ETS & SUB-STATION WORK - La Plage Project

Doc. Submission Status


SRN Procedure Name
Type Date
Reference Number
1 MS Installation of Submersible Pumps 10-Feb-18 under review
2 MS Installation of Drainage/Vent piping & Accesso. 10-Feb-18 under review
3 MS Installation of Ventilation & Air Conditioning System 10-Feb-18 under review
4 MS Testing & Commissioning of Ventilation & Air Conditioning System

5 MS Installation of FM200 System


6 MS Testing & Commissioning of Ventilation & Air Conditioning System
7 MS Testing & Commissioning of FM 200
8 MS Testing & Commissioning of Drainage System
New
Consultant comment Submission Status
date
Submission Status New
SRN Dra. Type DWG TITLE Submission Status
Date
Reference Number date
ETS ROOM

UCE-LPS-SDW-ETS-AC-6300-001 HEX- HVAC EQUIPMENT INSTALLATION 12-Feb-18 C 12-Mar-18


1SD DETAILS
2SD UCE-LPS-SDW-ETS-AC-6300-002 HEX- HVAC EQUIPMENT SCHEDULE
3SD UCE-LPS-SDW-ETS-AC-6300-101 HEX ROOM 1 - HVAC LAYOUT 12-Feb-18 C 12-Mar-18
4SD UCE-LPS-SDW-ETS-AC-6300-102 HEX ROOM 2 - HVAC LAYOUT 12-Feb-18 C 12-Mar-18
5SD UCE-LPS-SDW-ETS-AC-6300-103 HEX ROOM 3 - HVAC LAYOUT 12-Feb-18 C 12-Mar-18

UCE-LPS-SDW-ETS-AC-6300-101A HEX ROOM 1 - HVAC SECTION DETAILS 12-Feb-18 C 12-Mar-18


6SD LAYOUT

UCE-LPS-SDW-ETS-AC-6300-102A HEX ROOM 2 - HVAC SECTION DETAILS 12-Feb-18 C 12-Mar-18


7SD LAYOUT

UCE-LPS-SDW-ETS-AC-6300-103A HEX ROOM 3 - HVAC SECTION DETAILS 12-Feb-18 C 12-Mar-18


8SD LAYOUT

UCE-LPS-SDW-ETS-FF-6500-001 GENERAL NOTES LEGEND AND DETAILS 12-Feb-18 B


9SD - FIRE FIGHTING

UCE-LPS-SDW-ETS-FF-6500-101 HEX ROOM 1 - FIRE FIGHTING LAYOUT 12-Feb-18 B


10 S D
UCE-LPS-SDW-ETS-FF-6500-102 HEX ROOM 2 - FIRE FIGHTING LAYOUT 12-Feb-18 B
11 S D
UCE-LPS-SDW-ETS-FF-6500-103 HEX ROOM 3 - FIRE FIGHTING LAYOUT 12-Feb-18 B
12 S D
UCE-LPS-SDW-ETS-PL-6600-001 GENERAL NOTES LEGEND AND DETAILS 28-Feb-18
13 S D - PLUMBING & DRAINAGE

UCE-LPS-SDW-ETS-PL-6600-101 HEX ROOM 1 - PLUMBING & DRAINAGE 12-Feb-18 C 12-Mar-18


14 S D LAYOUT

UCE-LPS-SDW-ETS-PL-6600-102 HEX ROOM 2 - PLUMBING & DRAINAGE 12-Feb-18 C 12-Mar-18


15 S D LAYOUT
UCE-LPS-SDW-ETS-PL-6600-103 HEX ROOM 3 - PLUMBING & DRAINAGE 12-Feb-18 C 12-Mar-18
16 S D LAYOUT

SUBSTATION

UCE-LPS-SDW-SS-AC-6300-001 SUBSTATION EQUIPMENT TYPICAL 28-Feb-18


17 S D INSTALLATION DETAILS

UCE-LPS-SDW-ETS-AC-6300-101 SUBSTATION 1 ROOM HVAC LAYOUT 28-Feb-18


18 S D
UCE-LPS-SDW-ETS-AC-6300-102 SUBSTATION 2 ROOM HVAC LAYOUT 28-Feb-18
19 S D
UCE-LPS-SDW-ETS-AC-6300-103 SUBSTATION 3 ROOM HVAC LAYOUT 28-Feb-18
20 S D
UCE-LPS-SDW-ETS-AC-6300-104 SUBSTATION EQUIPMENT SCHEDULES
21 S D
UCE-LPS-SDW-ETS-FF-6400-107 GENERAL NOTES LEGEND AND DETAILS-
22 S D FIRE FIGHTING

UCE-LPS-SDW-ETS-FF-6400-108 SUBSTATION 1 OOREDOO ROOM-FM200


23 S D DETAILS

UCE-LPS-SDW-ETS-FF-6400-109 SUBSTATION 2 OOREDOO ROOM-FM200


24 S D DETAILS

UCE-LPS-SDW-ETS-FF-6400-110 SUBSTATION 2 OOREDOO ROOM-FM200


25 S D DETAILS
Remarks

subjected to material approval


subjected to material approval

BY Supplier

BY Supplier

BY Supplier

BY Supplier
Ets & Sub- Station Works - La Plage Project

Material Submittals

SRN Title Supplier Make Date STATUS LPO ETA on Site

1 Submersible pump Al ALI XYLEM, ITELY 15-Feb-18 UR


2 Split Ac Mannai Toshiba, thailand 21-Feb-18 UR
3 Exhasut Fan SYSTEMAIR SYATEMAIR 10-Feb-18 UR
4 VCD KMC KMC 24-Feb-18 UR
5 Louvers KMC KMC 24-Feb-18 UR
6 Sound Attnuators KMC KMC 24-Feb-18 UR
7 UPVC Drainage pipe Q-PLAST Q-PLAST 24-Feb-18 UR

UR- Under Review


Ets & Sub- Station Works - La Plage Project

Procurement Status Report

SRN Title Supplier Make LPO


1
2
3
4
ct

ETA on Site
27-Feb-2018
Mechanical Submittal Sheet

Submitted Submitted
TYPE Total Balance
(%)
Total Status
A 0
B 4
Shop Drawing 25 14 11 56%
C 10
UR 0
A 0
Material B 0
15 7 8 47%
submittal C 0
UR 7
A 0
B 1
Pre -
1 1 0 100%
Qualification C 0
UR 0
A 0
Method B 0
8 3 5 38%
Statement C 0
UR 2