause 205 11 Building Officials
30 Prohibition in the Practice of Architecture 206 12 Qualifications of Building Officials
31 Liability of Representatives and Non-Registered Persons 207 13 Duties and Responsibilities of Building Officials
Signing and Sealing of Architectural Plans, Specifications, Architectural Permit 208 14 Fees
32
and Other Contract Documents
209 15 Exemption
● IMHOTEP©2015 ● Page 15 of 24 ●
PD 1096 NATIONAL BULDING CODE OF THE PHILIPPINES PD 1096 NATIONAL BULDING CODE OF THE PHILIPPINES
CONTENTS CONTENTS
Rule II 210 16 Use of Income from Fees Occupancy 705 50 Allowable Floor Areas
Administration and 211 17 Implementing Rules and Regulations 706 51 Allowable Floor Area Increases
Reinforcement
212 18 Administrative Fines 707 52 Maximum Height of Buildings
213 19 Penal Provisions 708 53 Minimum Requirements for Group A Dwellings
214 20 Dangerous and Ruinous Buildings or Structures 709 54 Requirements for Other Group Occupancies
215 21 Abatement of Dangerous Buildings Rule VIII 11 801 55 General Requirements of Light and Ventilation
216 22 Other Remedies Light and Ventilation 802 56 Measurement of Site Occupancy
Rule III 9 301 23 Building Permits 803 57 Percentage of Site Occupancy
Permits and 302 24 Application of Permits 804 58 Sizes and Dimensions of Courts
Inspection
303 25 Processing of Building Permits 805 59 Ceiling Heights
304 26 Issuance of Building Permits 806 60 Sizes and Dimensions of Rooms
305 27 Validity of Building Permits 807 61 Air Space Requirements in Determining the Size of Rooms
306 28 Non-issuance, Suspension or Revocation of Building Permits 808 62 Window Openings
307 29 Appeal 809 63 Vent Shafts
308 30 Inspection and Supervision of Work 810 64 Ventilation Skylights
309 31 Certificate of Occupancy 811 65 Artificial Ventilation
Rule IV 3 401 32 Types of Construction Rule IX 7 901 66 General Requirements
Types of 402 33 Changes In Types Sanitation 902 67 Water Supply System
Construction
403 34 Requirements on Types of Construction 903 68 Wastewater Disposal System
Rule V 7 501 35 Fire Zones Defined 904 69 Storm Drainage System
Requirements of Fire 502 36 Buildings Located in More Than One Fire Zone 905 70 Pest and Vermin Control
Zones
503 37 Moved Buildings 906 71 Noise Pollution Control
504 38 Temporary Buildings/Structures 907 72 Pipes Materials
505 39 Center Lines of Streets Rule X 8 1001 73 General Requirements
506 40 Restrictions on Existing Buildings Building Projection 1002 74 Projection into Alleys or Streets
Over Public Streets
507 41 Designation of Fire Zones 1003 75 Projection of Balconies and Appendages Over Streets
Rule VI 4 601 42 Fire- Resistive Rating Defined 1004 76 Arcades
Requirements of Fire 602 43 Fire- Resistive Time Period Rating 1005 77 Canopies (Marquees)
Zones
603 44 Fire-Resistive Standards 1006 78 Movable Awnings or Hoods
604 45 Fire- Resistive Regulations 1007 79 Doors, Windows, and the Like
Rule VII 9 701 46 Occupancy Classified 1008 80 Corner Buildings with Chaflans
Classification 702 47 Change in Use
and General
Requirements of All 703 48 Mixed Occupancy
Buildings By Use or 704 49 Location on Property

● IMHOTEP©2015 ● Page 16 of 24 ●
PD 1096 NATIONAL BULDING CODE OF THE PHILIPPINES PD 1096 NATIONAL BULDING CODE OF THE PHILIPPINES
CONTENTS CONTENTS
Rule XI 8 1101 81 General Requirements Rule XVI 9 1601 110 Approved Plastics
Protection of 1102 82 Storage in Public Property Plastics 1602 111 Installation
Pedestrians During
Construction or 1103 83 Mixing Mortar on Public Property 1603 112 Glazing of Openings
Demolition 1104 84 Protection of Utilities 1604 113 Skylights
1105 85 Walkway 1605 114 Light-Transmitting Panels in Monitors and Sawtooth Roofs
1106 86 Pedestrian Protection 1606 115 Plastic Light Diffusers in Ceilings
1107 87 Maintenance and Removal of Protective Devices 1607 116 Partitions
1108 88 Demolition 1608 117 Exterior Veneer
Rule XII 15 1201 89 General Requirements 1609 118 Awnings and Canopies
General Design and 1202 90 Excavation, Foundation, and Retaining Walls Rule XVII 4 1701 119 Sheet Metal Paint Spray Booth
Construction
1203 91 Veneer Sheet Metal Paint 1702 120 Fire Protection
Requirements
Spray Booths
1204 92 Enclosure of Vertical Openings 1703 121 Light
1205 93 Floor Construction 1704 122 Ventilation
1206 94 Roof Construction and Covering Rule XVIII 5 1801 123 General Requirements
1207 95 Stairs, Exits, and Occupant Loads Glass and Glazing 1802 124 Area Limitation
1208 96 Skylights 1803 125 Glazing
1209 97 Bays, Porches, and Balconies 1804 126 Louvered Windows
1210 98 Penthouses and Roof Structures 1805 127 Impact
1211 99 Chimneys, Fireplaces, and Barbecues Rule XIX 3 1901 128 General Rule
1212 100 Fire-Extinguishing Systems The Use of 1902 129 Program Documentation
Computers
1213 101 Stages and Platform 1903 130 Submission of Computer-Generated Computations
1214 102 Motion Picture Projection Rooms Rule XX 6 2001 131 General Requirements
1215 103 Lathing, Plastering, and Installation of Wall Boards The Use of 2002 132 Maintenance
Computers
Rule XIII 2 2003 133 Design and Construction
1301 104 Electrical Regulations
Electrical & 2004 134 Supports and Anchorages
Mechanical
1302 105 Mechanical Regulations 2005 135 Projections and Clearances
Regulations
1401 106 Storage and Handling 2006 136 Lighting
Rule XIV 3
Photographic 1402 107 Classes of Film Exempted Rule XXI 3 2101 137 Separability Clause
and X-Ray Films Final Provisions 2102 138 Repealing and Amending Clause
1403 108 Fire Extinguishing System
1501 109 Prefabricated Assembly 2103 139 Effectivity
Rule XV 1
Prefabricated Annotation: The DPWH published these 2004 Revised Implementing Rules and Regulations (IRR) of P.D. No. 1096 (the 1977 NBCP) on 01, 08
Construction and 15 April 2005 in the Manila Standard Today. These IRR took effect 01 May 2005.

To date, only RLAs can prepare, sign and seal architectural documents, in full accordance with R.A. No. 9266 (The Architecture Act of 2004), its
IRR and derivative regulations and in accordance with this Revised IRR.

APPROVED this 29th of October 2004.


● IMHOTEP©2015 ● Page 17 of 24 ●
PARKING REQUIREMENTS LOADING REQUIREMENTS

TYPE OF OCCUPANCY PARKING REQUIREMENTS TYPE OF OCCUPANCY LOADING REQUIREMENTS

Low income single detached living unit with Pooled parking: 1 slot/10 units Stores, manufacturing, mercantile, wholesale and 1 loading slot for every 5000m² of gross floor
individual lots not more than 100m² the like area (minimum of 1 truck loading slot)

Multi-family living units regardless of no. of 1 slot / 8 units Hotels and hospitals 1 truck loading slot
stories with average living floor area of 50m²
Multi-family living units regardless of no. of 1 slot / 4 units SPECIAL PROVISIONS
stories with average living floor area of above
50m² to 100m² 1 accessible parking lot for 50-150 slots and an additional slot for every 100 thereafter.

Multi-family living units regardless of no. of 1 slot/ unit


stories with average living floor area of more than
100m²
Hotels 1 slot/ 10 rooms
Residential hotels and apartels
Motels
1 slot/ 5 units
1 slot/ unit
Jeremiah 29:11
New King James Version (NKJV)
11
Shopping centers
Markets
1 slot/ 100m²
1 slot/ 150m²
For I know the thoughts that I think
Restaurants,
beerhouses
fast food outlets, bars and 1 slot/ 30m² of customer area toward you, says the LORD, thoughts of
Nightclubs, supper clubs and theater-restaurants 1 slot/ 20m² of customer area peace and not of evil, to give you a future
Office building
Pension/ boarding/ lodging houses
1 slot/ 125m² of gross floor area
1 slot/ 20 beds
and a hope.
Other buildings in business and commercial 1 slot/ 125m² of gross floor area

Matthew 7:7-8
zones
Public assembly buildings 1 slot/ 50m² of spectator area
New King James Version (NKJV)
7
“Ask, and it will be given to you; seek,
Places of worship and funerary parlors 1 slot/ 50m² of congregation area
Elementary schools, secondary schools, 1 slot/ 10 classrooms

and you will find; knock, and it will be


vocational and trade schools
College and universities 1 slot/ 5 classrooms
Hospitals 1 slot/ 25 beds opened to you. 8 For everyone who asks
receives, and he who seeks finds, and to
Bowling alleys 1 slot/ 4 alleys
Amusement centers 1 slot/ 50m² of gross floor area
Clubhouses, beach houses, etc. 1 slot/ 100m² of gross floor area him who knocks it will be opened.
Factories, manufacturing, mercantile, 1 slot/ 1000m² of gross floor area
warehouses and storage bin
Tourist bus parking 2 bus slots/ hotel or theater restaurant

● IMHOTEP©2015 ● Page 18 of 24 ●
TABULATION OF DESIGN STANDARDS
PD 1096 RA 9514 PD 957 BP 220 BP 220 BP 344
SUBJECT
National Building Code and IRR Fire Code of 2008 Subdivision & Condominium Law Economic Housing Socialized Housing Accessibility Law

RESIDENTIAL REQUIREMENTS
Corner Lot Maximum of 90% of the lot
Inside Lot Maximum of 80% of the lot
At least 250 mm thick, 600 mm
Foundation below ground surface
Occupant Load 18.6 sq. m/ person 18.6 sq. m/ person No. of units No. of units
Multiplied by 6 Multiplied by 6
Live Load @ 1st floor At least 200 kg / sqm
Live Load @ 2nd floor At least 150 kg / sqm
Stair Width At least 750 mm 1.10 m 600 mm 600 mm
Stair Riser Max. of 200 mm 180 mm (New) 200 mm 250 mm 250 mm
205 mm (Existing)
230 mm (Fire Escape)
Stair Tread At least 200 mm 280 mm (New) 250 mm 200 mm 200 mm
230 mm (Existing)
230mm (Fire Escape)
Entrance & Exit At least 1 entrance & 1 exit Refer to Fire Code At least 1 entrance & 1 exit At least 1 entrance & 1 exit At least 1 entrance & 1 exit
Specifications (Too many to
tabulate)

LIGHT & VENTILATION


Min. dimension of court 2.00 m N/A 1.50 m 2.00 m 2.00 m
Passageway from Inner Court At least 1.20 m N/A At least 1.20 m At least 1.20 m At least 1.20 m
Min. Ht. Clearance from Firewall 1.00 m above the roof N/A 1.00 m above the roof 1.00 m above the roof 1.00 m above the roof
Headroom Clearance 2.00 m 2.00 m 2.00 m 2.00 m 2.00 m
Min. Ceiling Ht. for Habitable Artificial Ventilation Artificial Ventilation Artificial Ventilation Artificial Ventilation Artificial Ventilation Artificial Ventilation
Rooms 2.40 m 2.00 m 2.40 m 2.00 m 2.40 m 2.40 m
Natural Ventilation Natural Ventilation Natural Ventilation Natural Ventilation Natural Ventilation Natural Ventilation
2.70 m 2.70 m 2.70 m 2.70 m 2.70 m 2.70 m
Min. Ceiling Ht. for Buildings 2.70 m – 1st Storey
2.40 m – 2nd Storey 2.30 m
2.10 m – Succeeding 2.00 m 2.00 m 2.00 m
Storeys 1.80 m - Mezzanine 1.80 m - Mezzanine 1.80 m - Mezzanine
1.80 m – Mezzanine 2.13 m
Sum of Areas of Openings in Less than 50% of total area of Less than 50% of total area of Less than 25% of total area of Less than 25% of total area of
any Storey the wall on that storey the wall on that storey the wall on that storey the wall on that storey
Window Openings At least 10% of the floor area At least 10% of the floor area At least 10% of the floor area At least 10% of the floor area
Eaves over required windows At least 750 mm

● IMHOTEP©2015 ● Page 19 of 24 ●
TABULATION OF DESIGN STANDARDS
PD 1096 RA 9514 PD 957 BP 220 BP 220 BP 344
SUBJECT
National Building Code and IRR Fire Code of 2008 Subdivision & Condominium Law Economic Housing Socialized Housing Accessibility Law
SIZE/ DIMENSION OF ROOMS
Rooms for Human Habitation 6.00 sq. m w/ min. dimension of 18 sq. m for studio unit
2.00 m
Kitchens 3.00 sq. m w/ min dimension of
1.50 m
Toilet & Bath 1.20 sq. m w/ min. dimension of 2.25 sq. m
0.90 m

EXITS
Minimum number 1
Occupant Load of < 10 At least 1 exit At least 2 exits At least 1 exit At least 1 exit At least 1 exit N/A
Occupant Load of 10-499 At least 2 exits N/A At least 2 exits N/A N/A N/A
Occupant load of 500-999 At least 3 exits N/A At least 3 exits N/A N/A N/A
Occupant Load of 1000 At least 4 exits N/A At least 4 exits N/A N/A N/A
Distance to exit WITHOUT Max. of 45 m Max. of 46 m Max. of 45 m Max. of 45 m Max. of 45 m Max. of 45 m
Sprinkle System
Distance to exits WITH Sprinkle Max. of 60 m Max. of 61 m Max. of 60 m Max. of 60 m Max. of 60 m Max. of 60 m
System
Min. exit door width 900 mm 710 mm 900 mm 800 mm 800 mm 800 mm
Min. exit door height 2.00 m 2.00 m 2.00 m 2.00 m 2.00 m 2.00 m
Min. corridor width 1.10 m 1.12 mm 1.10 m 1.20 m 1.20 m 1.20 m
Max. slope of passageway 1:8 N/A 1:8 1:8 1:8
Dead ends Max. of 6.00 m Max. of 6.00 m Max. of 12.00 m Max. of 12.00 m Max. of 12.00 m 3.50 m
Mezzanine Floors >185.00 sqm / >18.00m in any
dimension
2 stairways

DOORS
Occupant Load of < 10 At least 1 exit At least 2 exits At least 1 exit At least 1 exit At least 1 exit
Swing
Width 900mm 910mm 900mm 800mm 800mm 800mm
Height 2000mm 2000mm 2000mm 2000mm 2000mm 2000mm

● IMHOTEP©2015 ● Page 20 of 24 ●
TABULATION OF DESIGN STANDARDS
PD 1096 RA 9514 PD 957 BP 220 BP 220 BP 344
SUBJECT
National Building Code and IRR Fire Code of 2008 Subdivision & Condominium Law Economic Housing Socialized Housing Accessibility Law
STAIRWAYS FOR BUILDINGS
Min. stair width:
750 mm <2000 Persons
Occupant load of 10-below
1120mm
Min. stair width: 600 mm 600 mm
900 mm
Occupant load of 10-50
>2000
Min. stair width: 1420mm
1100mm
Occupant load of 50 - above
Riser 200 mm 180 mm (New) 200 mm 200 mm 200 mm
205 mm (Existing)
230 mm (Fire Escape)
Tread 250 mm 280 mm (New) 250 mm 250 mm 250 mm
230 mm (Existing)
230mm (Fire Escape)
Distance bet. Landings 3.60 m 2.75 m (Class A) 3.60 m 3.60 m 3.60 m
3.70 m (Class B)
Dimension of Landings in the Equal to the width of the 1.12 m Equal to the width of the Equal to the width of the Equal to the width of the
direction of travel stairway stairway stairway stairway
Height of Handrails 800-900 mm 760-865 mm 800-1200 mm 800-1200 mm 700-900 mm
from the nosing above the surface of thread above the surface of thread above the surface of thread from the floor
Minimum Headroom 2000 mm 2000 mm 2000 mm 2000 mm 2000 mm 2000 mm

Maximum Height Between 3660 mm


Landings

SIDEWALKS & ARCADES


Min. of width of sidewalk 1/6 of R.O.W 0.60m to 1.00m 0.60m to 1.20m 0.50m to 1.20m 0.50m to 1.20m 1.20 m
0.60m to 1.00m
Planting Strip 0.20m to 1.20m 0.20m to 1.20m 0.40m to 1.30m 0.40m to 1.30m 0.40m to 1.30m
800 mm for sidewalks
 2.00 m in width

LOT FRONTAGES
Single Detached
a. Corner Lot 12.00 m 8.00 m 8.00 m
c. Irregular Lot 10.00 m 8.00 m 8.00 m
b. Regular Lot 6.00 m 4.00 m 4.00 m
d. Interior Lot 3.00 m 3.00 m 3.00 m
Duplex/Single Attached 8.00 m 6.00 m 6.00 m
Row Houses 4.00 m 4.00 m 3.50 m
● IMHOTEP©2015 ● Page 21 of 24 ●
TABULATION OF DESIGN STANDARDS
PD 1096 RA 9514 PD 957 BP 220 BP 220 BP 344
SUBJECT
National Building Code and IRR Fire Code of 2008 Subdivision & Condominium Law Economic Housing Socialized Housing Accessibility Law
DRIVEWAYS, ENTRANCES & EXITS
Slope of entryway 1:3 or 1:4 1:3 or 1:4
Max. slope of ramps 1:8 (w/o handrail) 1:12 (Max.) 15% 15% 1:12
1:10 (w/ handrail) 1:48 (Max. Cross Slope) Max. length 6.00 m
w/o landing
Minimum Width of Ramps 1120 mm
Maximum Rise for a single 760 mm
Ramp Run

OPEN SPACE REQUIREMENTS


Interior Lot 50% (A, B, C, D & J) 50% (A, B, C, D & J) 50% (A, B, C, D & J) 50% (A, B, C, D & J)
20% (E, F, G, H & I) 20% (E, F, G, H & I) 20% (E, F, G, H & I) 20% (E, F, G, H & I)
Inside Lot 20% (A, B, C, D & J) 20% (A, B, C, D & J) 20% (A, B, C, D & J) 20% (A, B, C, D & J)
15% (E, F, G, H & I) 15% (E, F, G, H & I) 15% (E, F, G, H & I) 15% (E, F, G, H & I)
Corner Lot 10% (A, B, C, D & J) 10% (A, B, C, D & J) 10% (A, B, C, D & J) 10% (A, B, C, D & J)
5% (E, F, G, H & I) 5% (E, F, G, H & I) 5% (E, F, G, H & I) 5% (E, F, G, H & I)
Through Lot 10% (A, B, C, D & J) 10% (A, B, C, D & J) 10% (A, B, C, D & J) 10% (A, B, C, D & J)
5% (E, F, G, H & I) 5% (E, F, G, H & I) 5% (E, F, G, H & I) 5% (E, F, G, H & I)
Corner-Through Lot 5% 5% 5% 5%
for all Group Occupancies for all Group Occupancies for all Group Occupancies for all Group Occupancies

Corner Lot Abutting 3 Or More 5% 5% 5% 5%


Streets, Alleys, Rivers, Etc. for all Group Occupancies for all Group Occupancies for all Group Occupancies for all Group Occupancies
End Lot 30% - 50% 30% - 50% 30% - 50% 30% - 50%
(A, B, C, D & E-2) (A, B, C, D & E-2) (A, B, C, D & E-2) (A, B, C, D & E-2)
20% - 50% 20% - 50% 20% - 50% 20% - 50%
(H-1, H-2, H-4, I, E-1, E-3) (H-1, H-2, H-4, I, E-1, E-3) (H-1, H-2, H-4, I, E-1, E-3) (H-1, H-2, H-4, I, E-1, E-3)

SETBACKS
Low Density Residential 4.50 m Front As per PD1096 (NBCP)
(R-1) 2.00 m Side
2.00 m Rear
Medium Density Residential Basic / Maximum As per PD1096 (NBCP)
(R-2) 3.00 m / 8.00 m Front
2.00 m Side
2.00 m Rear
High Density Residential Basic / Maximum As per PD1096 (NBCP) 1.50 m Front 1.50 m Front
(R-3) 3.00 m / 8.00 m Front 1.50 m Side 1.50 m Side
2.00 m Side 2.00 m Rear 2.00 m Rear
2.00 m Rear

● IMHOTEP©2015 ● Page 22 of 24 ●
TABULATION OF DESIGN STANDARDS
PD 1096 RA 9514 PD 957 BP 220 BP 220 BP 344
SUBJECT
National Building Code and IRR Fire Code of 2008 Subdivision & Condominium Law Economic Housing Socialized Housing Accessibility Law
PARKING
Size of Parking Slot 2.50 x 5.00 m 2.50 x 5.00 m 2.50 x 5.00 m 2.50 x 5.00 m 3.70 x 5.00 m
(Perpendicular & Diagonal) (Perpendicular & Diagonal) (Perpendicular & Diagonal) (Perpendicular & Diagonal)
2.15 x 6.00 (Parallel) 2.00 x 6.00 m 2.00 x 6.00 m 2.00 x 6.00 m
3.60 x 12.00 m (Parallel) (Parallel) (Parallel)
(Standard Truck)
3.60 x 18.00 m
(Articulated Truck)
3.00 x 9.00 m
(Jeepney / Shuttle)
Low-income single detached Pooled Parking Pooled Parking Pooled Parking Pooled Parking
living units w/ individual lot size 1 slot / 10 units 1 slot / 10 units 1 slot / 10 units 1 slot / 10 units
not more than 100 sq. m
50 sq. m below 1 slot / 8 units 1 slot / 8 units
50-100 sq. m 1 slot / 4 units 1 slot / 4 units 1 slot / 20 units 1 slot / 20 units
100 sq. m above 1 slot / 1 unit 1 slot / 1 unit

MINIMUM LOT SIZES


Single Detached 301.00 sqm 120.00 sqm 72.00 sqm 64.00 sqm
(Interior & Inside Lot) (Open Market)
365.00 sqm 100.00 sqm
(Corner, Through, Corner-Through (Medium Cost)
Lot)
548.00 sqm
(End Lot)
Duplex / Single Attached Basic / Maximum 96.00 sqm 54.00 sqm 48.00 sqm
80.00 sqm / 192.00 sqm (Open Market)
(Inside Lot) 80.00 sqm
96.00 sqm / 261.00 sqm (Medium Cost)
(Corner, Through, Corner-Through
Lot)
140.00 sqm / 378.00 sqm
(End Lot)
Row Houses Basic / Maximum 60.00 sqm 36.00 sqm 28.00 sqm
(20 Units per Block) 50.00 sqm / 400.00 sqm (Open Market)
(100 m Max. Length) (Inside Lot) 50.00 sqm
75.00 sqm / 475.00 sqm (Medium Cost)
(Corner, Through, Corner-Through
Lot)
200.00 sqm / 700.00 sqm
(End Lot)

● IMHOTEP©2015 ● Page 23 of 24 ●
PHILIPPIANS 4:6-7
The Message (MSG)
6-7
Don’t fret or worry. Instead of worrying, pray. Let petitions and praises shape your worries into
prayers, letting God know your concerns. Before you know it, a sense of God’s wholeness, everything
coming together for good, will come and settle you down. It’s wonderful what happens when Christ
displaces worry at the center of your life.

PROVERBS 16:3
New King James Version (NKJV)
3
Commit your works to the LORD,
And your thoughts will be established.

JEREMIAH 17:7-8
Living Bible (TLB)
7
But blessed is the man who trusts in the Lord and has made the Lord his hope and confidence. 8 He
is like a tree planted along a riverbank, with its roots reaching deep into the water—a tree not
bothered by the heat nor worried by long months of drought. Its leaves stay green, and it goes right on
producing all its luscious fruit.

● IMHOTEP©2015 ● Page 24 of 24 ●

Potrebbero piacerti anche