Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
PROJECT COST
MANAGEMENT
Asoka Perera
Construction Engineering and Management Division
Department of Civil Engineering
University of Moratuwa
1 © Asoka Perera
Project Cost Management
Project Management Knowledge areas
2 © Asoka Perera
Project Cost Management
Overview of lecture
4 © Asoka Perera
Project Cost Management
Cost Management :OVERVIEW
Project Cost Management includes the
processes involved in
Cost Estimating – developing an approximation of the
costs of the resources needed to complete project
activities.
Cost Budgeting – aggregating the estimated costs of
individual activities or work packages to establish a cost
baseline.
Cost Control – influencing the factors that create cost
variances and controlling changes to the project budget.
5 © Asoka Perera
Project Cost Management
Cost Management :OVERVIEW
6 © Asoka Perera
Project Cost Management
Cost Management :OVERVIEW
7 © Asoka Perera
Project Cost Management
Some Videos
8 © Asoka Perera
Project Cost Management
1.0 Project Cost Estimating
9 © Asoka Perera
Project Cost Management
1.0 Project Cost Management
10 © Asoka Perera
Project Cost Management
1.0 Cost Estimating - Inputs
11 © Asoka Perera
Project Cost Management
1.0 Cost Estimating - Inputs
12 © Asoka Perera
Project Cost Management
1.0 Cost Estimating - Inputs
15 © Asoka Perera
Project Cost Management
1.0 Cost Estimating - Inputs
16 © Asoka Perera
Project Cost Management
1.2 Cost Estimating – Tools and Techniques
17 © Asoka Perera
Project Cost Management
2 Project Cost Management
Approximate Cost Estimating
Approximate estimates might be regarded as
having an accuracy of more or less 20%;
House – per m2 as Rs.40,000
School per child
Hospital per bed
Road per km
Water tank per m3
We will do an example under Assignment
18 © Asoka Perera
Project Cost Management
2 Project Cost Management
2.6 Preliminary Cost Estimating
civil engineers require preliminary estimates at the
‘sketch plan’ or ‘outline proposal’ stage to address the
evolving scheme design and ultimately agree on an
outline cost plan with the client.
Preliminary estimates are used to help determine the
relative costs of alternative designs or alternative
scheme proposals to address a client's need(s), and
thus guide the team in deciding on a (practicable)
detailed design.
19 © Asoka Perera
Project Cost Management
2 Project Cost Management
2.6 Preliminary Cost Estimating: Elemental
Division
• 1. Substructure - Demolition, site clearance,
earthworks, foundations
• 2. Superstructure Frame, floors, roof, external walls
• 3. Internal finishes Wall, floor, ceiling
• 4. Fittings and fixtures Internal architecture, painter
work
• 5. Services Sanitary, water, heating, air-
conditioning, mechanical and electrical services
• 6. External works Site organisation, drainage,
20
minor works © Asoka Perera
Project Cost Management
1.2 Cost Estimating – Tools and Techniques
21 © Asoka Perera
Project Cost Management
1.2 Cost Estimating – Tools and Techniques
23 © Asoka Perera
Project Cost Management
2 Project Cost Management
24 © Asoka Perera
Project Cost Management
1.3 Cost Estimating – Outputs
26 © Asoka Perera
Project Cost Management
2.0 Cost Budgeting – Inputs
27 © Asoka Perera
Project Cost Management
2.1 Cost Budgeting – Inputs
29 © Asoka Perera
Project Cost Management
2.2 Cost Budgeting – Tools and Techniques
32 © Asoka Perera
Project Cost Management
2.3 Cost Budgeting – Outputs
33 © Asoka Perera
Project Cost Management
2.3 Cost Budgeting – Outputs
35 © Asoka Perera
Project Cost Management
2.3 Cost Budgeting – Outputs
36 © Asoka Perera
Project Cost Management
3.0 Cost Control – Overview
37 © Asoka Perera
Project Cost Management
3.0 Cost Control – Overview
39 © Asoka Perera
Project Cost Management
3.1 Cost Control – Inputs
41 © Asoka Perera
Project Cost Management
3.2 Cost Control – Tools and Techniques
42 © Asoka Perera
Project Cost Management
3.2 Cost Control – Tools and Techniques
43 © Asoka Perera
Project Cost Management
3.2 Cost Control – Tools and Techniques
44 © Asoka Perera
Project Cost Management
COST CONTROL
Systems in Current Use
Earned Value Technique
Earned value analysis involves calculating
five values for each activity or summary
activity from a project’s WBS
Five main variables are:
• The Planned Value(PV, Earlier BCWS);
• The Earned Value(E V, Earlier BCWP);
• The Actual Costs(AC, Earlier ACWP);
• The Cost Variance (CV,);
• The Schedule Variance (SV);
45 © Asoka Perera
Project Cost Management
COST CONTROL
Systems in Current Use
Earned Value Technique
Five main variables are:
• The Planned Value(PV, Earlier BCWS);
• Planned Value is how much the project should
cost to get to a specific point in the schedule.
• For example, if a project has a budget of
Rs.100,000 and month six represent 40% of the
project work, the PV for month six is Rs.40,000/=.
Planned Value used to be known as the Budget
Cost of Work Schedule (BCWS)
46 © Asoka Perera
Project Cost Management
COST CONTROL
Systems in Current Use
Earned Value Technique
Five main variables are:
• The Earned Value(E V, Earlier BCWP);
• Earned Value is representative of the work
completed to date regardless of how it took to
accomplish it.
• For example, if a project has a budget of
Rs.100,000 and the work completed to date
represents 25% of the entire project work, its EV
is Rs.25,000/=. Earned Value used to be known
as the Budgeted Cost of Work Performed (BCWP)
47 © Asoka Perera
Project Cost Management
COST CONTROL
Systems in Current Use
Earned Value Technique
Five main variables are:
• The Actual Costs(AC, Earlier ACWP);
• Actual Costs is the actual amount of monies the
project has required to date.
• For example, if a project has a budget of
Rs.100,000 and Rs.35,000/= has been spent on
the project to date, the AC of the project would
be Rs.35,000/=. This was earlier know as Actual
Cost of Work Performed (ACWP)
48 © Asoka Perera
Project Cost Management
COST CONTROL
Systems in Current Use
Earned Value Technique
Five main variables are:
• The Cost Variance (CV,);
• A Cost Variance occurs when the actual cost of
the project work is more than or less than EV.
• For example, EV is calculated to be Rs.25,000/=,
but you had spend Rs.35,000/= to get there. As
such the Cost Variance (CV) is Rs.10,000/=.
49 © Asoka Perera
Project Cost Management
COST CONTROL
Systems in Current Use
Earned Value Technique
Five main variables are:
• The Schedule Variance (SV);
• A Schedule Variance occurs when the EV is less
than the PV.
• For example, the project is supposed to be worth
Rs. 40,000/= in month six; however, at month six
your EV is only Rs.25,000/=. You have got SV of
Rs.15,000/=
50 © Asoka Perera
Project Cost Management
COST CONTROL
Systems in Current Use
Earned Value Technique
TERM FORMULA
Earned Value EV, Budgeted Cost of Work Performed (BCWP) =
budgeted cost to date X percent complete
Cost Variance CV = EV — AC(actual cost of work performed)
Schedule Variance SV = EV — PV
Cost Performance Index CPI = EV/AC
Schedule Performance Index SPI = EV/PV -
Budget at Completion BAC = Total Budget
Estimate at Completion EAC = BAC/CPI
Estimate to Complete ETC = EAC - AC
Variance at Completion VAC = BAC -EAC
51 © Asoka Perera
Project Cost Management
3.2 Cost Control – Tools and Techniques
3.2.3 Forecasting
Use of Earned Value
• ETC based on new estimate.
• ETC based on atypical variances
• EAC using a new estimate
• using remaining budget
• EAC using CPIC
52 © Asoka Perera
Project Cost Management
3.2 Cost Control – Tools and Techniques
53 © Asoka Perera
Project Cost Management
3.2 Cost Control – Tools and Techniques
54 © Asoka Perera
Project Cost Management
3.3 Cost Control – Outputs
55 © Asoka Perera
Project Cost Management
3.3 Cost Control – Outputs
Thank you
59 © Asoka Perera