METHOD STATEMENT

EXCAVATION

1. GENERAL
This works consist of the excavation , including all necessary handling, hauling to
disposal area and shaping and trimming in accordance with locations, lines, levels, grades
and dimension shown on the drawing.
In accordance with the Earth Moving Plan approved, material result from excavation
should be disposed to disposal area with hauling distance from 0 m'. Payment Item in this
section is II-1-3, II-1-4, II-1-5.

2. SCOPE OF WORKS

The scope of works for execution of excavation consist of some steps as description
below:
a. Staking out installation
b. Execution of excavation

The scope of the works on this method statement covers as below :


BOQ Description of Works Unit
SECTION II LEMPUING SECONDARY CANAL, SECTION-2
II-1.3 Excavation for embankment without hauling distance (less m3
than 0.1 km)
II-1.4 Excavation for embankment including transportation to m3
embankment site
SECTION II LEMPUING SECONDARY CANAL, SECTION-2
III-1.3 Excavation for embankment without hauling distance (less m3
than 0.1 km)
III-1.4 Excavation for embankment including transportation to m3
embankment site
SECTION IV DRAINAGE CANAL, BLOCK-F
IV-1.2 Excavation of drainage canal m3
IV-1.3 Excavation for structures m3

1
3. SEQUENCE OF EXCAVATION WORK
Sequence of Excavation work execution following the chart as below :

Material Start Inspection Form


Equipment Main Check
Item
Confirming Area of
Excavation and Check location Form AU-01
installing (finishing) of stakes and
stakes (ex. @10m) EL., slope
gradient
1
For Embankment Form EX-01:
Canal
Form EX-02:
Canal Borrow Structure
Structure Form Ex-04:
Borrow

Disposa
Exc. <0.1km w/hauling Disposal l area
BD
EX
DT Check moisture Check
Water content (wf) : moisture
tank everyday content

if Dry ≒Wopt if Wet


(-2~+3%)

Spray Dry-up
water

to Embankment Stock Pile


Site (if necessary)

Slope Berm width


Canal: 1:1.5 or 1.0m Check soil
BD as CDWG @3m high condition
EX Structure 1:0.5 or0.5m Suitable/Unsuitable
DT as CDWG @3m high for Embankment

Design
EL?
Structure

CPT Form EX-


02A
2

End Final Inspection


4. DETAIL OF WORKS (EXECUTION & METHOD)

In accordance with the scope of works as description above, the sequence of execution of
the work is:
1. Stake out installation accordance with the working drawing for right of way limit,
installled at cross section accordance with the added profile with installed .
2. Execution of the works

5. TIME SCHEDULE
In accordance with the construction method, quantity of the works include eith the number
or composition used, hence time schedule fo execution of the work is:
BOQ DESCRIPTION OFWORKS DEC’12 JUL’13
II-1.3 Excavation for embankment
without hauling distance (less
than 0.1 km)
II-1.4 Excavation for embankment
including transportation to
embankment site
III-1.3 Excavation for embankment
without hauling distance (less
than 0.1 km)
III-1.4 Excavation for embankment
including transportation to
embankment site
IV-1.2 Excavation of drainage canal
IV-1.3 Excavation for structures

6. EQUIPMENT REQUIREMENT FOR EXCAVATION WORK


No EQUIPMENT TYPE/CAP TOTAL UNIT
1 Excavator 0.8 m3 bucket 2
2 Bulldozer 24 T 2
3 Dump Truck 12 T 8

7. SAFETY CONTROL

For safety control of the execution the work around, safety control should be carry out as
following:
1. Contractor will take assumed actions require to utilize to protect areal work from
things able to bother work fluency and which can endanger / destroy environment
around work location.
3
2. Sign board Installation should be carry out at selected location especially village road
and access road intersection
3. Full responsibility by General Suprintendent for safety control and he has authority to
stop the works, if necessary, if the working condition is not safe.

8. Responsible Person

No Name of Person at site Position


1 Agung Susilo Supervisor
2 Basuki Surveyor

4
TABLE OF CONTENS

Page

1. General ......................................................................................................................... 1
2. Scope of Works ........................................................................................................... 1
3. Sequence of Earthworks .............................................................................................. 2
4. Detail of Works ........................................................................................................... 3
5. Time Schedule .............................................................................................................. 3
6. Equipment Requipment for Land Clearing and Grubbing .......................................... 3
7. Quality Plan ................................................................................................................. 3
8. Responsible .................................................................................................................. 4

Potrebbero piacerti anche