TIME TABLE

安装项目名称
1 大炉炉体组装
2 水淋加平台焊接
3 大烟囱旋转梯、平台、栏杆等
4 大炉支架平台整体结构框架
5 铺板 做夹层 梯层 栏杆 压炉
6 换热器两组安装
7 放铅放渣炉门
8 炉顶加料 烧嘴 油管道
9 所有大炉烟道制作闸门防护
10 输送机
11 除尘两组制作安装
13 换热器至水淋链接管道
14 大烟囱安装
15 水淋至除尘链接管道
16 轨道安装
17 除尘进出口安装
18 破碎拼装 平台 爬梯
19 除尘风机烟囱链接管道安装
20 压力罐安装2个
21 精炼炉壳安装
22 精炼平台
23 破碎压滤机及管道 输送上部平台
24 球磨机安装
TIME TABLE
Installation Project
Furnace Bodies
30 pipe water spray tower and platform
 Steel Chimney rolling ladder/platform/ handrail and so on
Furnace Platform With about supporting
bed board/ interlayer/handrail/pressure furnace for furnace bodies
40 tube heat exchanger
Lead door and slag materials door Rail for slag&lead
Feeding Equip./ Feeding Box/Feed Box Base/ Casing drum
Indoor Gas Flue Sys./Outdoor Gas Flue Sys.
ULAB Conveyor
Pulse dust remover
pipeline between 30 pipe water spray tower and 40 tube heat exchanger
 Steel Chimney
pipeline between 30 pipe water spray tower and Pulse dust remover
Rails
Inlet&outlet for Pulse dust remover
Breaker/ Breaker Base/ladder stand
 Dust-removing fan / Exhauster / pipeline to the steel Chimney
Air Tank
The Cover of Refine equipment
The platform of Refine equipment
Breaker/Filter Pressure/pipeline/First-stage Conveyor
Ball Mill
Deadline 截止日期 days时间天数
20171008 8
20171009 9
20171021 13
20171028 7
20171105 7
20171108 30
20171109 4
20171115 6
20171123 8
20171206 13
20171206 28
20171208 2
20171208 2
20171210 2
20171218 10
20171219 9
20180107 20
20171223 4
20171224 4
20180117 25
20180122 5
20170122 15
20180124 2
计划时间表TIME TABLE (2017 Nov 1-7)
Construction works Deadline days People
编号 安装项目名称
截止日期 时间 负责人
Concrete work: Road,1st - 9th pillars
围厂路混凝土浇筑 1柱-9柱 Technical requirements: 1.Length 80 m, width 8m, thickness 30cm;
技术要求:长大约80米 宽8米 厚度30cm,每隔6米为一段,每50cm 2.Use sand and stone as base, Watering and compaction coefficient of 96%.
1 下一根钢筋(∅16mm*60cm)按巴方提供的消防图纸下水管; 先用 20171107 8 Adan
插捣振动棒振动,再使用振动梁振动最后用磨光机; 基础砂石垫层 3.Separate each 6m;
,喷水并压实系数96%; 4.Each 50 cm put a rebar(∅16mm*60cm); Start with concrete vibrating
rob; then use the vibrating beam finally with power float concrete;
Breaker Room--ditch/Compacting/Concrete
2 破碎车间-挖沟/土地平整/混凝土浇筑 11柱-20柱 20171107 8 Adan
技术要求:地坪 30CM 不需要垫层 11th - 20th pillars
Technical Requirements: thickness 30cm, no low cement concrete
water spray tower+heat exchanger foundation
水淋塔基础扩大并浇筑+换热器基础 Water spray tower-excavation, concrete according to old one standard
3 (注水 震压 垫层 钢筋 混凝土) 20171107 8 Adan
不需要打垫层其他和老的水淋塔基础一样 Heat exchanger-Spray water/ vibration/low cement concrete/steel bars/
concrete
Road concrete work front of the Administration building
4 办公室前路面水泥浇筑—从大门到办公室水泵部分 20171107 8 Adan
From the front door to the water pump near the Administration buliding
地坪 25CM 不需要垫层
Technical Requirements: Thickness 25 cm , no low cement concrete
5 配电室 Generator Room Concrete work 20171107 8 Adan
6 脱硫池第四层浇筑 The fourth layer concrete work of de-sulf foundation 20171107 8 Adan