Sei sulla pagina 1di 8

J Fail. Anal. and Preven.

(2008) 8:564–571
DOI 10.1007/s11668-008-9183-0

TECHNICAL ARTICLE—PEER-REVIEWED

Failure Analysis of Stacker-cum-Reclaimer in Ore Handling Plant


S. Ghosal Æ D. Misra Æ T. K. Saha Æ D. Chakravorty Æ
B. Chaudhuri

Submitted: 12 May 2008 / Accepted: 18 September 2008 / Published online: 15 November 2008
 ASM International 2008

Abstract A catastrophic failure of a Stacker-cum- Keywords Stacker-cum-Reclaimer  Root cause


Reclaimer led to loss of several days of service in one ore failure analysis  Fatigue  Impact loading
handling plant in India. The failure was severe enough to
initiate an investigation into the possible causes of failure
and estimation of the residual life for other units of Introduction
Stacker-cum-Reclaimer of the same design and age,
working in the plant. The failure analysis included a visual The present study pertains to the failure analysis of a
inspection of the failed structure, metallographic studies, Stacker-cum-Reclaimer (Fig. 1) and assessment of the
static stress and stability analysis under normal operating residual life of the other working units of the same design
conditions, stress analysis for a possible impact load on the at an ore handling plant in India. It has been reported that
structure, experimental stress analysis, and fatigue life one unit failed while in operation, causing the entire
cycle analysis. The results obtained indicate that the failure counterweight structure to fall. The material collapsed near
could be caused by an impact load arising out of some the junction of the pylon and the counterweight structure.
operational conditions resulting from the conditions of the A few other similar units are still in operation. Hence, a
rail track on which the machine travels. The material thorough study has been carried out to ascertain the pos-
properties, the physical conditions of the material, and a sible causes of failure and to estimate the residual life of
fatigue analysis indicate that the existing system can work other similar structures that are still in operation. This
for several more decades, provided some checkpoints are paper presents the root cause failure analysis.
planned and instituted to monitor the health of the structure The Stacker-cum-Reclaimer in the plant conveys coal/
at regular intervals. iron ore from the box tippler house where railway wagons
unload the materials from mines and stacks them on either
side of the rail track. The same system also reclaims
material from the stacking using rotary buckets and con-
veyors (Fig. 1) and transports material by conveyor belt to
the ships for loading and eventual dispatch. The boom that
S. Ghosal (&)  D. Misra  T. K. Saha is used for stacking as well as reclaiming can be moved in a
Department of Mechanical Engineering, Jadavpur University, horizontal plane (slewing) over a total angle of 210. As
Kolkata 700032, India per the design, the worst operating conditions for the sys-
e-mail: sujit.ghosal@gmail.com
tem are when the boom is operating in a direction
D. Chakravorty transverse to the rail longitudinal direction. The accident
Department of Civil Engineering, Jadavpur University, also took place when the system was reclaiming material
Kolkata 700032, India with its boom operating in the transverse direction.
Figure 2 shows the condition of the system after the acci-
B. Chaudhuri
Department of Materials and Metallurgical Engineering, dent, and Fig. 3 gives a closer view of the portion of the
Jadavpur University, Kolkata 700032, India structure that collapsed.

123
J Fail. Anal. and Preven. (2008) 8:564–571 565

Root Cause Failure Analysis

Strategies for Analyses

The possible reasons for failure are considered to be one or


combination of the following:
• Reduction in the thickness at the failed portion
• Deterioration of mechanical properties of the materials
of construction
• Exceeding the life cycle time with respect to fatigue
loading
• Any abnormal loading conditions that occurred during
operation
Fig. 1 Stacker-cum-Reclaimer for handling of iron ore
For the purpose of accomplishing the job, the following
procedural steps were conducted.
1. Visual inspection of the site, the failed structure, and
the units in operation
2. Metallographic analyses of samples from the failed
structure and determination of mechanical properties
of the material
3. Analytical study for the stability and stresses on the
structure under conditions of normal loading
4. Impact load analysis of the structure
5. Experimental stress analysis on the structure under
actual loading conditions
6. Fatigue analysis

Observations upon Visual Inspection Fig. 2 View of the failed Stacker-cum-Reclaimer highlighting the
derailment

A preliminary study was made by inspecting the site to


assess the nature of failure and the types of loading during
normal operating conditions. This was followed by study of
the engineering and operation of the system. The opera-
tional manual for the system, relevant drawings, and design
data were studied for subsequent analyses, while vital
inputs were obtained through interactions with various
technical personnel of the plant.
It was observed that the failed structure had been
derailed and was displaced in a transverse direction by
about a meter (Fig. 2). It was evident that the loading/
unloading boom was almost at its extreme slewing position
(transverse to the rail) when the structure failed. Such a
condition of operation seems to be critical from a stability
viewpoint.
The locations of the material failures were found to be
near the junction of the pylon and the counterweight boom Fig. 3 Failed portion of the pylon structure
(Fig. 3). It was further observed visually that the type of
failure was ductile. the structure were affected by corrosion to some extent.
The site is close to the seashore (about 25 km away); Most of the corrosion appeared to be in the form of pitting
upon visual inspection, it was apparent that a few areas in and was limited to the surfaces.

123
566 J Fail. Anal. and Preven. (2008) 8:564–571

Metallographic Analyses of a Sample of the Failed Hardness test was carried out on the base plate using a
Structure Brinell hardness tester applying 3000 kg load with 10 mm
diameter steel ball indenter. Five spots were prepared for
A portion of the bulged failed plates (including the weld testing, and all the results come within HB 190–200. No
bead) of the hoist was cut and taken to laboratory for significant difference in hardness values was observed near
metallurgical investigation. The surface of the sample the weld; however, the size of the Brinell indentation could
shows the presence of uniform light brown scale. A crack mark a low hardness in the heat-affected zone.
was observed in the base metal along the parting line of A tensile test sample was prepared from the base plate
weld and base metal. The following tests were carried out portion and tested in a universal testing machine. The
on samples removed from the plate: results were:
• Ultrasonic • Yield stress: 320 MPa
• Dye penetration • Ultimate tensile stress: 653 MPa
• Ultrasonic thickness measurements • Elongation: 34.3%
• Hardness
Chemical analysis. Drilled borings were taken from the
• Tensile
base plates tested for chemical composition by wet analy-
• Chemical analysis
sis. The results of this analysis are given in Table 1.
• Metallography
Metallography. A sample was cut from the failed por-
Observations were as follows. tion of the structure. The cross section of the sample was
Ultrasonic tests to detect internal flaws on the base plate polished and etched using a 1% nital solution. The etched
were made using a microprocessor-based search unit with surface was observed under an optical microscope. The
10 mm diameter, 4 MHz, dual probe. The sensitivity level microstructure of the base plate showed a predominantly
was set on 1.5 mm, and no significant indication of a dis- ferrite matrix with some pearlite (Fig. 4a and b). No sig-
continuity was observed on the base plate. nificant variation in microstructure from surface to core has
Dye penetration tests were carried out on the surfaces of been observed. The weld zone showed more pearlite than
the sample to detect the presence of surface discontinuities the base metal. The structure of the weld zone was not
on the sample. A magnaflux red dye penetrant was used, and homogeneous (Fig. 4c). However, no significant indica-
the penetrant remover and developer were compatible with tions of corrosion or intergranular attack were observed.
the red dye. Other than the crack that had been visually The grains of the microstructure were oriented as expected
observed by the side of the weld line, no significant indi- for rolled plate.
cation of discontinuities was observed on the entire surface.
Ultrasonic thickness gauging was carried out on dif-
Table 1 Chemical composition of the base plate near the zone
ferent locations of the base plate to measure the remaining of failure
thickness of the base plate at different locations. The
Composition, wt.%
ultrasonic thickness tester used to measure the thickness
had an accuracy level of ±0.1 mm. The maximum thick- C Mn Si S P
ness observed was 12.6 mm, and the minimum in the
0.19 0.84 0.31 0.043 0.039
bulging portion of the plate was 12.3 mm.

Fig. 4 Microstructure of the sample taken from failed portion

123
J Fail. Anal. and Preven. (2008) 8:564–571 567

Analysis. The chemistry and physical properties of the


base plate conform to those of a standard structural steel. B C
No significant effects of any thermal excursion or of cor-
rosion were observed. Bulging of the plate is assumed to 45°

have occurred as an effect of overloading. No significant 61.2°

metallurgical discontinuities were observed and the weld


Box tower
appeared normal.

13.5m

13m
6.16
+1= 4.08t
2
Structural Analysis of Box Tower (Pylon)

6m
of Stacker–cum-Reclaimer for Stress and Stability 57.6° 13.5m
A O
For the purpose of analysis, various data were taken from
the operation manual, drawings of the structure, and rele- Boom of hoisting triangle
vant standards. Mechanical properties necessary for the
analysis were taken from test results obtained from a por- Fig. 5 Frame structure of the hoisting mechanism for analysis
tion of the plate.
Based on the values of maximum bulk density of iron
ores during handling, the rated stacking capacity, belt
45.4°
speed, and the length of the conveyor on the boom, the
maximum load on the conveyer belt will correspond to a 6t = F4 15t
stacking time equal to the time a belt section takes to travel
26.6°
the boom length, which works out to be 9.33 s. The max-
18°
imum stacking capacity is 800 m3/h and the rate of loading C
on the belt is 600 kg/s; hence, the maximum static load on
the conveyer belt becomes 5600 kg. 10% more is taken to
account for self-weight of the system, and the maximum
load on the conveyor boom becomes 6160 kg. 15m
The weight of bucket wheel is 675 kg, and the total Z
weight of the bucket wheel assemblage is approximately D
1000 kg, including self-weight and load of materials in the
active buckets. The authors refer to Fig. 5 and 6 and carry
X
out stress analysis for the structure. Applying the appro- 6m
priate criterion, the authors determine that the maximum
stress, as developed at the root, D, is 27.38 MPa.
For yield stress of 320 MPa, the permissible stress in
O
compression is 185 MPa [1]. So, the factor of safety with
respect to the permissible compressive stress under normal Fig. 6 Forces on the structure
conditions becomes 6.76.
The counterweight boom (CD) section is a hollow box The axial load acting on the counterweight boom (cal-
with 1800 9 1800 mm2 outer dimension and of thickness culated as 11,000 kg) is much less than this, and hence the
12.5 mm having radius of gyration (k) of 729.78 mm [2]. boom is safe from buckling failure.
So, the slenderness ratio = leq/k = 2 9 6000/729.78 =
16.44, assuming fixed-free end conditions of vertical pylon. Stress Analysis of the Structure under Conditions
Critical slenderness ratio is computed as 111.07, and hence the of Impact Loading
structure is considered to be a short column. Critical load is
calculated using Johnson’s formula [3] for short column, as: Calculation of Bending Stress
" #
r l 2 Referring to Fig. 6 for the analysis, the bending stress at D
yield eq
Pcr ¼ ryield A I  ðEq 1Þ was determined as follows. The authors took a free fall of
4pE k
the structure from the rail to the ground, height of the rail
or, above the ground being 0.3 m. They considered the
counterweight mass and the tension of the wire at C to be
Pcr ¼ 38; 480 kg acting at a point at the end of the counterweight boom.

123
568 J Fail. Anal. and Preven. (2008) 8:564–571

Axial Stress due to Impact

Developed direct stress = rd = 1.23 MPa (obtained from


l static analysis as above):
 rffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffi
2heq
E, I raxial impact ¼ rd 1 þ 1 þ ðEq 5Þ
dd
m
u rd L
dd ¼ ¼ 0:037 mm
E
heq ¼ Vx2 =ð2 gÞ ¼ 60:1 mm

y Therefore,
 rffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffi
2heq
Fig. 7 Definition sketch for impact analysis raxial impact ¼ rd 1 þ 1 þ ¼ 71:347 MPa
dd
Resultant normal stress due to impact = rimpact =
The differential equation for the deflection of a beam under rbjimpact ? raxial_impact = 763.327 MPa. Developed shear
an impact load [4] is given by: stress = f = 2.07 MPa carried only by webs (same as in
y þ ky ¼ 0
m€ ðEq 2Þ the static analysis).
The above set of direct and shear stresses can give rise
Figure 7 shows the corresponding geometric model and
to the worst principal stress caused by impact loading,
the relevant parameters. The general solution of this
which is given by:
becomes: rffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffi
h . iffi 
y ¼ a cos xn t þ b sin xn t ðEq 3Þ rprincipal ¼ f2 þ r2impact 4 þ rimpact 2 ðEq 6Þ
where the symbols have their usual meaning.
With proper initial conditions, the maximum deflection rprincipal = 763.328 MPa, which is greater than the ulti-
at C due to impact loading is found from Eq 2 as: mate tensile strength of the material (653 MPa). Therefore
 3 0:5 if, under some circumstances, the structure is subjected to a
mL force acting transverse to the rail longitudinal direction,
dmax ¼ Vz ðEq 4Þ
3EI there is a chance that the wheels come off the rails. When
this happens the drop gives rise to an impact load, and the
where m is the equivalent mass corresponding to the force
stress generated thereby will be very high and is sufficient
acting at C perpendicular to CD, and Vz is the component
to cause a possible failure of the pylon structure.
of velocity in z-direction, as shown in Fig. 5, when the
wheels strike ground. Experimental Stress Analysis
 
m ¼ ð15; 000 cos 26:6  6000 cos 45:4 Þ kg ¼ 9200 kg
Online strain measurements are carried out at some selec-
Now, CD = L = 6 m, E = 200 9 109 Pa. I (moment of
ted locations near the junctions of the counterweight
area of the box structure of the counterweight pylon) =
structure and the pylon. The surfaces are properly cleaned
4.76 9 10-2 m4. h (height of rail above ground) = 0.3 m.
and ground, and a pair of strain gauges are properly glued
P = net force at C acting perpendicular to AC = 9200 kg.
pffiffiffiffiffiffiffiffi to the plate structure at each location to obtain strain in two
Velocity of fall = V = 2gh = 2.426 m/s. So, Vz =
mutually perpendicular directions. Half-bridge, tempera-
2.169 m/s and Vx = 1.086 m/s. Therefore, the maximum
ture-compensating-type strain gauges are used for the
deflection (at C) due to impact loading, dmax 18.09 mm.
purpose [5]. Measurements are carried out continuously for
Now, the deflection at C due to static loading is given by,
all possible conditions of stacking and reclaiming, slewing
L3 (horizontal rotational traversing), and luffing (traversing in
dstatic ¼ P ¼ 0:683 mm
3EI vertical plane), and the strains at various locations have
Bending stress ¼ rb ¼ 26:11 MPa been monitored with help of a multichannel recorder.
Figure 8(a) shows the physical form and the bridge circuit
ðobtained from static analysis)
used for the purpose, while Fig. 8(b) shows strain gauges
dmax being laid onto the pylon structure. Two gauges are laid
Bending stress due to impact ¼ rbjimpact ¼ rb
dstatic side by side, but only one is fastened to the strained sur-
¼ 691:98 MPa face, the other is used for temperature compensation.

123
J Fail. Anal. and Preven. (2008) 8:564–571 569

Conductive strip

Direction of Direction of
strain strain
Mica Connection

Calibrated Active strain gauge


adjustment
Supply voltage
AC or DC

Fig. 9 Definition diagram for cyclic load with nonzero mean stress
To null indicator

Passive
strain gauge The type of loading on the structure is one of cyclic, but
nonreversing type (Fig. 9). We now proceed to determine
the safe working stress for a given period of loading under
the cyclic condition. For the purpose of analysis, opera-
tional frequency of 24 cycles a day has been considered.
Taking a life span of 50 years, the total number of cycles
becomes 438,000. This becomes a long cycle design for the
structure.
The following data from test results carried out on the
samples from the failed structure are considered for the
analysis:
Ultimate tensile strength ðSut Þ ¼ 653 MPa
Yield pointðryield Þ ¼ 320 MPa
From S–N curve for completely reversed axial stress
Fig. 8 (a) Bridge circuit for strain gauge. (b) View of strain gauges under specified test conditions [6], the fatigue limits are
fitted on pylon structure given by:
Sf j103 cycles ¼ 0:86Sut
Se j  106 cycles ¼ 0:506Sut
The strain data have been subsequently processed with
appropriate gauge factor (fractional change of resistance We consider a loading frequency of 360 cycles per day
divided by the change in strain) to arrive at the stresses and a working life of 25 years, giving N = 3,285,000
induced at the relevant locations. These stress values cor- cycles, which is more than 106, and hence one takes the
respond to the amplitude of fluctuating stress as a result of limiting value of endurance limit from S–N diagram as,
loading the conveyor boom over the steady component of S0f ¼ Se j  106 cycles = 330.418 MPa for completely reversed
stress caused by static loading due to the self-weight and cyclic stress under ideal test conditions.
moments of all members. The maximum of the stress We modify this value by incorporating various factors
values as calculated from the strain data is 9 MPa. as:
S0e ¼ Ka Kb Kc Kd S0f ðEq 7Þ
Fatigue Analysis
where S0e is the effective endurance limit and Ka, Kb, Kc,
and Kd are surface finish factor, size factor, reliability
Fatigue analysis for the structure has been carried out to
factor, and modifying factor, respectively.
investigate any possibility of fatigue failure of the struc-
A surface finish factor, Ka of 0.55 for a hot-rolled sur-
ture. The data required for this have been obtained from the
face with ultimate strength of 653 MPa may be taken with
following sources:
some degree of reliability [6]. A size factor, Kb = 0.558, a
• Tests carried out on the failed structure reliability factor of Kc = 0.753 (based on a reliability of
• Experimental stress analysis through strain-gauge mea- 99.9%), the modifying factor, Kd = (to take care of effect
surements conducted on Stacker-cum-Reclaimer while of stress concentration) = 0.465 (considering the diameter
in operation of the bolt is equal to half the pitch on the bolted joint at the
• Results of theoretical analyses of the structure pylon-counterweight boom junction).

123
570 J Fail. Anal. and Preven. (2008) 8:564–571

Therefore, Table 2 Computed safety factors


S0e ¼ Ka Kb Kc Kd S0f ¼ 35:51 MPa Criteria Factor of safety

Minimum stress; rmin ¼ 27:38 MPa Goodman line 4.52


ðfrom theoretical analysis) Gerber line 5.44
Soderberg 3.63
Maximum stress; rmax ¼ 38 MPa Langer 8.000
ðfrom theoretical analysis)

For the purpose of fatigue analysis, rmin = 30 MPa and


rmax = 42 MPa. Therefore, reduction of stress, rr = Table 3 Recommended safety factors [7]
12 MPa (from theoretical analysis). From strain gauge Conditions of the system under load Factor of safety
measurements, reduction of stress, rr = 9 MPa. For the
Reliable materials, under well known loading 1.25–1.50
purpose of fatigue analysis, we take the larger value as
Well-known materials under reasonably 1.50–2.00
rr = 12 MPa. Therefore, the amplitude of stress, ra = constant environmental conditions,
(rmax - rmin)/2 = 6 MPa. easy to compute stresses
From the type of loading, maximum stress is equal to Average materials, ordinary environments, 2.00–2.50
steady stress, that is: loads, and stresses can be determined
rmean ¼ ðrmax þ rmin Þ=2 ¼ 36 MPa Less tried materials, brittle materials, average 2.50–3.00
conditions of load and stresses
With these data, we can proceed to construct Goodman Untried materials, average conditions 3.00–4.00
diagram (Fig. 10) to obtain the endurance limit for a of loads or stresses
fluctuating load without complete reversal of stress Known materials, not average conditions 3.00–4.00
of loads or stresses
(nonzero mean stress). However, in the present
Impact forces 3.00–6.00
calculation, algebraic forms, suitable for machine
computation, for solving the diagram have been used.
Fatigue factor of safety are calculated according to Gerber that Goodman line criteria (usually recommended) has a
line, yield line (Langer line), Goodman line, and Soderberg safety factor equal to 4.52. So, under the circumstances, it is
line criteria. Table 2 compares the calculated values of felt that the Stacker-cum-Reclaimer has been working with
factor of safety based on different criteria, as mentioned. adequate factor of safety with theoretically infinite life.
Table 3 furnishes data on recommended factor of safety
under various conditions [7]. We consider situations of
‘‘known materials with not average conditions of loads or Observations and Remarks
stresses’’ as there could be corrosion-induced stress caused
by the harsh atmospheric conditions prevailing at the plant From the foregoing static analysis, it is observed that the
site and suggest a safety factor range of 3–4. It is observed stress induced in the critical pylon area, as shown in Fig. 1
and 2, is only 27.38 MPa, with a factor of safety of 6.76
syt with respect to the allowable compressive stress.
Metallographic analyses suggest that the material
Yield line properties correspond to those of structural quality steel.
The welded portion also does not show any significant
deterioration in material property. The nature of the failure
Alternating stress σa

se does not indicate a fatigue failure (absence of typical beach


Gerber line
marks). There has been no significant decrease in thickness
of the structure as measured in the sample taken from the
Goodman line failed portion. There is also no sign of corrosion crevice.
sG
From the fatigue analysis, it may be said that the sys-
A
Soderberg line
tems have an infinite cycle life, with the cycle of loading
per day as considered for the analysis. So, the failure
appears to not be caused by fatigue failure, which is also
0 corroborated from metallographic analyses.
0 sm syt sut
Mean stress σm It is noted from the working manual of the system that it
is subjected to the most severe operating condition, from a
Fig. 10 Goodman diagram for cyclic loading stability viewpoint, when the loading boom works

123
J Fail. Anal. and Preven. (2008) 8:564–571 571

transverse to the rail axial direction, which has also been properties and normal service stresses showed that normal
the actual condition of operation when the structure failed. operating conditions would not cause overload or fatigue
A visual inspection of the site revealed that the entire failures, and that this failure was caused by the derailment,
structure came off the rails as a result of a possible huge not vice versa. This analysis, therefore, showed that the
force in the direction transverse to the rails caused by the other units of the same design should be safe to operate.
particular condition of operation. This force might have Additionally, the result suggests that the rails should be
derailed the structure, possibly giving rise to a huge evaluated to determine the cause of the derailment failure.
bending moment on the pylon caused by impact force of
the counterweight. As a matter of fact, the impact force
analysis shows that, under such circumstances, the struc-
ture would fail near the pylon-counterweight boom References
junction (root of the cantilever). Therefore, one may con-
1. Code of Practice for General Construction in Steel, IS 800, Bureau
clude that operational conditions caused the structure to of Indian Standards, Table 5.1, Clause 5.1.1, 39 (1984)
come off the rails, and that the free fall caused the accident. 2. Code of Practice for General Construction in Steel, IS 800, Bureau
of Indian Standards, Table 5.2, Clause 5.2.2, 41 (1984)
3. Web site: http://www.engineersedge.com/column_buckling/column_
ideal.htm
Conclusions 4. Web site: http:/www.tech.plymouth.ac.uk
5. Holman, J.P.: Force, Torque and Strain Measurements, Chap. 10.
The catastrophic failure of a Stacker-cum-Reclaimer was In: Experimental Methods for Engineers, McGraw-Hill, New York
the result of operational conditions that caused the machine (2001)
6. Shigley, J., Mischke, C.: Failure Analysis from Variable Loading,
to derail, and the impact load from the derailment caused Chap. 7. In: Mechanical Engineering Design, Tata McGraw-Hill,
the structure to collapse near the junction of the pylon and New Delhi, India (2001)
the counterweight structure. Analysis of the material 7. Web site: www.ame.arizona.edu/courses/324b/l21.pdf

123

Potrebbero piacerti anche