CIVE 423 HMW 2

Problem 2:

b.
Problem 4:

Activity Duration IPA Lag ES EF LS LF TF FF


A 5 - 0 5 5 0 0 0
B 6 A 5 11 11 5 0 0
C 4 A 3 8 12 13 9 1 0
D 5 A 5 10 11 6 1 0
E 9 B 11 20 22 13 2 2
F 7 B,C 2 13 20 20 13 0 0
G 6 C 12 18 22 16 4 4
H 8 C,D 4 14 22 23 15 1 0
I 3 D 10 13 26 23 13 12
J 7 E,G,F 2 22 29 29 22 0 0
K 4 F,G,H 22 26 27 23 1 0
L 1 H,I 3 25 26 27 26 1 0
M 2 K,L 26 28 29 27 1 1
Problem 5:

Critical path is shown in red.


Sample calculation:
ES(3) = ES(2) + lag = 2 +1 = 3
LS(3) = ES(3) + duration = 4
LF(3) = LS(4) = 4
LS(3) = LF(3) – duration = 3
TF(3) = LS(3) – ES(3) = 0
FF(3) = ES(4) – EF (3) = 0

Primavera output:
Problem 6:

Critical path is shown in red.


Sample calculation:
FF(B) = minlag (BE,BD) = min (2,0) = 0
TF(B) = min ( TF(E) + lag EB , TF(D) + lag ED) = min (2,14) = 2
LF (B) = EF (B) + TF (B) = 10 +2 = 12
Bar chart:

Primavera output