Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
A RESTROOM WALL
CHB (10mm x 200mm x 400mm) UNIT 413.00 14.00 5,782.00
PORTLAND CEMENT BAG 36.00 240.00 8,640.00
SCREENED SAND CU.M. 3.00 630.00 1,890.00
10mm REINF. STEEL BAR LNGTH. 36.00 148.00 5,328.00
TIE WIRE KG. 3.00 63.00 189.00
E RESTROOM FIXTURES
WATER CLOSET UNIT 3.00 4,000.00 12,000.00
URINAL UNIT 1.00 4,000.00 4,000.00
FLOOR DRAIN 4" UNIT 7.00 53.00 371.00
LAVATORY SINK WITH FITTINGS UNIT 2.00 1,700.00 3,400.00
FAUCET UNIT 7.00 220.00 1,540.00
PIPE, FITTINGS AND ACCESSORIES (L.S.) LOT 1.00 15,000.00 15,000.00
F LIGHTING FIXTURES
7W T8 LED LAMP UNIT 15.00 245.00 3,675.00
9W LED PINLIGHT UNIT 3.00 150.00 450.00
SINGLE GANG SWITH UNIT 7.00 63.00 441.00
TWO GANG SWITCH UNIT 3.00 100.00 300.00
TWO GANG OUTLET UNIT 7.00 100.00 700.00
WIRING, PIPE AND FITTINGS (L.S.) LOT 1.00 10,000.00 10,000.00
H CONTINGENCIES
CONTINGENCIES
I LABOR COST
LABOR LOT 1.00 50,000.00
Prepared by:
ALDRENE ROBERT S. BADILLA
Project Architect
11/16/2017
RIALS/ESTIMATE SHEET
SHEET NO.:
1 OF 1
TOTAL
21,829.00
22,280.00
4,790.00
4,630.00
36,311.00
15,566.00
30,960.00
20,000.00
50,000.00
206,366.00
DATE
BILL OF MATERIALS/ESTIMATE SHEET
TOTAL COST
Prepared by:
SHEET NO.:
1 OF 1
TOTAL
7,850.00
26,220.00
34,070.00
DATE
BILL OF MATERIALS/ESTIMATE SHEET
A FRAMING MATERIALS
25mm G.I. PIPE LNGTH 1.00 600.00 600.00
1.2mm X 20mm X 20mm ANGLE BAR LNGTH 1.00 650.00 650.00
WELDING ROD KG 1.00 80.00 80.00
B FINISHING MATERIALS
3/4 MARINE PLYWOOD SHT 1.00 720.00 720.00
1" FLATHEAD SCREW (METAL) PC 1.00 700.00 700.00
COLORED FORMICA SHT 2.00 450.00 900.00
RUBBER EDGING MTR 2.00 910.00 1,820.00
RUBBER STOPPER (FOR 25mm PIPE) PC 1.00 400.00 400.00
C CONTINGENCIES
CONTINGENCIES LOT 1.00 570.00
C LABOR
LABOR COST LOT 1.00 4,000.00
TOTAL COST
Approved:
ROSELYN P. CARLOS
President
2/27/2018
RIALS/ESTIMATE SHEET
SHEET NO.:
1 OF 1
TOTAL
1,330.00
4,140.00
570.00
4,000.00
10,040.00
4.45M G.I. PER CHAIR
2.625M ANGLE BAR PER CAHIR
.02KG PER P 20PCS WELDING ROD PER CHAIR
A FRAMING MATERIALS
1" X 2.0mm G.I. PIPE LNGTH 37.00 700.00 25,900.00
2mm X 3/4" X 3/4" ANGLE BAR LNGTH 22.00 220.00 4,840.00
WELDING ROD BOX 1.00 1,900.00 1,900.00
B FINISHING MATERIALS
3/4 MARINE PLYWOOD SHT 9.00 900.00 8,100.00
1" FLATHEAD SCREW (METAL) PC 750.00 0.50 375.00
COLORED FORMICA SHT 9.00 990.00 8,910.00
RUBBER EDGING MTR 260.00 195.00 50,700.00
RUBBER STOPPER (FOR 25mm PIPE) PC 300.00 10.00 3,000.00
METAL PRIMER GAL 1.00 400.00 400.00
C CONTINGENCIES
CONTINGENCIES LOT 1.00 12,495.00
D LABOR
LABOR COST LOT 1.00 41,650.00
TOTAL COST
Approved:
ROSELYN P. CARLOS
President
2/28/2018
RIALS/ESTIMATE SHEET
SHEET NO.:
1 OF 1
TOTAL
32,640.00
71,485.00
12,495.00
41,650.00
158,270.00
4.45M G.I. PER CHAIR 222.5 37.083333
2.625M ANGLE BAR PER CAHIR 131.25 21.875
.02KG PER P 20PCS WELDING ROD PER CHAIR 20 1
2,915.50
BOX
DATE
BILL OF MATERIALS/ESTIMATE SHEET
A FRAMING MATERIALS
1" X 1.5mm SQUARE TUBE LNGTH 50.00 700.00 35,000.00
10mm SQUARE BAR LNGTH 7.00 150.00 1,050.00
WELDING ROD BOX 1.00 1,900.00 1,900.00
B FINISHING MATERIALS
3/4 MARINE PLYWOOD SHT 9.00 900.00 8,100.00
1" FLATHEAD SCREW (METAL) PC 850.00 0.50 425.00
RUBBER STOPPER (25mm SQ. TUBE) PC 300.00 25.00 7,500.00
METAL PRIMER GAL 2.00 400.00 800.00
EPOXY ENAMEL GAL 2.00 1,100.00 2,200.00
EPOXY REDUCER GAL 1.00 500.00 500.00
TIMBERCOAT (GLOSS) GAL 1.00 600.00 600.00
C CONTINGENCIES
CONTINGENCIES LOT 1.00 6,969.00
D LABOR
LABOR COST LOT 1.00 23,230.00
TOTAL COST
Approved:
ROSELYN P. CARLOS
President
2/28/2018
RIALS/ESTIMATE SHEET
SHEET NO.:
1 OF 1
TOTAL
37,950.00
20,125.00
6,969.00
23,230.00
88,274.00
5.8M SQ.TUBE PER CHAIR 300 50
.8M SQUARE BAR PER CAHIR 40 6.6666667
.02KG PER P 20PCS WELDING ROD PER CHAIR 20 1
1,626.10
BOX
DATE
BILL OF MATERIALS/ESTIMATE SHEET
A FRAMING MATERIALS
1 1/2" X 1 1/2 " X 3.0mm ANGLE BAR LNGTH 50.00 600.00 30,000.00
1" x 3.0mm FLAT BAR LNGTH 7.00 200.00 1,400.00
WELDING ROD BOX 1.00 1,900.00 1,900.00
B FINISHING MATERIALS
3/4 MARINE PLYWOOD SHT 9.00 900.00 8,100.00
1" FLATHEAD SCREW (METAL) PC 850.00 0.50 425.00
RUBBER STOPPER (25mm SQ. TUBE) PC 300.00 25.00 7,500.00
METAL PRIMER GAL 2.00 400.00 800.00
EPOXY ENAMEL GAL 2.00 1,100.00 2,200.00
EPOXY REDUCER GAL 1.00 500.00 500.00
TIMBERCOAT (GLOSS) GAL 1.00 600.00 600.00
C CONTINGENCIES
CONTINGENCIES LOT 1.00 6,500.00
D LABOR
LABOR COST LOT 1.00 22,000.00
TOTAL COST
Approved:
ROSELYN P. CARLOS
President
3/15/2018
RIALS/ESTIMATE SHEET
SHEET NO.:
1 OF 1
TOTAL
33,300.00
20,125.00
6,500.00
22,000.00
81,925.00
5.8M SQ.TUBE PER CHAIR 300 50
.8M SQUARE BAR PER CAHIR 40 6.6666667
.02KG PER P 20PCS WELDING ROD PER CHAIR 20 1
1,508.50
BOX