2.a) Explain the essential factors which influence the selection of site for a hydro electric
plant.
b) With the neat diagrams, explain the following with respect to hydro power plant.
(i)Penstock (ii)Surge tank (iii)Tail race
c) A hydro electric power station is supplied from a reservoir having an area of 50km2
and a head 50m. If the overall efficiency plant is 60%, find the rate at which the water
level fall when the station is generating 30,000kW
3.a) Explain the principle of operation of heavy water cooled (CANDU) type reactor.
b) Explain the functions of the following in a nuclear reactor. (i)Control rod
(ii) Moderator (iii)Reflector (iv)Shielding
c) Discuss the factors to be considered for the selection of site for a nuclear power
plant.
OR
4.a) Draw the schematic diagram of a thermal power station and briefly explain the
function of each.
b) Sketch and explain working of boiling water reactor and enumerate the advantages
and disadvantages.
5.a) Draw the flow diagram of a diesel power station and discuss its operation, 10
b) Discuss the merits and demerits of a diesel power plant. 4
c) Discuss the advantages and disadvantages of a gas turbine power plant.
OR
7.a) A domestic consumer has 10lamps of 40w. each connected in his house. His
demand is given as follows:
Midnight to 5am — 40watt
5am to 6pm — No load
6pm to 7pm — 320watt
7pm to 9pm — 360watt
9pm to 12 midnight — 160watt
Plot the load curve. Determine: (a)Average load
(b)Maximum load
(c)Load factor
(d)Energy consumption during one day
b) Discuss the advantages of interconnection of power stations
c) Define the terms: (a) Plant use factor
(b) Plant utilization factor
(c) Demand factor
OR
OR
10.a) W hat are the advantages of neutral grounding
b) With the help of neat sketch explain
(i)Single bus bar arrangement with bus sectionalize
15
(ii) Ring bus bar arrangement
(iii)Resonant grounding
C t