Sei sulla pagina 1di 17

7.

INSPECTION AND TEST PROCEDURES

7.6 Circuit Breakers


1. Low-Voltage
1. Insulated Case/Molded Case

1. Visual and Mechanical Inspection

1. Compare nameplate data with drawings and


specifications.

2. Inspect circuit breaker for correct mounting.

3. Operate circuit breaker to insure smooth operation.

4. Inspect case for cracks or other defects.

5. Inspect all bolted electrical connections for high


resistance using one of the following methods:

1. Use of low-resistance ohmmeter in accordance


with Section 7.6.1.1.2 (Electrical Tests).

2. Verify tightness of accessible bolted electrical


connections by calibrated torque-wrench
method in accordance with manufacturer’s
published data or Table 10.12.

3. Perform thermographic survey in accordance


with Section 9.

6. Inspect mechanism contacts and arc chutes in


unsealed units.

2. Electrical Tests

1. Perform a contact-resistance test.

2. Perform an insulation-resistance test at 1000 volts dc


from pole-to-pole and from each pole-to-ground with
breaker closed and across open contacts of each
phase

*Optional
58 ATS – 1999
7. INSPECTION AND TEST PROCEDURES

7.6 Circuit Breakers (cont.)


1. Low-Voltage (cont.)
1. Insulated Case/Molded Case (cont.)

3. Perform resistance measurements through all bolted


connections with low-resistance ohmmeter, if
applicable, in accordance with Section 7.6.1.1.1 (Visual
and Mechanical Inspection).

*4. Perform insulation resistance tests at 1000 volts dc on


all control wiring. Do not perform the test on wiring
connected to solid state components.

5. Perform adjustments for final settings in accordance


with coordination study supplied by owner.

6. Perform long-time delay time-current characteristic


tests by passing 300 percent rated primary current
through each pole separately unless series testing is
required to defeat ground fault functions.

7. Determine short-time pickup and delay by primary


current injection.

8. Determine ground-fault pickup and time delay by


primary current injection.

9. Determine instantaneous pickup current by primary


injection using run-up or pulse method.

10. Verify correct operation of any auxiliary features such


as trip and pickup indicators, zone interlocking,
electrical close and trip operation, trip-free, and
antipump function.

*11. Verify the calibration of all functions of the trip unit by


means of secondary injection.

*Optional ATS – 1999 59


7. INSPECTION AND TEST PROCEDURES

7.6 Circuit Breakers (cont.)


1. Low-Voltage (cont.)
1. Insulated Case/Molded Case (cont.)

3. Test Values

1. Compare bolted connection resistance to values of


similar connections.

2. Bolt-torque levels should be in accordance with Table


10.12 unless otherwise specified by manufacturer

3. Microhm or millivolt drop values shall not exceed the


high levels of the normal range as indicated in the
manufacturer’s published data. If manufacturer’s data
is not available, investigate any values which deviate
from similar connections by more than 50 percent of
the lowest value.

4. Circuit breaker insulation resistance should be in


accordance with Table 10.1.

5. Control wiring insulation resistance should be a


minimum of two megohms.

6. Trip characteristic of breakers shall fall within


manufacturer’s published time-current characteristic
tolerance band, including adjustment factors. If
manufacturer’s curves are not available trip times shall
be equal to or less than the values shown in Table
10.7. Circuit breakers exceeding specified trip time at
300 percent of pickup shall be tagged defective.

7. Instantaneous pickup values of molded-case circuit


breakers shall be within the tolerances shown in Table
10.8.

*Optional
60 ATS – 1999
7. INSPECTION AND TEST PROCEDURES

7.6 Circuit Breakers (cont.)


1. Low-Voltage (cont.)
2. Power

1. Visual and Mechanical Inspection

1. Compare nameplate data with drawings and


specifications.

2. Inspect physical and mechanical condition.

3. Confirm correct application of manufacturer’s


recommended lubricants.

4. Inspect anchorage, alignment, and grounding. Inspect


arc chutes. Inspect moving and stationary contacts for
condition, wear, and alignment.

5. Verify that all maintenance devices are available for


servicing and operating the breaker.

6. Verify that primary and secondary contact wipe and


other dimensions vital to satisfactory operation of the
breaker are correct.

7. Perform all mechanical operator and contact alignment


tests on both the breaker and its operating mechanism.

8. Inspect all bolted electrical connections for high


resistance using one of the following methods:

1. Use of low-resistance ohmmeter in accordance


with Section 7.6.1.2.2 (Electrical Tests).

2. Verify tightness of accessible bolted electrical


connections by calibrated torque-wrench
method in accordance with manufacturer’s
published data or Table 10.12.

3. Perform thermographic survey in accordance


with Section 9.

9. Verify cell fit and element alignment.

10. Verify racking mechanism.

*Optional ATS – 1999 61


7. INSPECTION AND TEST PROCEDURES

7.6 Circuit Breakers (cont.)


1. Low-Voltage (cont.)
2. Power (cont.)

2. Electrical Tests

1. Perform a contact-resistance test.

2. Perform resistance measurements through all bolted


connections with low-resistance ohmmeter, if
applicable, in accordance with Section 7.6.1.2.1 (Visual
and Mechanical Inspection).

3. Perform an insulation-resistance test at 1000 volts dc


from pole-to-pole and from each pole-to-ground with
breaker closed and across open contacts of each
phase.

*4. Perform insulation-resistance tests at 1000 volts dc on


all control wiring. Do not perform the test on wiring
connected to solid state components.

5. Make adjustments for the final settings in accordance


with the coordination study supplied by owner.

6. Determine minimum pickup current by primary current


injection.

7. Determine long-time delay by primary current injection.

8. Determine short-time pickup and delay by primary


current injection.

9. Determine ground-fault pickup and delay by primary


current injection.

10. Determine instantaneous pickup value by primary


current injection.

*11. Verify the calibration of all functions of the trip unit by


means of secondary injection.

*Optional
62 ATS – 1999
7. INSPECTION AND TEST PROCEDURES

7.6 Circuit Breakers (cont.)


1. Low-Voltage (cont.)
2. Power (cont.)

12. Activate auxiliary protective devices, such as ground-


fault or undervoltage relays, to insure operation of shunt
trip devices. Check the operation of electrically-
operated breakers in their cubicles.

13. Verify correct operation of any auxiliary features such


as trip and pickup indicators, zone interlocking,
electrical close and trip operation, trip-free, and
antipump function and verify trip unit battery condition.

14. Verify operation of charging mechanism.

3. Test Values

1. Compare bolted connection resistance to values of


similar connections.

2. Bolt-torque levels should be in accordance with Table


10.12 unless otherwise specified by manufacturer.

3. Microhm or millivolt drop values shall not exceed the


high levels of the normal range as indicated in the
manufacturer’s published data. If manufacturer’s data
is not available, investigate any values which deviate
from similar connections by more than 50 percent of
the lowest value.

4. Circuit breaker insulation resistance should be in


accordance with Table 10.1.

5. Central wiring insulation resistance should be a


minimum of two megohms.

6. Trip characteristics of breakers shall fall within


manufacturer’s published time-current tolerance bands.

*Optional ATS – 1999 63


7. INSPECTION AND TEST PROCEDURES

7.6 Circuit Breakers (cont.)


2. Medium-Voltage (cont.)
1. Air

1. Visual and Mechanical Inspection

1. Compare nameplate data with drawings and


specifications.

2. Inspect physical and mechanical condition.

3. Confirm correct application of manufacturer’s


recommended lubricants.

4. Inspect anchorage, alignment, and grounding. Inspect


arc chutes. Inspect moving and stationary contacts for
condition, wear, and alignment.

5. Verify that all maintenance devices are available for


servicing and operating the breaker.

6. Verify that primary and secondary contact wipe and


other dimensions vital to satisfactory operation of the
breaker are correct.

7. Perform all mechanical operator and contact alignment


tests on both the breaker and its operating mechanism.

8. Inspect all bolted electrical connections for high


resistance using one of the following methods:

1. Use of low-resistance ohmmeter in accordance


with Section 7.6.2.1.2 (Electrical Tests).

2. Verify tightness of accessible bolted electrical


connections by calibrated torque-wrench
method in accordance with manufacturer’s
published data or Table 10.12.

3. Perform thermographic survey in accordance


with Section 9.

9. Check cell fit and element alignment.

*Optional
64 ATS – 1999
7. INSPECTION AND TEST PROCEDURES

7.6 Circuit Breakers (cont.)


2. Medium-Voltage (cont.)
1. Air (cont.)

10. Check racking mechanism.

11. Inspect puffer operation.

*12. Perform circuit breaker timing tests.

13. Record as-found and as-left operation-counter


readings.

2. Electrical Tests

1. Perform a contact resistance test.

2. Measure insulation resistance pole-to-pole, pole-to-


ground, and across open poles. Use a minimum test
voltage of 2500 volts.

3. Perform resistance measurements through all bolted


connections with low-resistance ohmmeter, if
applicable, in accordance with Section 7.6.2.1.1 (Visual
and Mechanical Inspection).

*4. Perform insulation-resistance tests at 1000 volts dc on


all control wiring. Do not perform the test on wiring
connected to solid-state components.

5. With breaker in the test position, make the following


tests:

1. Trip and close breaker with the control switch.

2. Trip breaker by operating each of its protective


relays.

3. Verify trip-free and antipump function.

*4. Test trip and close circuit at reduced control


voltages, if applicable.

*6. Perform dissipation-factor/power-factor test with


breaker in both open and closed positions.

*Optional ATS – 1999 65


7. INSPECTION AND TEST PROCEDURES

7.6 Circuit Breakers (cont.)


2. Medium-Voltage (cont.)
1. Air (cont.)

*7. Perform an overpotential test in accordance with


manufacturer’s published data.

8. Measure blow-out coil circuit resistance.

3. Test Values

1. Compare bolted connection resistance to values of


similar connections.

2. Bolt-torque levels should be in accordance with Table


10.12 unless otherwise specified by manufacturer.

3. Microhm or millivolt drop values shall not exceed the


high levels of the normal range as indicated in the
manufacturer’s published data. If manufacturer’s data
is not available, investigate any values which deviate
from similar connections by more than 50 percent of
the lowest value.

4. Circuit breaker insulation resistance should be in


accordance with Table 10.1.

5. Control wiring insulation resistance should be a


minimum of two megohms.

6. Dissipation-factor/power-factor test results shall be


compared with previous tests of similar breakers or
manufacturer’s published data.

7. The insulation shall withstand the overpotential test


voltage applied.

8. Minimum pickup for trip and close coils shall conform


to manufacturer’s published data.

*Optional
66 ATS – 1999
7. INSPECTION AND TEST PROCEDURES

7.6 Circuit Breakers (cont.)


2. Medium-Voltage (cont.)
2. Oil

1. Visual and Mechanical Inspection

1. Compare equipment nameplate data with drawings


and specifications.

2. Inspect physical and mechanical condition.

3. Confirm correct application of manufacturer’s


recommended lubricants.

4. Inspect anchorage, alignment, and grounding.

5. Verify that breather vents are clear.

6. Perform all mechanical operation and contact


alignment tests on both the circuit breaker and its
operating mechanism in accordance with
manufacturer’s published data.

7. If performing internal inspection:

1. Remove oil. Lower tanks or remove manhole


covers as necessary. Inspect bottom of tank for
broken parts and debris.

2. Inspect lift rod and toggle assemblies, contacts,


interrupters, bumpers, dashpots, bushing
current transformers, tank liners, and gaskets.

3. Slow-close breaker and check for binding,


friction, contact alignment, penetration, and
overtravel. Verify that all phases make contact
simultaneously.

4. Refill tank(s) with filtered oil to correct levels.

*Optional ATS – 1999 67


7. INSPECTION AND TEST PROCEDURES

7.6 Circuit Breakers (cont.)


2. Medium-Voltage (cont.)
2. Oil (cont.)

8. Inspect all bolted electrical connections for high


resistance using one of the following methods:

1. Use of low-resistance ohmmeter in accordance


with Section 7.6.2.2.2 (Electrical Tests).

2. Verify tightness of accessible bolted electrical


connections by calibrated torque-wrench
method in accordance with manufacturer’s
published data or Table 10.12.

3. Perform thermographic survey in accordance


with Section 9.

9. Test alarms and lockouts for pneumatic and/or


hydraulic operators as recommended by the
manufacturer.

10. Perform circuit breaker time-travel analysis.

11. Record as-found and as-left operation counter


readings.

2. Electrical Tests

1. Perform a contact resistance test.

2. Remove a sample of insulating liquid in accordance


with ASTM D-923. Sample shall be tested for the
following:

1. Dielectric breakdown voltage: ASTM D-877.

2. Color: ANSI/ASTM D-1500.

*3. Power factor: ASTM D-924.

*4. Interfacial tension: ANSI/ASTM D-971 or


ANSI/ASTM D-2285.

5. Visual condition: ASTM D-1524.

*Optional
68 ATS – 1999
7. INSPECTION AND TEST PROCEDURES

7.6 Circuit Breakers (cont.)


2. Medium-Voltage (cont.)
2. Oil (cont.)

3. Trip circuit breaker by operation of each protective


device.

4. Perform insulation-resistance tests pole-to-pole, pole-


to-ground, and across open poles at 2500 volts
minimum.

5. Perform resistance measurements through all bolted


connections with low-resistance ohmmeter, if
applicable, in accordance with Section 7.6.2.2.1 (Visual
and Mechanical Inspection).

*6. Perform insulation-resistance tests on all control wiring


at 1000 volts dc. Do not perform this test on wiring
connected to solid-state relays.

7. Perform dissipation factor/power factor tests on each


pole with breaker open and each phase with breaker
closed. Determine tank loss index.

8. Perform dissipation-factor/power-factor tests on each


bushing. Use conductive straps and hot collar
procedures if bushings are not equipped with a power-
factor tap.

9. Verify trip, close, trip-free, and antipump functions.

*10. Perform minimum pickup voltage tests on trip and close


coils.

*11. Perform an overpotential test in accordance with


manufacturer’s instructions.

*Optional ATS – 1999 69


7. INSPECTION AND TEST PROCEDURES

7.6 Circuit Breakers (cont.)


2. Medium-Voltage (cont.)
2. Oil (cont.)

3. Test Values

1. Compare bolted connection resistance to values of


similar connections.

2. Bolt-torque levels should be in accordance with Table


10.12 unless otherwise specified by manufacturer.

3. Microhm or millivolt drop values shall not exceed the


high levels of the normal range as indicated in the
manufacturer’s published data. If manufacturer’s data
is not available, investigate any values which deviate
from similar connections by more than 50 percent of
the lowest value.

4. Compare circuit breaker travel and velocity values to


manufacturer’s acceptable limits.

5. Insulating-liquid test results should comply with Table


10.4.

6. Circuit breaker insulation resistance should be in


accordance with Table 10.1.

7. Control wiring insulation resistance should be a


minimum of two megohms.

8. Dissipation-factor/power-factor test results and tank


loss index shall be compared to manufacturer’s
published data. In the absence of manufacturer’s
published data, the comparison shall be made to
similar breakers.

9. Dissipation-factor/power-factor and capacitance test


results should be within ten percent of nameplate
rating for bushings.

10. The insulation shall withstand the overpotential test


voltage applied.

11. Minimum pickup for trip and close coils shall conform to
manufacturer’s published data.
*Optional
70 ATS – 1999
7. INSPECTION AND TEST PROCEDURES

7.6 Circuit Breakers (cont.)


2. Medium-Voltage (cont.)
3. Vacuum

1. Visual and Mechanical Inspection

1. Compare equipment nameplate data with drawings


and specifications.

2. Inspect physical and mechanical condition.

3. Confirm correct application of manufacturer’s


recommended lubricants.

4. Inspect anchorage, alignment, and grounding.

5. Perform all mechanical operational tests on both the


circuit breaker and its operating mechanism.

6. Measure critical distances such as contact gap as


recommended by manufacturer.

7. Inspect all bolted electrical connections for high


resistance using one of the following methods:

1. Use of low-resistance ohmmeter in accordance


with Section 7.6.2.3.2 (Electrical Tests).

2. Verify tightness of accessible bolted electrical


connections by calibrated torque-wrench
method in accordance with manufacturer’s
published data or Table 10.12.

3. Perform thermographic survey in accordance


with Section 9.

8. Perform timing tests.

9. Record as-found and as-left operation counter


readings.

*Optional ATS – 1999 71


7. INSPECTION AND TEST PROCEDURES

7.6 Circuit Breakers (cont.)


2. Medium-Voltage (cont.)
3. Vacuum (cont.)

2. Electrical Tests

1. Perform a contact-resistance test.

*2. Perform minimum pickup voltage tests on trip and close


coils.

3. Verify trip, close, trip-free, and antipump function.

4. Trip circuit breaker by operation of each protective


device.

5. Perform resistance measurements through all bolted


connections with low-resistance ohmmeter, if
applicable, in accordance with Section 7.6.2.3.1 (Visual
and Mechanical Inspection).

6. Perform insulation-resistance tests pole-to-pole, pole-


to-ground, and across open poles at 2500 volts
minimum

7. Perform vacuum bottle integrity (overpotential) test


across each vacuum bottle with the breaker in the
open position in strict accordance with manufacturer’s
instructions.

*8. Perform insulation-resistance tests at 1000 volts on all


control wiring dc. For units with solid-state components,
follow manufacturer’s recommendations.

*9. Perform dissipation-factor/power-factor tests on each


pole with the breaker open and each phase with the
breaker closed.

*10. Perform dissipation-factor/power-factor tests on each


bushing. Use conductive straps and hot collar
procedures if bushings are not equipped with a power
factor tap.

*11. Perform an overpotential test in accordance with


manufacturer’s instructions.

*Optional
72 ATS – 1999
7. INSPECTION AND TEST PROCEDURES

7.6 Circuit Breakers (cont.)


2. Medium-Voltage (cont.)
3. Vacuum (cont.)

3. Test Values

1. Compare bolted connection resistance to values of


similar connections.

2. Bolt-torque levels should be in accordance with Table


10.12 unless otherwise specified by manufacturer.

3. Microhm or millivolt drop values shall not exceed the


high levels of the normal range as indicated in the
manufacturer’s published data. If manufacturer’s data
is not available, investigate any values which deviate
from similar connections by more than 50 percent of
the lowest value.

4. Circuit breaker insulation resistance should be in


accordance with Table 10.1.

5. Contact displacement shall be in accordance with


factory recorded data marked on the nameplate of
each vacuum breaker or bottle.

6. The interrupter shall withstand the overpotential


voltage applied.

7. Compare circuit breaker timing values to


manufacturer’s published data.

8. Control wiring insulation resistance should be a


minimum of two megohms.

9. Dissipation-factor/power-factor test results shall be


compared to manufacturer’s published data. In the
absence of manufacturer’s published data the
comparison shall be made to similar breakers.

*Optional ATS – 1999 73


7. INSPECTION AND TEST PROCEDURES

7.6 Circuit Breakers (cont.)


2. Medium-Voltage (cont.)
3. Vacuum (cont.)

10. Dissipation-factor/power-factor and capacitance test


results should be within ten percent of nameplate
rating for bushings.

11. The insulation shall withstand the overpotential test


voltage applied.

*Optional
74 ATS – 1999

Potrebbero piacerti anche