Sei sulla pagina 1di 85

ANALYSIS OF RATE FOR GRANULAR BACKFILL

UNIT = 100 Cft.

1 Sub base course in 50 % proportion

8510.31 x 0.50 = 4255.16 = Rs. 4255.16

2 Supplying and mixing sand of river or pit ( 50 % ) = Rs. 1379.68

Total = Rs. 5634.83

Rate Per CM 5634.83 x 35.32 = 1990.22


100

Executive Engineer
Road Construction Division
Lahore.

(MRS 1st Bi-Annual 2017)


ANALYSIS OF RATE FOR P/F TUFF TILES 80 MM THICK
Unit = P.Sft.
Take 100 Sft Area for Analysis Purpose.

1 Pre casted Tuff pavers 80 mm thick

1 x 10 x 10 = 100 Sft.

@ 77.00 P.Sft. = Rs.7,700


(76+78)/2

2 S/F Sand under paving tiles

0.75" sand for leveling purpose and 0.25" for joints filling etc.

1 x 10 x 10 x 0.08 = 8.33 Cft.

@ 1260.00 P% Cft. = Rs.105.00


(1100x1.20)

4 Compactor working for paving tiles.

1 x 1 = 1.00 Job.

@ Rs.230.00 P. Hr = Rs.230.00

5 Labour for laying paving blocks.

1 x 10 x 10 = 100.00 Sft.

@ Rs.15.00 P.Sft. = Rs.1,500.00


Total = Rs.9,535.00

Add 20% Contractor profit on item No.1. (+) Rs.1,540.00


G.Total = Rs.11,075.00

Rate per Sft Rs.11,075.00 / 100 = Rs.110.75

Rate per SM Rs.110.75 x 10.765 = Rs.1,192.22

Executive Engineer
Road Construction Division
Lahore.

(MRS 1st Bi-Annual 2017)


ANALYSIS OF RATE FOR P/F Precast Paving Blocks (Paving Tiles) 60 mm thick
Unit = P.Sft.
Take 100 Sft Area for Analysis Purpose.

1
S/O Precast Paving Blocks (Paving Tiles) Size 60
mm thick of approved colour and shape as
directed by the Engineer Incharge at the site of
work i/c carriage etc complete.

1 x 10 x 10 = 100 Sft.

@ 58.00 P.Sft. = Rs.5,800


(57+59)/2

2 S/F Sand under paving tiles / floor.

2" sand for leveling purpose and 1/2" for joints filliing etc.

1 x 10 x 10 x 0.21 = 21.00 Cft.

@ 1260.00 P% Cft. = Rs.264.60


(1100x1.20)

3 Compactor working for paving tiles.

1 x 1 = 1.00 Job.

@ Rs.230.00 P.Job. = Rs.230.00

4 Labour for laying paving blocks.

1 x 10 x 10 = 100.00 Sft.

@ Rs.15.00 P.Sft. = Rs.1,500.00


Total = Rs.7,794.60

Add 10% Sundries charges on item No.6. (+) Rs.150.00


Add 20% Contractor profit on item No.1. (+) Rs.1,160.00
G.Total = Rs.9,104.60

Rate per Sft Rs.9,104.60 / 100 = Rs.91.05

Rate per SM Rs.91.05 x 10.765 = Rs.980.11

Executive Engineer
Road Construction Division
Lahore.

(MRS 1st Bi-Annual 2017)


ANALYSIS OF RATE FOR P/F KERB STONE ( 14" HIGH )
Unit = Per Rft
Take 10 Rft Length for Analysis purpose

1 Cement concrete 1:4:8 plain i/c placing , levelling ,etc complete.

1 x 10 x 1 x 0.25 = 2.50 Cft.

@ Rs.19,978.25 P% Cft. = Rs.499.46

2 Read made Kerb Stone 14" high ( Tuff / Izhar with compressive strength )
size 12" long & 14" high of approved shape -

1 x 10 = 10.00 No
( Note: Each Kerb stone will be 12" long )

@ Rs.108.00 Each = Rs.1,080.00


(90x1.20)

3 Cement Concrete Plain including placing, compacting , finishing and


curing complete ( Ratio 1:2:4 )

Haunching
1 x 10 x 0.21 x 0.50 = 1.05 Cft.
(0.25+0.17)/2

@ Rs.24,411.24 P.%Cft = Rs.256.32

4 Labour charges for fixing , positioning & aligning of Kerb stones

One Mason can fix 100 Kerb stones in a day


Labour for fixing 10 kerb stones = Rs.625 x 10 = Rs.62.50
100

5 Preparing surface and painting of small detached articles, not exceeding one sq. ft.
(Sq.m) of painted surface (03 coats):-

1 x 10 = 10 Nos.

@ Rs.2,963.65 P% Nos. = Rs.296.37


(1326.75+818.45+818.45)
Total = Rs.2,194.64

Rate per Rft. = Rs.2,194.64 / 10 = 219.46 P.Rft.

Rate per Meter 219.46 x 3.281 = 720.06 P.Mtr.

Executive Engineer
Road Construction Division
Lahore.

(MRS 1st Bi-Annual 2017)


ANALYSIS OF RATE FOR M.S STEEL LINER

Unit =

P/F M.S Steel Liner 10 mm thick i/c cutting, bending, welding


(fabrication) and carriage etc complete.

Weight of Liner for 1 meter length, 5' dia pile and 10 mm thick.

Length
1 x 3.28 = 3.28 Rft

Circumfrence 2 R
2 x 3.14 x 2.5 = 15.70 Ft

Thickness
10 / 25.4 / 12 = 0.033 Ft

3.28 x 15.70 x 0.033 = 1.70 Cft

weight @ 490 lbs/Cft.


1.70 x 490 / 2.20 = 378.50 Kg.

Qty for 3 meter liner.


3 x 378.50 = 1135.49 Kg.

1 Fabrication of heavy steel work, with angle, tees, flat iron


round iron and sheet iron for making trusses, girders,
tanks, etc., including cutting, drilling, revitting, handling,
assembling and fixing, but excluding erection in position.

1 x 1135.49 = 1135.49 Kg.

@ Rs.11,324.15 P%Kg. =
(MRS Chap-25, Page 153, item No.10)

2 Carriage / transportation of liner from workshop to site of


work.

= 1 Job.

@ Rs.5,000.00 P.Job. =

3 Loading & unloading charges with crane 20 ton.

= 2 Hrs.

@ Rs.1,953.00 P.Hrs. =

(MRS 1st Bi-Annual 2017) Page5


4 Erection and fitting in position iron trusses, staging of water
tanks, etc.

1 x 1135.49 = 1135.49 Kg.

@ Rs.678.50 P%Kg. =
(MRS Chap-25, Page 153, item No.11)
Total =

Rate Per Kg.


Rs.145,194.00 = Rs.127.87
1135.49

Rate Per Meter


Rs.145,194.00 = Rs.48,398
3.00

Executive Engineer
Road Construction Division
Lahore.

(MRS 1st Bi-Annual 2017) Page6


F RATE FOR M.S STEEL LINER

%Kg.

0 mm thick i/c cutting, bending, welding


on) and carriage etc complete.

Rs.128,584

Rs.5,000

Rs.3,906

(MRS 1st Bi-Annual 2017) Page7


Rs.7,704

Rs.145,194

(MRS 1st Bi-Annual 2017) Page8


DESCRIPTION OF ITEM:
Item No. 7 Providing and casting in situ bored reinforced concrete pile with type '
concrete (Nominal mix 1 : 2: 4), using 10% extra cement in dry mix, and
course sand including all labour and material (except the cost of steel
reinforcement and its labour for bending and laying in position etc., wh
will be paid separately, including screening and washing of shingle and
curing.
(iv) 24" dia (600 mm) pile.

Detail Unit Rate (British System) per Rft

Qty Rate Per Unit

MATERIAL Analysis for 100 Rft


1 Concrete x 100 =
( 24 )² 314.16 Cft.
12x12x4
2 Cement 55.29 bags 533.00 per bag
3 Sand (Harro) 138.23 Cft ### % Cft
4 Bajri 276.46 Cft ### % Cft
5 Extra cement (10%) 5.53 bags 533.00 per bag
5 Cost of casing pipe
100' @ 933 P.Rft = 93300
Can be used 100 times
93300 ÷ 100 = 933
Total
Contractor's Profit 20 Percent
Total
LABOUR

1 Mason 8.00 Nos. 625.00 per day


2 Cooly skilled 8.00 Nos. 625.00 per day
3 Coolies un-skilled 95.00 No. 550.00 per day
4 Bahisthi 1.00 No. 570.00 per day
5 Fitter 4.75 Nos. 625.00 per day
Total
6 Boring hole 60" dia 100.00 Rft 350.00 per foot
7 Working of rig during casting 2.50 hrs. ### per hour
8 Constructin of Temparary Island (LS-05) L.S
9 Carriage of material to site of work
(Boaring Material) LS-06 L.S

Total
Sundries 10 Percent on ###
Total
Contractor's Profit 20 Percent
on Rs. ###
Total for 100 Rft

ITEM RATES
Labour rate per Rft Rs. ### Say
Labour rate per L.M Rs. ### Say

Composite rate per Rft Rs. ### Say


Composite rate per L.M Rs. ### Say

Executive Engineer
Road Construction Division
Lahore.

(MRS 1st Bi-Annual 2017)


and casting in situ bored reinforced concrete pile with type 'C'
Nominal mix 1 : 2: 4), using 10% extra cement in dry mix, and
nd including all labour and material (except the cost of steel
ment and its labour for bending and laying in position etc., which
d separately, including screening and washing of shingle and

Unit Rate (British System) per Rft

Amount (Rs.)

29469.57
5114.51
8846.72
2946.96

933
47310.76
9462.15
56772.91

5000.00
5000.00
52250.00
570.00
2968.75
65788.75
35000.00
2500.00
13000.00

550.00

###
6578.88
###

14473.53
###

Road Construction Division

(MRS 1st Bi-Annual 2017)


DESCRIPTION OF ITEM:

Item No. 7 Providing and casting in situ bored reinforced concrete pile with type 'C'
concrete (Nominal mix 1 : 1.50: 3), using 10% extra cement in dry mix, and
course sand including all labour and material (except the cost of steel
reinforcement and its labour for bending and laying in position etc., which
will be paid separately, including screening and washing of shingle and
curing.

(i) 60" dia pile.

Detail Unit Rate (British System) per Rft

Qty Rate Per Unit

MATERIAL Analysis for 100 Rft

1 Concrete 22 x ( 60 x 100 = 1963.49


7x12x 12 x 4
Dry Material = 3023.77
2 Cement 439.82 bags 533.00 per bag
3 Sand (Harro) 824.67 Cft 3,700.00 % Cft
4 Bajri 1649.33 Cft 3,200.00 % Cft
5 Extra cement (10%) 43.98 bags 533.00 per bag
6 Cost of casing pipe
100' @ @ 933 P.Rft = 93300
Can be used 100 times
93300 ÷ 100 = 933

Total
Contractor's Profit & Overheads 20 Percent
Total

LABOUR
Labour for 60" dia pile
1 Mason 1963.49 Cft. 209.41 P.Cft.
2 Cooly skilled
3 Coolies un-skilled
4 Bahisthi
5 Fitter
Total
Sundries 10 Percent on R###
Total
Contractor's Profit & Overheads 20 Percent
Total

6 Boring hole 60" dia 100.00 Rft 1,500.00 per foot


7 Working of rig during casting 2.50 hrs. 1,000.00 per hour
8 Constructin of Temparary Island L.S
9 Carriage of material to site of work
(Boaring Material) L.S

Total for 100 Rft

ITEM RATES
Labour rate per Rft Rs. 7,088.00 Say
Labour rate per L.M Rs. 23,248.65 Say

Composite rate per Rft Rs. 11,193.10 Say


Composite rate per L.M Rs. 36,713.38 Say

Composite Rate Per Rft. Rs. 11193.10

Add extra of Bajri

(MRS 1st Bi-Annual 2017)


Qty of Bajri
For %Rft. RCC required Bajri 1649.33 Cft.
For 1 Rft RCC required Bajri 16.49 P.Cft.
4047.55 / 100 x 16.49 Rs. 667.44
(As per same carriage of base course)

Total Rs. 11,860.54 Rft.

Or Rs. 38,902.59 LM

(MRS 1st Bi-Annual 2017)


g and casting in situ bored reinforced concrete pile with type 'C'
e (Nominal mix 1 : 1.50: 3), using 10% extra cement in dry mix, and
and including all labour and material (except the cost of steel
ement and its labour for bending and laying in position etc., which
aid separately, including screening and washing of shingle and

Unit Rate (British System) per Rft

Amount (Rs.)

234425.00
30512.63
52778.61
23442.50

933.00

###
68418.35
###

411174.44

###
41117.44
###
90458.38
###

150000.00
2500.00
13000.00

550.00

###

(MRS 1st Bi-Annual 2017)


DESCRIPTION OF ITEM:
Item No. 7 Providing and casting in situ bored reinforced concrete pile with type 'C'
concrete (Nominal mix 1 : 1.50: 3), using 10% extra cement in dry mix, and
course sand including all labour and material (except the cost of steel
reinforcement and its labour for bending and laying in position etc., which
will be paid separately, including screening and washing of shingle and
curing.
(i) 1500 mm dia pile.

Detail Unit Rate (British System) per Rft

Qty Rate Per Unit Amount (Rs.)

MATERIAL Analysis for 100 Rft


1 Concrete 22 x (1.50x3.2x 100 = 1900.20
7 x 4
Dry Material = 2926.31
2 Cement 425.64 bags 533.00 per bag 226868.68
3 Sand (Harro) 798.08 Cft 3,700.00 % Cft 29529.11
4 Bajri 1596.17 Cft 3,200.00 % Cft 51077.38
5 Extra cement (10%) 42.56 bags 533.00 per bag 22686.87
6 Cost of casing pipe
100' @ @ 933 P.Rft = 93300
Can be used 100 times
93300 ÷ 100 = 933 933.00
Total ###
Contractor's Profit & Overheads 20 Percent 66219.01
Total ###
LABOUR
Labour for 60" dia pile
1 Mason 1900.20 Cft. 209.41 P.Cft. 397920.88
2 Cooly skilled
3 Coolies un-skilled
4 Bahisthi
5 Fitter
Total ###
Sundries 10 Percent on R ### 39792.09
Total ###
Contractor's Profit & Overheads 20 Percent 87542.59
Total ###

6 Boring hole 60" dia 100.00 Rft 1,500.00 per foot 150000.00
7 Working of rig during casting 2.50 hrs. 1,000.00 per hour 2500.00
8 Constructin of Temparary Island L.S 13000.00
9 Carriage of material to site of work
(Boaring Material) L.S 550.00
Total for 100 Rft ###
ITEM RATES
Labour rate per Rft Rs. 6,913.06 Say
Labour rate per L.M Rs. 22,674.82 Say

Composite rate per Rft Rs. 10,886.20 Say


Composite rate per L.M Rs. 35,706.72 Say

Composite Rate Per Rft. Rs. 10886.20


Add extra of Bajri
Qty of Bajri
For %Rft. RCC required Bajri 1596.17 Cft.
For 1 Rft RCC required Bajri 15.96 P.Cft.
4047.55 / 100 x 15.96 Rs. 645.99
(As per same carriage of base course)

Total Rs. 11,532.18 Rft.

Or Rs. 37,825.57 LM

Executive Engineer

(MRS 1st Bi-Annual 2017)


Road Construction Division
Lahore.

(MRS 1st Bi-Annual 2017)


DESCRIPTION OF ITEM:

Item No. 7 Providing and casting in situ bored reinforced concrete pile with type 'C'
concrete (Nominal mix 1 : 1.50: 3), using 10% extra cement in dry mix, and
course sand including all labour and material (except the cost of steel
reinforcement and its labour for bending and laying in position etc., which
will be paid separately, including screening and washing of shingle and
curing.
(i) 1000 mm dia pile.

Detail Unit Rate (British System) per Rft

Qty Rate Per Unit Amount (Rs.)


MATERIAL Analysis for 100 Rft

1 Concrete 22 x (1x3.28 ) x 100 = 844.53


7 x 4
Dry Material = 1300.58
2 Cement 189.17 bags 533.00 per bag 100830.13
3 Sand (Harro) 354.70 Cft 3,700.00 % Cft 13124.00
4 Bajri 709.41 Cft 3,200.00 % Cft 22700.97
5 Extra cement (10%) 18.92 bags 533.00 per bag 10083.01
6 Cost of casing pipe
100' @ @ 933 P.Rft = 93300
Can be used 100 times
93300 ÷ 100 = 933 933.00
Total ###
Contractor's Profit & Overheads 20 Percent 29534.22
Total ###
LABOUR
Labour for 60" dia pile
1 Mason 844.53 Cft. 209.41 P.Cft. 176853.03
2 Cooly skilled
3 Coolies un-skilled
4 Bahisthi
5 Fitter
Total ###
Sundries 10 Percent on R### 17685.30
Total ###
Contractor's Profit & Overheads 20 Percent 38907.67
Total ###

6 Boring hole 60" dia 100.00 Rft 1,500.00 per foot 150000.00
7 Working of rig during casting 2.50 hrs. 1,000.00 per hour 2500.00
8 Constructin of Temparary Island L.S 13000.00
9 Carriage of material to site of work
(Boaring Material) L.S 550.00
Total for 100 Rft ###

ITEM RATES
Labour rate per Rft Rs. 3,994.96 Say
Labour rate per L.M Rs. 13,103.47 Say
Composite rate per Rft Rs. 5,767.01 Say
Composite rate per L.M Rs. 18,915.80 Say

Composite Rate Per Rft. Rs. 5767.01


Add extra of Bajri
Qty of Bajri
For %Rft. RCC required Bajri 709.41 Cft.
For 1 Rft RCC required Bajri 7.09 P.Cft.
4047.55 / 100 x 7.09 Rs. 286.97
(As per same carriage of base course)

Total Rs. 6,053.98 Rft.

Or Rs. 19,857.07 LM

(MRS 1st Bi-Annual 2017)


Executive Engineer
Road Construction Division
Lahore.

(MRS 1st Bi-Annual 2017)


DESCRIPTION OF ITEM:

Item No. 8 Fabrication of mild steel reinforcement bar cage for R.C.C bored piles
including cutting bending, laying in position, welding and fastening,
including cost of binding wire and labour charges for binding of steel
reinforcement (also includes removal of rust from the bars).

(b) Deformed bars Grade 40.

Detail Unit Rate (British System) per Cwt

Qty Rate Per Unit Amount (Rs.)

Analysis for 48 Cwt


MATERIAL
2.443 Ton
1 Fabrication of steel (48.00 Cwt) 70,750.00 per ton 172842.25
2 Welding electrode 1.00 bundle 310.00 per bundle 310.00
3 Hire charges of plant L.S 880.00
4 Working of rig during lowering of cage 3.00 hrs. 1,000.00 per hour 3000.00

Total 177032.25
Contractor's Profit & Overheads 20 Percent 35406.45
Total 212438.70
Material cost per Cwt 4425.81

LABOUR for 2 Cwt

1 Welder 1.00 Nos. 625.00 per day 625.00


2 Coolies un-skilled 3.00 Nos. 550.00 per day 1650.00

Total 2275.00
Sundries 10 Percent 227.50
Total 2502.50
Contractor's Profit & Overheads 20 Percent 500.50
Total 3003.00

ITEM RATES

Labour rate per Cwt Rs. 1,501.50 Say


Labour rate per 100 Kg Rs. 2,955.71 Say

Composite rate per Cwt Rs. 5,927.31 Say


Composite rate per 100 Kg Rs. 11,667.93 Say

(MRS 1st Bi-Annual 2017)


DESCRIPTION OF ITEM:

Item No. 8 Fabrication of mild steel reinforcement bar cage for R.C.C bored piles
including cutting bending, laying in position, welding and fastening,
including cost of binding wire and labour charges for binding of steel
reinforcement (also includes removal of rust from the bars).

(b) Deformed bars Grade 60.

Detail Unit Rate (British System) per Cwt

Qty Rate Per Unit Amount (Rs.)

Analysis for 48 Cwt


MATERIAL
2.443 Ton
1 Fabrication of steel (48.00 Cwt) 74,250.00 per ton 181392.75
2 Welding electrode 1.00 bundle 310.00 per bundle 310.00
3 Hire charges of plant L.S 880.00
4 Working of rig during lowering of cage 3.00 hrs. 1,000.00 per hour 3000.00

Total 185582.75
Contractor's Profit & Overheads 20 Percent 37116.55
Total 222699.30
Material cost per Cwt 4639.57

LABOUR for 2 Cwt

1 Welder 1.00 Nos. 625.00 per day 625.00


2 Coolies un-skilled 3.00 Nos. 550.00 per day 1650.00

Total 2275.00
Sundries 10 Percent 227.50
Total 2502.50
Contractor's Profit & Overheads 20 Percent 500.50
Total 3003.00

ITEM RATES

Labour rate per Cwt Rs. 1,501.50 Say


Labour rate per 100 Kg Rs. 2,955.71 Say

Composite rate per Cwt Rs. 6,141.07 Say


Composite rate per 100 Kg Rs. 12,088.72 Say

Composite Rate Per 100 Kg. = Rs.12,088.72

Or Rs.120,887.18 P. Ton

Executive Engineer
Road Construction Division
Lahore.

(MRS 1st Bi-Annual 2017)


DESCRIPTION OF ITEM:

Item No. 22 Lifting, transporting and placing precast prestressed concrete Beam,
Girder and other members (excluding battens) etc., in position on the
bridge to correct alignment and level, etc., complete.

(i) Beam upto 50 ft. (15.0 metre) length.

Detail Unit Rate (British System) per 100 Cft

Qty Rate Per Unit Amount (Rs.)

Assumed for 375 Cft


EQUIPMENT

1 Cost of lifting machinery including carriage 1.00 No. 1,150,000 each 1150000.00
2 Cost of trollies 3.00 Nos. 46,000.00 each 138000.00
3 Cost of steel rope 1" Ø 450.00 Rft 70.00 Rft 31500.00
4 U Clamp i/c 5/8" bolts & nuts 3.00 Nos. 60.00 each 180.00
5 Steel rope ¾" (3 x 20) 60.00 Rft 55.00 Rft 3300.00
6 Railway track 200 ft. including sleepers bolts
& nuts complete 200' x 2 = 400 Rft @
235/-P-Rft 400.00 Rft 242.00 Rft 96800.00
7 Crow bar 6.00 Nos. 440.00 each 2640.00
Total 1422420.00
Assume life of machinery = 5 years
depreciation for one year
1422420 ÷ 5 = ### 284484.00
Contractor's Profit & Overheads 20 Percent 56896.80
Total 341380.80

(a) Beam 50'.0 in length 50x2x3.75 = 375 Cft


The above equipment used to lift/
transport and fixing in postion
during one year = 200 beams
Cft = 200 x 375 75000 Cft
Amount per beam
### x 375 ### 1706.90
75000
For 100 Cft 1,707 x 100 455.17
375
LABOUR Working team for two beams of 375 Cft

1 Supervisor/foreman 1.00 No. 625.00 per day 625.00


2 Colies skilled 3.00 Nos. 625.00 per day 1875.00
3 Crane operator 1.00 No. 617.00 per day 617.00
4 Coolies un-skilled 8.00 Nos. 550.00 per day 4400.00
Total 7517.00
Sundries 10 Percent 751.70
Total 8268.70
Contractor's Profit & Overheads 20 Percent 1653.74
Total for 2 beams of 375 Cft each 9922.44
Rate for 100 Cft 9,922 x 100 ###
2 x 375

ITEM RATES
Labour rate per 100 Cft Rs. 1,322.99 Say
Labour rater per Cum Rs. 467.28 Say

Composite rate per 100 Cft Rs. 1,778.17 Say


Composite rate per Cum Rs. 628.05 Say

DESCRIPTION OF ITEM:

Item No. 22 Lifting, transporting and placing precast prestressed concrete Beam,
Girder and other members (excluding battens) etc., in position on the
bridge to correct alignment and level, etc., complete.

(ii) Beam above 50 ft. upto 75 ft (15 metre to 23 metre) length.

(MRS 1st Bi-Annual 2017)


Detail Unit Rate (British System) per 100 Cft

Qty Rate Per Unit Amount (Rs.)

EQUIPMENT

As per item 22(i)

(a) Beam 75 x 2 x 3.75 = 562.5 Cft


The equipment used to lift/
transport and fixing in postion
during one year = 80 beams
Cft = 80 x 562.5 = 45000 Cft
Amount per beam
### x 562.5 ### 4267.26
45000
LABOUR

Full shift of Labour is required for


one day as per item 22(i) 9922.44

Total 14189.70

ITEM RATES

Machinary + Labour required to operate the


machinary Rs.
Rate per 100 Cft Rs. 14,189.70 x 10 2522.61
562.50
Rate per Cum Rs.

DESCRIPTION OF ITEM:

Item No. 22 Lifting, transporting and placing precast prestressed concrete Beam,
Girder and other members (excluding battens) etc., in position on the
bridge to correct alignment and level, etc., complete.

(iii) Beam above 75 ft. upto 100 ft (23 metre to 30 metre) length.

Detail Unit Rate (British System) per 100 Cft

Qty Rate Per Unit Amount (Rs.)

EQUIPMENT

As per item 22(i)

(a) Beam = 100 x 2 x 3.75 = 750 Cft


The equipment used to lift/
transport and fixing in postion
during one year = 60 beams
Cft = 60 x 750.0 = 45000 Cft
Amount per beam
### x 750 ### 5689.68
45000
LABOUR

Full shift of Labour is required for


two days as per item 22(i) 2.00 9,922.44 19844.88

Total 25534.56

ITEM RATES

Machinary + Labour required to operate the

(MRS 1st Bi-Annual 2017)


machinary Rs.
Rate per 100 Cft Rs. 25,534.56 x 10 3404.61
750.00 Say
Rate per Cum Rs.

DESCRIPTION OF ITEM:

Item No. 22 Lifting, transporting and placing precast prestressed concrete Beam,
Girder and other members (excluding battens) etc., in position on the
bridge to correct alignment and level, etc., complete.

(iv) Beam above 100 ft. upto 150 ft (23 metre to 30 metre) length.

Detail Unit Rate (British System) per 100 Cft

Qty Rate Per Unit Amount (Rs.)

EQUIPMENT

As per item 22(i)

(a) Beam = 150 x 2 x 3.75 1125 Cft


The equipment used to lift/
transport and fixing in postion
during one year = 34 beams
Cft = 34 x 1125 = 38250 Cft
Amount per beam 34 x 1125 =
### x 1125 ### 10040.61
38250
LABOUR

Full shift of Labour is required for


four days as per item 22(i) 4.00 9,922.44 39689.76

Total 39689.76

ITEM RATES

Machinary + Labour required to operate the


machinary Rs. 49,730.37
Rate per 100 Cft Rs. 49,730.37 100 4420.48
1,125.00 Say
Rater per Cum Rs. 1561.31
Say

DESCRIPTION OF ITEM:

Item No. 22 Lifting, transporting and placing precast prestressed concrete Beam,
Girder and other members (excluding battens) etc., in position on the
bridge to correct alignment and level, etc., complete.

(v) Beam above 150 ft. upto 175 ft (46 metre to 53 metre) length.

Detail Unit Rate (British System) per 100 Cft

Qty Rate Per Unit Amount (Rs.)

EQUIPMENT

As per item 22(i)

(a) Beam = 175 x 2 x 3.75 1312.5 Cft


The equipment used to lift/
transport and fixing in postion
during one year = 28 beams
Cft = 28 x 1312.5 = 36750 Cft
Amount per beam

(MRS 1st Bi-Annual 2017)


### x 1312.5 ### 12192.17
36750
LABOUR

Full shift of Labour is required for


six days as per item 22(i) 6.00 9,922.44 59534.64

Total 71726.81

ITEM RATES

Machinary + Labour required to operate the


machinary Rs.
Rate per 100 Cft Rs. 71,726.81 100 5464.90
1,312.50 Say
Rater per Cum Rs.
Say

(MRS 1st Bi-Annual 2017)


ANALYSIS ON MARKET RATES.

Unit = P.Cft.
Lead = 180 Km.

1 P/L R.C.C 1:2:4 in Slab.

Basic Rate for 1 Cft RCC = 338.90

Add Carriage of Bajri

Qty of Bajri
For %Cft. RCC 88.00 Cft.
For One Cft RCC 0.88 P.Cft.
4047.55 / 100 x 0.88 = 35.62
(As per same carriage of base course)

Total = Rs.374.52

2 P/L R.C.C 1:2:4 in bed plate.

Basic Rate for 1 Cft RCC = 246.45

Add Carriage of Bajri

For %Cft. RCC 88.00 Cft.


For One Cft RCC 0.88 P.Cft.
4047.55 / 100 x 0.88 = 35.62
(As per same carriage of base course)

Total = Rs.282.07

3 P/L R.C.C 1:1.50:3 in slab.

Add Carriage of Bajri = 368.00

Add extra of Bajri

For %Cft. RCC 84.00 Cft.


For One Cft RCC 0.84 P.Cft.
4047.55 / 100 x 0.84 = 34.00
(As per same carriage of base course)

Total = Rs.402.00

Executive Engineer
Road Construction Division
(MRS 1st Bi-Annual 2017)
Lahore.

(MRS 1st Bi-Annual 2017)


ANALYSIS ON MARKET RATES.

Unit = P.Cft.
Lead = 180 Km.
1 P/L R.C.C 1:1:2 with horizontal shuttering.

Basic Rate for 1 Cft RCC = 422.15

Add Carriage of Bajri

Qty of Bajri
For %Cft. RCC 78.00 Cft.
For One Cft RCC 0.78 P.Cft.
4047.55 / 100 x 0.78 = 31.57
(As per same carriage of base course)
Total = Rs.453.72

Or = Rs.16,025.39 P.CM

2 P/L R.C.C 1:1.50:3 with horizontal shuttering.

Basic Rate for 1 Cft RCC = 368.00

Add Carriage of Bajri

Qty of Bajri
For %Cft. RCC 84.00 Cft.
For One Cft RCC 0.84 P.Cft.
4047.55 / 100 x 0.84 = 34.00
(As per same carriage of base course)
Total = Rs.402.00

Or = Rs.14,198.64 P.CM

3 P/L R.C.C 1:2:4 with horizontal shuttering.

Basic Rate for 1 Cft RCC = 338.90


Add Carriage of Bajri

Qty of Bajri
For %Cft. RCC 88.00 Cft.
For One Cft RCC 0.88 P.Cft.
4047.55 / 100 x 0.88 = 35.62
(As per same carriage of base course)
Total = Rs.374.52

Or = Rs.13,228.05 P.CM

Executive Engineer
(MRS 1st Bi-Annual 2017)
Road Construction Division
Lahore.

(MRS 1st Bi-Annual 2017)


ANALYSIS ON MARKET RATES.

Unit = P.Cft.
Lead = 224 Km.

1 P/L R.C.C 1:1.50:3 with horizontal shuttering.


(4000 PSI)

Basic Rate for 1 Cft RCC = 403.35

Add Carriage of Bajri

Qty of Bajri
For %Cft. RCC 84.00 Cft.
For One Cft RCC 0.84 P.Cft.
4047.55 / 100 x 0.84 = 34.00
(As per same carriage of base course)
Total = Rs.437.35

Or = Rs.15,447.20 P.CM

1 P/L R.C.C 1:1.50:3 without horizontal shuttering.


(4000 PSI)

Basic Rate for 1 Cft RCC = 310.96

Add Carriage of Bajri

Qty of Bajri
For %Cft. RCC 84.00 Cft.
For One Cft RCC 0.84 P.Cft.
4047.55 / 100 x 0.84 = 34.00
(As per same carriage of base course)
Total = Rs.344.96

Or = Rs.12,183.99 P.CM

Executive Engineer
Road Construction Division
Lahore.

(MRS 1st Bi-Annual 2017)


CONCRETE CLASS A2 (4000 PSI)

Unit of Rate = 50 Cm x 35.32 = 1766.00 Cft


Loose material

As per NESPAK analysis

Cement 396 Bags For %Cft.


396 x 1.25 = 495 Cft. 28.029

Coarse sand 21 CM
21 x 35.32 = 741.72 Cft. 42.00

Bajri 42 CM
42 x 35.32 = 1483.44 Cft. 84.00

Total Loose Material = 2720.16 Cft.

Executive Engineer
Road Construction Division
Lahore.

(MRS 1st Bi-Annual 2017)


DESCRIPTION OF ITEM:

Item No. 6 Providing and laying reinforced cement concrete (including pre-stressed
concrete), using coarse sand and screened graded and washed
aggregate, in required shape and design, including forms, moulds,
shuttering, lifting, compacting, curing, rendering and finishing exposed
surface, complete (but excluding the cost of steel reinforcement, its
fabrication and placing in position etc).

(a) (i) Reinforced cement concrete in roof slab, beams, columns, lintels, girders
and other structural members laid in situ or pre cast laid in position or pre
stressed members cast in situ complete in all respect.

2- Type 'B' (Nominal mix 1 : 1½: 3).

Detail Unit Rate (British System) per Cft

Qty Rate Per Unit Amount (Rs.)

Analysis for 100 Cft


MATERIAL

1 Cement 22.50 bags 533.00 bags 11992.50


2 Sand (Harro) 42.00 Cft 3,700.00 % Cft 1554.00
3 Bajri 84.00 Cft 3,200.00 % Cft 2688.00

4 Shuttering

Wood for shuttering detail as per


item 5-(a) (i)-1 1.62 Cft 1,750.00 per Cft 2835.00
Bolts and nuts, nails 3.5 Kg. 134.00 Per Kg. 469.00
Greasing and oiling for surfacing
and shuttering 2.432 Kg. 85.00 Per Kg. 206.72

Total 19745.22
Contractor's Profit 20 Percent 3949.04
Total 23694.26

LABOUR

1 Mason 1.00 Nos. 625.00 per day 625.00


2 Cooly skilled 1.50 Nos. 625.00 per day 937.50
3 Coolies un-skilled 10.00 No. 550.00 per day 5500.00
4 Bahisthi 2.00 No. 570.00 per day 1140.00
5 Carpanter 1.00 Nos. 625.00 per day 625.00
6 Helper 2.00 Nos. 550.00 per day 1100.00

Total 9927.50
Sundries 10 Percent 992.75
Total 10920.25
Contractor's Profit 20 Percent 2184.05
Total for 100 Cft 13104.30
Rate per Cft
ITEM RATES
Labour rate per Cft Rs. 131.04 Say
Labour rate per Cum Rs. Say

Composite rate per Cft Rs. 367.99 Say 367.99


Composite rate per Cum Rs. ### Say 12997.25

(MRS 1st Bi-Annual 2017)


DESCRIPTION OF ITEM:
Item No. 6 Providing and laying reinforced cement concrete (including pre-stressed
concrete), using coarse sand and screened graded and washed
aggregate, in required shape and design, including forms, moulds,
shuttering, lifting, compacting, curing, rendering and finishing exposed
surface, complete (but excluding the cost of steel reinforcement, its
fabrication and placing in position etc).
(a) (i) Reinforced cement concrete in roof slab, beams, columns, lintels, girders
and other structural members laid in situ or pre cast laid in position or pre
stressed members cast in situ complete in all respect.
2- Concrete Class A2 (4000 PSI)
NESPAK Recommended

Detail Unit Rate (British System) per Cft


Qty Rate Per Unit Amount (Rs.)
Analysis for 100 Cft
MATERIAL
1 Cement 28.03 bags 533.00 bags 14939.69
2 Sand (Harro) 42.00 Cft 3,700.00 % Cft 1554.00
3 Bajri 84.00 Cft 3,200.00 % Cft 2688.00
4 Shuttering
Wood for shuttering detail as per
item 5-(a) (i)-1 1.62 Cft 1,750.00 per Cft 2835.00
Bolts and nuts, nails 3.5 Kg. 134.00 Per Kg. 469.00
Greasing and oiling for surfacing
and shuttering 2.432 Kg. 85.00 Per Kg. 206.72
Total 22692.41
Contractor's Profit 20.0 Percent 4538.48
Total 27230.90
LABOUR
1 Mason 1.00 Nos. 625.00 per day 625.00
2 Cooly skilled 1.50 Nos. 625.00 per day 937.50
3 Coolies un-skilled 10.00 No. 550.00 per day 5500.00
4 Bahisthi 2.00 No. 570.00 per day 1140.00
5 Carpanter 1.00 Nos. 625.00 per day 625.00
6 Helper 2.00 Nos. 550.00 per day 1100.00
Total 9927.50
Sundries 10 Percent 992.75
Total 10920.25
Contractor's Profit 20.0 Percent 2184.05
Total for 100 Cft 13104.30
Rate per Cft
ITEM RATES
Labour rate per Cft Rs. 131.04 Say
Labour rate per Cum Rs. Say
Composite rate per Cft Rs. 403.35 Say
Composite rate per Cum Rs. ### Say

Composite Rate Per Rft. = Rs.403.35


Add extra of Bajri
Qty of Bajri
For %Rft. RCC required Bajri 84.00 Cft.
For 1 Rft RCC required Bajri 0.84 P.Cft.
4047.55 / 100 x 0.84 Rs. 34.00
(As per same carriage of base course)
Total Rs. 437.35 Rft.

Or Rs. 15,447.20 CM

Executive Engineer
Road Construction Division
Lahore.

(MRS 1st Bi-Annual 2017)


DESCRIPTION OF ITEM:

Item No. 6 Providing and laying reinforced cement concrete (including pre-stressed
concrete), using coarse sand and screened graded and washed
aggregate, in required shape and design, including forms, moulds,
shuttering, lifting, compacting, curing, rendering and finishing exposed
surface, complete (but excluding the cost of steel reinforcement, its
fabrication and placing in position etc).

(a) (ii) Reinforcement cement concrete in slab of roofs/strip foundation; base


slab of column and retaining walls; etc., and other structural members
other than those mentioned in 6(a) (i) above not requiring form work
complete in all respects.

2- Type 'B' (Nominal mix 1 : 1½ : 3).

Detail Unit Rate (British System) per Cft

Qty Rate Per Unit Amount (Rs.)

Analysis for 100 Cft


MATERIAL

1 Cement 22.50 bags 533.00 per bag 11992.50


2 Sand (Harro) 42.00 Cft 3,700.00 % Cft 1554.00
3 Bajri 84.00 Cft 3,200.00 % Cft 2688.00
4 Kail Wood for shuttering 0.17 Cft. 1,750.00 P. Cft 297.50
5 Bolts, nuts & nails 0.5 Kg. 134.00 Per Kg. 67.00
6 Oiling, greasing, surface of shuttering 0.560 Kg. 85.00 Per Kg. 47.60

Total 16646.60
Contractor's Profit 20 Percent 3329.32
Total 19975.92

LABOUR

1 Mason 1.00 Nos. 625.00 per day 625.00


2 Cooly skilled 1.00 Nos. 625.00 per day 625.00
3 Coolies un-skilled 5.00 No. 550.00 per day 2750.00
4 Bahisthi 1.00 No. 570.00 per day 570.00
5 Carpanter 1.00 Nos. 625.00 per day 625.00
6 Helper 1.00 Nos. 550.00 per day 550.00

Total 5745.00
Sundries 10 Percent 574.50
Total 6319.50
Contractor's Profit 20 Percent 1263.90
Total rate for 100 Cft 7583.40
Rate per Cft 27559.32

ITEM RATES

Labour rate per Cft Rs. 75.83 Say


Labour rate per Cum Rs. Say

Composite rate per Cft Rs. 275.59 Say


Composite rate per Cum Rs. 9,733.95 Say

(MRS 1st Bi-Annual 2017)


DESCRIPTION OF ITEM:

Item No. 6 Providing and laying reinforced cement concrete (including pre-stressed
concrete), using coarse sand and screened graded and washed
aggregate, in required shape and design, including forms, moulds,
shuttering, lifting, compacting, curing, rendering and finishing exposed
surface, complete (but excluding the cost of steel reinforcement, its
fabrication and placing in position etc).

(a) (ii) Reinforcement cement concrete in slab of roofs/strip foundation; base


slab of column and retaining walls; etc., and other structural members
other than those mentioned in 6(a) (i) above not requiring form work
complete in all respects.

2- Concrete Class A2 (4000 PSI)


NESPAK Recommended

Detail Unit Rate (British System) per Cft


Qty Rate Per Unit Amount (Rs.)
Analysis for 100 Cft
MATERIAL
1 Cement 28.03 bags 533.00 per bag 14939.69
2 Sand (Harro) 42.00 Cft 3,700.00 % Cft 1554.00
3 Bajri 84.00 Cft 3,200.00 % Cft 2688.00
4 Kail Wood for shuttering 0.17 Cft. 1,750.00 P. Cft 297.50
5 Bolts, nuts & nails 0.5 Kg. 134.00 Per Kg. 67.00
6 Oiling, greasing, surface of shuttering 0.560 Kg. 85.00 Per Kg. 47.60

Total 19593.79
Contractor's Profit 20 Percent 3918.76
Total 23512.55

LABOUR

1 Mason 1.00 Nos. 625.00 per day 625.00


2 Cooly skilled 1.00 Nos. 625.00 per day 625.00
3 Coolies un-skilled 5.00 No. 550.00 per day 2750.00
4 Bahisthi 1.00 No. 570.00 per day 570.00
5 Carpanter 1.00 Nos. 625.00 per day 625.00
6 Helper 1.00 Nos. 550.00 per day 550.00

Total 5745.00
Sundries 10 Percent 574.50
Total 6319.50
Contractor's Profit 20 Percent 1263.90
Total rate for 100 Cft 7583.40
Rate per Cft 31095.95
ITEM RATES
Labour rate per Cft Rs. 75.83 Say
Labour rate per Cum Rs. Say

Composite rate per Cft Rs. 310.96 Say


Composite rate per Cum Rs. ### Say

Composite Rate Per Rft. = Rs.310.96


Add extra of Bajri
Qty of Bajri
For %Rft. RCC required Bajri 84.00 Cft.
For 1 Rft RCC required Bajri 0.84 P.Cft.
4047.55 / 100 x 0.84 Rs. 34.00
(As per same carriage of base course)
Total Rs. 344.96 Rft.

Or Rs. 12,183.99 CM

(MRS 1st Bi-Annual 2017)


Executive Engineer
Road Construction Division
Lahore.

(MRS 1st Bi-Annual 2017)


ANALYSIS ON MARKET RATES.

Unit = P.Cft.
Lead = 180 Km.
1 P/L R.C.C 1:1:2 without horizontal shuttering.

Basic Rate for 1 Cft RCC = 334.65


Add Carriage of Bajri

Qty of Bajri
For %Cft. RCC 78.00 Cft.
For One Cft RCC 0.78 P.Cft.
4047.55 / 100 x 0.78 = 31.57
(As per same carriage of base course)
Total = Rs.366.22

Or = Rs.12,934.89 P.CM

2 P/L R.C.C 1:1.50:3 without horizontal shuttering.

Basic Rate for 1 Cft RCC = 275.60


Add Carriage of Bajri

Qty of Bajri
For %Cft. RCC 84.00 Cft.
For One Cft RCC 0.84 P.Cft.
4047.55 / 100 x 0.84 = 34.00
(As per same carriage of base course)
Total = Rs.309.60

Or = Rs.10,935.07 P.CM

3 P/L R.C.C 1:2:4 without horizontal shuttering.

Basic Rate for 1 Cft RCC = 246.45


Add Carriage of Bajri

Qty of Bajri
For %Cft. RCC 88.00 Cft.
For One Cft RCC 0.88 P.Cft.
4047.55 / 100 x 0.88 = 35.62
(As per same carriage of base course)
Total = Rs.282.07

Or = Rs.9,962.71 P.CM

Executive Engineer
(MRS 1st Bi-Annual 2017)
Road Construction Division
Lahore.

(MRS 1st Bi-Annual 2017)


ANALYSIS ON MARKET RATES.

Unit = P%Cft.
Lead = 180

1 P/L P.C.C 1:3:6.

Basic Rate for %Cft. = 18087.25

Add Carriage of Bajri

For %Cft. Material 92.00 Cft.

4047.55 / 100 x 92.00 = 3723.75


(As per same carriage of base course)

Total = Rs.21,811.00

Or = 7703.65 P.CM

Executive Engineer
Road Construction Division
Lahore.

(MRS 1st Bi-Annual 2017)


Km.

(MRS 1st Bi-Annual 2017)


ANALYSIS ON MARKET RATES.

Unit = P%Cft.
Lead = 180

1 P/L P.C.C 1:2:4 plain.

Basic Rate for %Cft. = 20849.40

Add Carriage of Bajri

For %Cft. Material 88.00 Cft.

4047.55 / 100 x 88.00 = 3561.84


(As per same carriage of base course)

Total = Rs.24,411.24

2 P/L P.C.C 1:4:8.

Basic Rate for %Cft. = 16092.60

Add Carriage of Bajri

For %Cft. Material 96.00 Cft.

4047.55 / 100 x 96.00 = 3885.65


(As per same carriage of base course)

Total = Rs.19,978.25

Executive Engineer
Road Construction Division
Lahore.

(MRS 1st Bi-Annual 2017)


Km.

(MRS 1st Bi-Annual 2017)


Analysis of Rate for cold milling including diposal upto 3 km
UNIT = 100
LEAD = 3.00

1 Dismantling of asphalt using cold milling technique ( upto 2 inch) = Rs.17.00

2 Transportation of metal for every upto1/4 mile. ( 1320 Rft )

0.25 Mile 5280 x 0.25 = 1320 Rft = 2821.40

3 Subsequent lead beyond 1/4 Mile upto 1 Mile for every 330'

5280 x 0.25 = 1320 Rft

5280 - 1320 = 3960 Rft

3960 / 330 = 12.00 Segments / part

( Note 1 Segment 330 Rft )

@ Rs 10.15 Per Segment ( part ) = 121.80

4 Subsequent lead beyond I Mile upto (3 Km) for every 1/4 Mile

9840 - 5280 4560 Rft

4560 / 1320 = 3.45

( Note 1 Segment 1320 Rft )

@ Rs 158.00 Per Segment ( part ) = 545.10


( for 1000 Cft) S.Total = 3488.30

Rate of 100 Cft. 3488.30 x 100 = Rs.348.83


1000

Total = Rs.365.83

Executive Engineer
Road Construction Division
Lahore.
Sft.
Km
Analysis of Rate for Disposal of Unsuitable Material with 3 Km Lead.

UNIT = 100 Cft.


LEAD = 3.00 Km

1 Transportation of metal for every upto1/4 mile. ( 1320 Rft )

0.25 Mile 5280 x 0.25 = 1320 Rft = Rs. 2821.40

2 Subsequent lead beyond 1/4 Mile upto 1 Mile for every 330'

5280 x 0.25 = 1320 Rft

5280 - 1320 = 3960 Rft

3960 / 330 = 12.00 Segments / part

( Note 1 Segment 330 Rft )

@ Rs 10.15 Per Segment ( part ) = Rs. 121.80

3 Subsequent lead beyond I Mile upto (3 Km) for every 1/4 Mile

9840 - 5280 4560 Rft

4560 \ 1320 = 3.45 Segments

@ Rs 164.90 Per Segment ( part ) = Rs. 569.65

Total = Rs. 3512.85

Rate Per CM = Rs. 124.07

Executive Engineer
Road Construction Division
Lahore.

(MRS 1st Bi-Annual 2017)


ANALYSIS ON MARKET RATES.

Unit = P%Sft.
Lead = 180 Km.

1 P/L Plant premixed bituminous Asphaltic Base Course


carpet with 4.0 % bitumen contents.

Basic Rate for 1" thick carpet = 2644.15

Add Cost of Carriage of Bajri for 1" thick carpet

For 1" thick carpet 8.225

4047.55 / 100 x 8.225 = 332.91


(As per same carriage of base course)

Total = Rs.2,977.06

Rate Per CM = 12,617.97

2 P/L Plant premixed bituminous Asphaltic Wearing


Course carpet with 4.5 % bitumen contents.

Basic Rate for 1" thick carpet = 2819.45

Add Cost of Carriage of Bajri for 1" thick carpet

For 1" thick carpet required Bajri 8.225 Cft.

4047.55 / 100 x 8.225 = 332.91


(As per same carriage of base course)

Total = Rs.3,152.36

Rate Per CM = 13,360.96

Executive Engineer
Road Construction Division
Lahore.

(MRS 1st Bi-Annual 2017)


MARKET RATES ANALYSIS WITH CARRIAGE

ESTABLISHMENT OF FLYOVER ACROSS RAILWAY TRACK IN RAIWIND CITY DISTRICT LAHORE

1 Sub Base Course

Providing and laying sub-base course of stone product of


approved quality and grade, including placing, mixing, spreading
and compaction of sub-base material to required depth, grade to
achieve 100% maximum modified AASHO dry density, excluding
carriage of material.
(Lead 180 Kms) (From Sikhanwali Quarry)

Crushed stone aggregat {Chapter 18 item No.8(a)} = Rs. 3,653.25


Carriage charges

Carriage charges for %Cft Material


(Rate with lead upto 10 Km) Rs.571.05
Km 10 to 180 = 170 Km @ 20.45 Per Km. Rs.3,476.50

S.Total Rs.4,047.55

Add Carriage charges for 20 Cft Material (Loos)

Rs.4,047.55 x 0.20 (+) Rs. 809.51

Total Rs.4,857.06 = Rs.4,857.06

Total = Rs.8,510.31
Rate Per CM = Rs.3,005.84
2 Base Course

Providing and laying base course of crushed stone aggregate of


approved quality and grade and supply and spreading of stone
screening including placing mixing spreading and compaction of
base course material to required camber and grade to achieve
100% ex

(Lead 180 Kms) (From Sikhanwali Quarry)

Crushed stone aggregat {Chapter 18 item No.8(a)} = Rs. 6,010.95


Carriage charges

Carriage charges for %Cft Material


(Rate with lead upto 10 Km) Rs.571.05
Km 10 to 180 = 170 Km @ 20.45 Per Km. Rs.3,476.50

S.Total Rs.4,047.55

Add Carriage charges for 22 Cft Material (Loos)

Rs.4,047.55 x 0.22 (+) Rs. 890.46

Total Rs.4,938.01 = Rs.4,938.01

Total = Rs.10,948.96

Rate Per CM = Rs.3,867.17

Executive Engineer

(MRS 1st Bi-Annual 2017)


Road Construction Division
Lahore.

(MRS 1st Bi-Annual 2017)


Analysis of Rate for P/L Sand Filling
UNIT = 100 Cft.

1 P/L Sand Filling = Rs. 1100

Add 20% contractor profit = Rs. 220

= Rs. 1320.00

Compaction charges 95%. 596.75

596.75 x 100 = Rs. 59.68


1000

Total = Rs. 1379.68

Rate Per CM = Rs. 487.30

Executive Engineer
Road Construction Division
Lahore.

(MRS 1st Bi-Annual 2017)


Analysis of Rate for Making Embankment 95% Compaction
UNIT = 1000 Cft.
LEAD = 5.00 Km

1 Making embankment 95% without compaction = Rs. 5033.00

2 Transportation of metal for every upto1/4 mile. ( 1320 Rft )

0.25 Mile 5280 x 0.25 = 1320 Rft = Rs. 2821.40

3 Subsequent lead beyond 1/4 Mile upto 1 Mile for every 330'

5280 x 0.25 = 1320 Rft

5280 - 1320 = 3960 Rft

3960 / 330 = 12.00 Segments / part

( Note 1 Segment 330 Rft )

@ Rs 10.15 Per Segment ( part ) = Rs. 121.80

4 Subsequent lead beyond I Mile upto (5 Km) for every 1/4 Mile

16400 - 5280 11120 Rft

11120 \ 1320 = 8.42 Segments

@ Rs 164.90 Per Segment ( part ) = Rs. 1389.16

Total = Rs. 9365.36

Rate Per CM = Rs. 330.78

Executive Engineer
Road Construction Division
Lahore.

(MRS 1st Bi-Annual 2017)


Analysis of Rate for Excavation & Removal of Unsuitable Material with 3 Km Lead.

UNIT = 1000 Cft.


LEAD = 3.00 Km

1 Regular Excavation Undressed = Rs. 2613.60

1 Transportation of metal for every upto1/4 mile. ( 1320 Rft )

0.25 Mile 5280 x 0.25 = 1320 Rft = Rs. 2821.40

2 Subsequent lead beyond 1/4 Mile upto 1 Mile for every 330'

5280 x 0.25 = 1320 Rft

5280 - 1320 = 3960 Rft

3960 / 330 = 12.00 Segments / part

( Note 1 Segment 330 Rft )

@ Rs 10.15 Per Segment ( part ) = Rs. 121.80

3 Subsequent lead beyond I Mile upto (3 Km) for every 1/4 Mile

9840 - 5280 4560 Rft

4560 \ 1320 = 3.45 Segments

@ Rs 164.90 Per Segment ( part ) = Rs. 569.65

Total = Rs. 6126.45

Rate Per CM = Rs. 216.39

Executive Engineer
Road Construction Division
Lahore.

(MRS 1st Bi-Annual 2017)


CONSTRUCTION OF ADDITIONAL BRIDGE OVER RIVER RAVI

Calculation Backup
Bill # 1 Earthwork and Allied Activities
Length Width Depth
Item # Item Description Unit No Quantity Remarks
m m m
101 Clearing & Grubbing SM

From Nazi Chowk & Toll Plaza Ramps 2 100 19.6 3,920

I Land 2 200 4 1,600

Total 5,520

Add 10% 552

Net Total 6,072

Say 6,080

104 Compaction of Natural Ground SM

From Nazi Chowk & Toll Plaza Ramps 2 100 19.6 3,920

I Land 2 200 4 1,600

Total 5,520

Add 10% 552

Net Total 6,072

Say 6,080

Excavate Unsuitable/Surplus Common


106a CM
Material

From Nazi Chowk & Toll Plaza Ramps 2 100 2.5 1 500

Widening of Niazi Chowk Interchange toword


1 50 25 5.1 6,375
Shahdara side

Niazi Chowk Ring Road 2 100 50 5.5 55,000

Total 61,875

Add 10% 6,188

Net Total 68,063

Say 68,070

107di Granular Backfill with Sand CM

From Nazi Chowk & Toll Plaza Ramps 2 500 2.5 1 2,500

Total 2,500

Add 10% 250

Net Total 2,750

Say 2,750

(Bill No.1) Page50


CONSTRUCTION OF ADDITIONAL BRIDGE OVER RIVER RAVI

Calculation Backup
Bill # 1 Earthwork and Allied Activities
Length Width Depth
Item # Item Description Unit No Quantity Remarks
m m m
Formation of embankment from Borrow
108c CM
Excavation in Common Material

From Nazi Chowk & Toll Plaza Ramps 2 100 19.8 5 19,800

Total 19,800
Add 10% 1,980
Net Total 21,780

Say 21,780

109a Subgrade Preparation in Earth Cut SM

I Land 2 100 15.6 3,120

Widening of Niazi Chowk Interchange toword


1 50 25 1,250
Shahdara side

Total 4,370

Add 10% 437

Net Total 4,807


Say 4,810

(Bill No.1) Page51


CONSTRUCTION OF ADDITIONAL BRIDGE OVER RIVER RAVI

Calculation Backup
Bill # 2 Sub Base and Base
Length Width Depth
Item # Item Description Unit No Quantities Remarks
m m m

201 Granular Subbase CM

From Nazi Chowk & Toll Plaza Ramps 2 100 16.80 0.20 672.00

I Land 1 100 4.00 0.20 80.00

MBS Portion 1 400 9.40 0.20 752.00

Existing Road Nazi Chowk Side 1 200 29.20 0.20 1,168.00

Existing Road Toll Plaza Side 1 200 14.60 0.20 584.00

Road Toll Plaza Side 1 100 16.80 0.20 336.00

Slip Lane from Ring Road 1 50 10.40 0.20 104.00

Widening of Niazi Chowk Interchange


1 5,500 0.20 1,100.00
toword Shahdara side

Ring Road 1 100 45.00 0.20 20.00

Reused of Existing Subbase (2,619.00)

Total 1,445

Add 10% 145

Net Total 1,590

Total 2,197.00

Reuse of Broken Pavement Material


201a CM 2,619.00
from Existing Road as Subbase

Asphaltic Base Course Plant Mix(Class


203b CM
B)

From Nazi Chowk & Toll Plaza Ramps 2 100 16.80 0.15 504.00

MBS Portion 1 400 9.40 0.15 564.00

Existing Road Nazi Chowk Side 1 200 29.20 0.15 876.00

Existing Road Toll Plaza Side 1 200 14.60 0.15 438.00

Road Toll Plaza Side 1 100 19.60 0.15 294.00

Slip Lane from Ring Road 1 50 10.40 0.15 78.00

Widening of Niazi Chowk Interchange


1 5,500 0.15 825.00
toword Shahdara side

Ring Road 1 100 45.00 0.15 675.00

Total 4,254.00

Total 4,254

Add 10% 425

Net Total 4,679

Say 4,680

Water Bound Macadam Base with Coarse


206 Aggregate Class B
CM

From Nazi Chowk & Toll Plaza Ramps 2 100 16.80 0.25 840.00

MBS Portion 1 300 7.60 0.25 570.00

(Bill No.2)
CONSTRUCTION OF ADDITIONAL BRIDGE OVER RIVER RAVI

Calculation Backup
Bill # 2 Sub Base and Base
Length Width Depth
Item # Item Description Unit No Quantities Remarks
m m m

Existing Road Nazi Chowk Side 1 295 29.20 0.25 2,153.50

Existing Road Toll Plaza Side 1 200 14.60 0.25 730.00

Road Toll Plaza Side 1 100 16.80 0.25 420.00

Slip Lane from Ring Road 1 50 10.40 0.25 130.00

Widening of Niazi Chowk Interchange


1 6,000 0.25 1,500.00
toword Shahdara side

Ring Road 1 100 45.00 0.25 1,125.00

Total 7,469

Add 10% 747

Net Total 8,215

Say 8,220

207a Deep Patching ( 0 - 15 cm ) SM

2 10 5.0 100.00

Total 100.00

207b Deep Patching (15 - 30 cm ) SM

2 10 5.0 100.00

Total 100.00

Breaking of Existing Road Pavement


209a CM Areas
Structure
Road MBS Portion 1 500 10.00 0.200 1,000.00
Existing Road Nazi Chowk Side 1 500 29.20 0.200 2,920.00
Existing Road Toll Plaza Side 1 200 14.60 0.200 584.00
Slip Lane from Ring Road 1 200 10.40 0.200 416.00
Widening of Niazi Chowk Interchange
1 6,000 0.200
toword Shahdara side
Ring Road 1 100 45.00 0.200 900.00
Total Qty For Asphaltic Layer 5,820.00 2,910.00
Total Qty For Aggregate Layer 2,910.00 2,619.00
291.00
Total 5,820

Add 10% 582

Net Total 6,402

Say 6,410

(Bill No.2)
CONSTRUCTION OF ADDITIONAL BRIDGE OVER RIVER RAVI

Calculation Backup
Bill # 2 Sub Base and Base
Length Width Depth
Item # Item Description Unit No Quantities Remarks
m m m

Scarification of Existing Road


209b SM
Pavement

Token Quantity 2 10 5.0 100.00

Total 100.00

Disposal of Existing Unusable Road


209c CM
Pavement Structure (Asphaltic)

qty from Item no 209a 3,201.00

(1102+110.2)

Total 3,201.00

309a Cold Milling S.M

Existing Bridge 1 505 14 7,070.00

New Bridge 1 505 10 5,050.00

Total 12,120

Add 10% 1,212

Net Total 13,332

Say 13,340

- Cutting of Asphalt with Saw L.M

Center Median 4 200 800.00

Total 800

Add 10% 80

Net Total 880

Say 880

(Bill No.2)
CONSTRUCTION OF ADDITIONAL BRIDGE OVER RIVER RAVI

Calculation Backup
Bill # 3 Surface Courses and Pavement
Length Width Depth
Item # Item Description Unit No Quantities Remarks
m m m
302 Bituminous Prime Coat SM

From Nazi Chowk & Toll Plaza Ramps 2 100 16.80 3,360.00

MBS Portion 1 400 7.60 3,040.00


Existing Road Nazi Chowk Side 1 200 29.40 5,880.00
Existing Road Toll Plaza Side 1 200 14.60 2,920.00
Road Toll Plaza Side 1 100 16.80 1,680.00
Slip Lane from Ring Road 1 50 10.40 520.00
Widening of Niazi Chowk Interchange
1 6,000 6,000.00
toword Shahdara side
Ring Road 1 100 45.00 4,500.00
Total 27,900
Add 10% 2,790
Net Total 30,690
Say 30,690

303 Bituminous Tack Coat SM

From Nazi Chowk & Toll Plaza Ramps 4 100 16.80 6,720.00

MBS Portion 2 400 7.60 6,080.00


MBS Bridge Portion 1 500 7.60 3,800.00
Existing Bridge 1 505 5.00 2,525.00
New Bridge 1 505 16.80 8,484.00
Existing Road Nazi Chowk Side 2 200 29.20 11,680.00
Existing Road Toll Plaza Side 2 200 14.60 5,840.00
Road Toll Plaza Side 2 100 16.80 3,360.00
Slip Lane from Ring Road 2 50 10.40 1,040.00
Existing Loops 1 252.5 8.00 2,020.00
Existing Ramps 1 332 10.40 3,452.80
Widening of Niazi Chowk Interchange
1 6,000 6,000.00
toword Shahdara side
Ring Road 1 100 45.00 4,500.00
Total 65,502
Add 10% 6,550
Net Total 72,052
Say 72,060

Asphaltic Wearing Course Plant Mix


305 CM
(Class A)

From Nazi Chowk & Toll Plaza Ramps 2 100 16.80 0.05 168.00

MBS Portion 1 400 7.60 0.05 152.00

MBS Bridge Portion 1 500 7.60 0.05 190.00

Existing Bridge 1 505 5.00 0.05 126.25

New Bridge 1 505 16.80 0.05 424.20

Existing Road Nazi Chowk Side 1 200 29.20 0.05 292.00

Existing Road Toll Plaza Side 1 200 14.60 0.05 146.00

Road Toll Plaza Side 1 100 16.80 0.05 84.00


(Bill No.30
CONSTRUCTION OF ADDITIONAL BRIDGE OVER RIVER RAVI

Calculation Backup
Bill # 3 Surface Courses and Pavement
Length Width Depth
Item # Item Description Unit No Quantities Remarks
m m m
Slip Lane from Ring Road 1 50 10.40 0.05 26.00

Existing Loops 1 252.5 8.00 0.05 101.00

Existing Ramps 1 332 10.40 0.05 172.64

Widening of Niazi Chowk Interchange


1 6,000 0.05 300.00
toword Shahdara side
Ring Road 1 100 45.00 0.05 225.00
Total 2,407
Add 10% 241
Net Total 2,648
Say 2,650

(Bill No.30
CONSTRUCTION OF ADDITIONAL BRIDGE OVER RIVER RAVI
Back up Calculations

BILL No. 4.1 STRUCTURES (BRIDGE)


FOR 19.6m DECK
Item L W H No.
Description Unit Quantity
No. (m) (m) (m)

401 a (i) Approach Slab, Concrete Class A1 CM 19.6 4 0.3 2 47.04


CM 19.6 0.45 0.15 2 2.65
Reinforcement @ 120 kg/CM ton 5.96

401 b (ii) Wing Wall, Concrete Class A2 CM 4 0.4 2 4 12.80


CM 4 0.4 0.757 4 4.84
Reinforcement @ 120 kg/CM ton 2.12

401 a (i) N.J.Barrier, Concrete Class A1 CM 493 0.25 2 246.50


Reinforcement @ 100 kg/CM ton 24.65

401 a (ii) Concrete Bearing Pads, Concrete Class A1 CM 0.6 0.7 0.15 168 10.58
Reinforcement @ 100 kg/CM ton 1.06

401 b (ii) Diaphragms, Concrete Class A2 CM 15.3 0.3 2.05 60 564.57


Reinforcement @ 150 kg/CM ton 84.69

401 b (ii) Deck Slab Concrete Class A2 CM 493 19.6 0.225 1 2,174.13
Reinforcement @ 120 kg/CM 260.90

401 d Prestress 'I' Girder, Concrete Class D1 CM 40.9 0.9805 84 3,873.90


Reinforcement @ 170 kg/CM ton 658.56

405 a Tendons (0.5 " dia) Prestressed steel Wires in Girders Ton 309.91
@ 80 kg/CM

405 b Launching of Precast Girders Ton @ 2.4 X Qty. in CM 9,297.35

401 b (ii) Transom Concrete Class A2 CM 18.5 2 1.5 11 610.50


Retaining Block Concrete Class A2 CM 1.975 0.5 0.6 44 26.07
CM 1.975 0.125 0.6 8 1.19
Reinforcement @ 150 kg/CM ton 95.66

401 b (ii) Piers, Concrete Class A2 CM 6 1.767 65 689.17


Reinforcement @ 220 kg/CM ton 151.62

401 b (ii) Abutment Girder Seat , Concrete Class A2 CM 19.6 2 1.5 2 117.60
CM 19.6 0.3 2.25 2 26.46
CM 19.6 0.3 0.525 2 6.17
Reinforcement @ 150 kg/CM ton 22.54

401f Lean Concrete CM 19.6 4.075 0.075 2 11.98


CM 19.6 2.15 0.075 2 6.32

404 b Total Reinforcement as AASHTO M-31 Grade-60 Ton 2,849.03

407 k 1500 mm dia. Cast inplace Concrete Piles LM 65 10 650.00


Piles under Abutment Concrete Class A3 LM 65 55 3,575.00
Test Pile LM 65 2 130.00

CM 65 A= 1.77 10 1,148.55
CM 65 A= 1.77 55 6,327.75
Test Pile CM 65 A= 1.77 2 230.10
Reinforcement @ 200 kg/CM Ton 1,541.28

407 m Pile Load Test Dia 1500 mm Each 1.00


(upto 2.5 times the design load)

407 n Proof Load Test Dia 1500 mm Each 2.00


(upto 1.5 times the design load)

SP 423 Finger Type Expansion Joint LM 19.6 13 254.80


CONSTRUCTION OF ADDITIONAL BRIDGE OVER RIVER RAVI
Back up Calculations

BILL No. 4.1 STRUCTURES (BRIDGE)


FOR 19.6m DECK
Item L W H No.
Description Unit Quantity
No. (m) (m) (m)
406 d Free/Fix End Steel Support KG 30 Kg/ plate 168 5,040.00
CONSTRUCTION OF ADDITIONAL BRIDGE OVER RIVER RAVI
Back up Calculations

BILL No. 4.1 STRUCTURES (BRIDGE)


FOR 19.6m DECK
Item L W H No.
Description Unit Quantity
No. (m) (m) (m)

cubic
406 c Elastomeric Bearing Pads centi 50 60 8.7 168 4,384,800.00
meter

SP 418a 100 mm Dia. G.I. Drain Pipe Each 300 300.00

SP 416 100 mm Dia. C.I. Drain Pipe LM 493 4 1,972.00

SP 419b Providing and Fixing Steel Hand Rail LM 493 1 493.00

407p MS Steel Linner 10mm THICK LM 6 55 346.50


TION OF ADDITIONAL BRIDGE OVER RIVER RAVI
Back up Calculations

BILL No. 4.1 STRUCTURES (BRIDGE)


FOR 19.6m DECK
Quantity

49.69

17.64

246.50

10.58

564.57

2,174.13

3,873.90

310.00

11,157.00

637.76

689.17

150.23

18.30

2,849.03

4,355.00

1.00

2.00

254.80
TION OF ADDITIONAL BRIDGE OVER RIVER RAVI
Back up Calculations

BILL No. 4.1 STRUCTURES (BRIDGE)


FOR 19.6m DECK
Quantity

5,040.00
TION OF ADDITIONAL BRIDGE OVER RIVER RAVI
Back up Calculations

BILL No. 4.1 STRUCTURES (BRIDGE)


FOR 19.6m DECK
Quantity

4,384,800.00

300.00

1,972.00

493.00

346.50
CONSTRUCTION OF ADDITIONAL BRIDGE OVER RIVER RAVI
Calculation Backup
Bill # 4.2 Structures (Drain / NJB)
Length Width Depth
Item # Item Description Unit No Quantity
m m m
107a Structural Excavation CM
New Drain Wall 2 100 2.23 1.4 624.4
Total 624
Add 10% 62
Net Total 687
Say 690

107d Granular Backfill CM


New Drain Wall 2 100 0.3 1 60

Total 60
Add 10% 6
Net Total 66
Say 70

401b(i) Concrete Class A-2(On Ground) CM

Base Slab Drain 1 500 1.93 0.250 241.25

Total 241
Add 10% 24
Net Total 265
Say 270

401 a(ii) Concrete Class A-2 (Elevated) CM

Concrete Top Slab of drain

New RCC Drain Top 2 500 1.93 0.250 482.50

New RCC Drain wall 4 500 0.20 1.000 400.00

Total 883

Add 10% 88

Net Total 971

Say 980

401b(i) Concrete Class A2 for NJB With Slipform Paver CM

Both Side of MBS slip form Barrier

Both Side of MBS slip form Barrier Double Face 2 500 0.307 307.00

Both Side of MBS slip form Barrier Double Face 1 200 0.307 61.40

Total 368

Add 10% 37

(Bill No.4.2)
CONSTRUCTION OF ADDITIONAL BRIDGE OVER RIVER RAVI
Calculation Backup
Bill # 4.2 Structures (Drain / NJB)
Length Width Depth
Item # Item Description Unit No Quantity
m m m

Net Total 405

Say 410

401f Lean Concrete CM

New Drain Slab 1 500 1.93 0.100 96.50

Both Side of MBS slip form Barrier Double Face 2 500 0.70 0.050 35.00

Both Side of MBS slip form Barrier Double Face 1 100 0.70 0.050 3.50

Total 135

Add 10% 14

Net Total 149

Say 150

404b Reinforcement As per AASHTO M-31 Grade -60 Ton

Base Slab @ 60Kg/Cu.m 16.20

Both Side of MBS slip form Barrier @ 60 Kg / Cum 24.60

Total 40.80

406a Expansion Joint Including Sealent/Filler L.M

12.5 4 50.00

Total 50

Add 10% 5

Net Total 55

Say 60

413d Galvanised Mild Steel Grating S.M

66.67 66.67

Total 67

Add 10% 7

Net Total 73

Say 80

(Bill No.4.2)
CONSTRUCTION OF ADDITIONAL BRIDGE OVER RIVER RAVI
Calculation Backup
Bill # 4.2 Structures (Drain / NJB)
Length Width Depth
Item # Item Description Unit No Quantity
m m m

410a Brick Work CM

1.00 100.0 0.75 2.00 150.00

Total 150

Add 10% 15

Net Total 165

Say 170

(Bill No.4.2)
CONSTRUCTION OF ADDITIONAL BRIDGE OVER RIVER RAVI

Calculation Backup

Bill # 5 Drainage and Erosion Works


Length Width Depth
Item # Item Description Unit No Quantity
m m m
510a Dismantling Of RCC Structures CM

Barrier 2 100 0.35 70.00

2 100 0.35 70.00

Drain 1 500 3 0.50 750.00

Existing Bridge Nazi Chowk 1 430 0.50 215.00

Barrier 1 500 0.307 153.50

Girder 20 25 0.980 490.00

Abutment 1 46 5.500 0.600 151.80

Total 1,900.30

Add 10% 190.03

Net Total 2,090.33

Say 2,100.00

510b Dismantling of PCC structures CM

2 167.00 2.00 0.30 100.00

Total 100.00

Add 10% 10.00

Net Total 110.00

Say 110.00

510c Dismantling of Brick masonry CM

Building 4.00 3.50 3.50 10.00 490.00

Total 490.00

Add 10% 49.00

Net Total 539.00

Say 540.00

509a Riprap Class "A" CM

River Ravi Portection 1 150 7.0 1.00 1,050.00

Total 1,050.00

Add 10% 105.00

Net Total 1,155.00

Say 1,160.00

509i Grouted Rip Rap CM

River Ravi Portection 2 200 5.0 0.30 600.00

Total 600.00
Add 10% 60.00
Net Total 660.00
Say 660.00
CONSTRUCTION OF ADDITIONAL BRIDGE OVER RIVER RAVI

Calculation Backup
Bill # 6 Ancillary Works
Length Width Depth
Item # Item Description Unit No Quantity Remarks
m m m

Concrete Class "A1" in haunches around


401a(i)
PVC pipes
CM

DUCT 6 20 0.5 0.3 18.00 Area


Total 18
Add 10% 2
Net Total 20
Say 20

601a Pre-cast Kerb (Non-Mountable) I/c Painting M

Curbstone for Walkway Both Side 2 400 800.00

MBS Portion Bridge 2 500 1,000.00

Miscellaneous islands 1 500 500.00

Total 2,300

Add 10% 230

Net Total 2,530

Say 2,530

601b Pre cast Edge Kerb M

Curbstone for Walkway Both Side 2 400 800.00

Miscellaneous islands 1 500 500.00

Total 1,300
Add 10% 130
Net Total 1,430

Say 1,430

Traffic Signs, Triangular sides 1200 mm with


607a Each 5.00
Post

607b Traffic Signs, Circular dia 1200 mm with Post Each 5.00

607ci Traffic Signs, with single post assembly Sq.-m 25.00

607cii Traffic Signs, with double post assembly Sq.-m 25.00

Manufacture & Installation of Gantry Sign


607d Each 2.00
Type-I
Manufacture & Installation of Gantry Sign
607f Each 2.00
Type-IV
Pavement marking in Thermoplastic paint
608a M
for lines of 15cm wide
Yellow Line
From Nazi Chowk & Toll Plaza Ramps 2 100 200.00

Bridge Portion 2 505 1,010.00

Existing Bridge 2 505 1,010.00

MBS Portion 2 400 800.00

Existing Road 4 500 2,000.00

Ring Road 2 100 200.00

White Line

From Nazi Chowk & Toll Plaza Ramps 0.66 100 66.00

Bridge Portion 1.32 505 666.60

Existing Bridge 2.64 505 1,333.20

MBS Portion 0.66 400 264.00

Existing Road 2.64 500 1,320.00

Ring Road 2.67 100 266.67

(Bill No.6)
CONSTRUCTION OF ADDITIONAL BRIDGE OVER RIVER RAVI

Calculation Backup
Bill # 6 Ancillary Works
Length Width Depth
Item # Item Description Unit No Quantity Remarks
m m m

Total 9,136

Add 10% 914

Net Total 10,050

Say 10,060

Pavement marking with Thermoplastic


608b paint for Arrows, stops, pedestrian SM
crossing, hatch area etc. as specified

Zebra crossing, stop lines, etc. Token 100 100.00

Total 100

Add 10% 10

Net Total 110

Say 110

Reflectorized pavement Studs


609c No
(Single Side)

No of studs @ 10 m c/c 12 161 1,926.00

No of studs @ 10 m c/c 4 51 202.00

No of studs @ 10 m c/c 4 10 40.00

Total 2,168

Add 10% 217

Net Total 2,385

Say 2,390

SP-619 Providing and Fixing of BRTS Fencing Lm

Length along main Carriage way 2 400 800.00

Total 800

Add 10% 80

Net Total 880

Say 880

SP 614(i) Paving Tiles on Drain Slab SM

MBS Bridge 2 500 1 1,200.00

New Bridge 1 500 2 1,000.00

Total 2,200

Add 10% 220

Net Total 2,420

Say 2,420

SP 614(ii) Paving Tiles on Compacted Soil SM

Walkway Both Side 2 400 2 1,600.00

Total 1,600

Add 10% 160

(Bill No.6)
CONSTRUCTION OF ADDITIONAL BRIDGE OVER RIVER RAVI

Calculation Backup
Bill # 6 Ancillary Works
Length Width Depth
Item # Item Description Unit No Quantity Remarks
m m m

Net Total 1,760

Say 1,760

SP 617(i) Dismantling and removal of walkways M

Old Walkway Both Side 2 400 2 1,600.00

Total 1,600
Add 10% 160
Net Total 1,760

Say 1,760

Dismantling ,removal and stockpiling of


SP 617(ii) M
Kerb stones of walkways

Side Walkway 2 400 800.00

Total 800

Add 10% 80

Net Total 880

Say 880

Dismantling ,Removal and Stockpiling of


SP 617(iii) SM
Paving tiles of walkways

Side Walkway 2 200 2 800.00

Total 800

Add 10% 80

Net Total 880

Say 880

Reuse of Kerb stone after removal i/c


SP 618(i) M
painting

Total 100.00

SP 618(ii) Reuse of paving tiles after removal SM Total 100.00

Dismantling of Existing Railing L.M

2 400 800.00

1 500 500.00

Total 1,300

Add 10% 130

Net Total 1,430

Say 1,430

(Bill No.6)
CONSTRUCTION OF ADDITIONAL BRIDGE OVER RIVER RAVI

ENGINEER'S ESTIMATE
SUMMARY
Amount
Bill No. Description
(Rs.)

1 Earthwork and Allied Activities 23,592,628

2 Subbase and Base 104,767,907

3 Surface Courses & Pavement 40,967,548

4.1 Structures (Ravi Bridge) 795,824,215

4.1a Structures (Widening of Existing Bridge at Niazi Interchange) 152,749,978

4.2 Structures (Drain/ NJB ) 31,367,208

5 Drainage & Erosion Works 14,331,445

6 Ancillary Works 29,576,658

7 General Items 10,700,000

8 Electrical Works 21,652,619

Sub Total Cost = 1,225,530,204


Add 4.16% Premium for Mega Project on Sub Total Cost
- 50,536,936
Excluding Bill No. 7
Total Construction Cost = 1,276,067,140

- Traffic Maintenance, Temporary Diversion, Safety Works (etc.) 1,000,000

- Shifting of Utilities (P.S) 5,000,000

- Landscaping and Horticulture work @ 1% of Total Cost 12,760,671

- Contingencies @ 3% of Total Cost 37,961,014

- Consultancy Charges for Design Services @ 1.84% of Total Cost 23,282,755


Consultancy Charges for Construction Supervision @ 2% of Total on Man
- 25,307,343
Month basis
Land Acquisition and Structure Compensation 2.67 Kanal @ 11.4 Million /
- 40,004,000
Kanal (P.S)
Prevision on account of compensation of Toll Collection during traffic
- 20,000,000
diversion Period
Total Project Cost = 1,441,382,924

Rs. In Million 1441.383


CONSTRUCTION OF ADDITIONAL BRIDGE OVER RIVER RAVI

ENGINEER'S ESTIMATE

Bill No. 1 Earthwork and Allied Activities

Rate Amount
Item No Item Description Unit Quantity
(Rs) (Rs)

101 Clearing & Grubbing SM 6,080.00 0.00 -

104 Compaction of Natural Ground SM 6,080.00 10.55 64,144

Excavate Unsuitable/Surplus Common Material and


106a CM 68,070.00 216.39 14,729,667
removal upto 3 Km Lead.

107di Granular Backfill with Sand CM 2,750.00 487.30 1,340,075

Formation of embankment from Borrow Excavation in


108c CM 21,780.00 330.78 7,204,388
Common Material

109a Subgrade Preparation in Earth Cut SM 4,810.00 52.88 254,353

Total of Bill No. 1 23,592,628


CONSTRUCTION OF ADDITIONAL BRIDGE OVER RIVER RAVI

ENGINEER'S ESTIMATE

Bill No. 2 Subbase and Base

Rate Amount
Item No Item Description Unit Quantity
(Rs) (Rs)

201 Granular Subbase CM 2,197.00 3,005.84 6,603,830

Reuse of broken pavement material from existing road as


201a CM 2,619.00 883.45 2,313,756
Sub base

203a Asphaltic Base Course Plant Mix (Class B) CM 4,680.00 12,617.97 59,052,100

Water Bound Macadam Base with Coarse Aggregate Class


206 CM 8,220.00 3,867.17 31,788,137
B

207a Deep Patching ( 0 - 15 cm ) SM 100.00 64.47 6,447

207b Deep Patching (15 - 30 cm ) SM 100.00 43.06 4,306

209a Breaking of Existing Road Pavement Structure CM 6,410.00 547.75 3,511,078

209b Scarification of Existing Road Pavement SM 100.00 26.05 2,605

Disposal of Existing Unusable Road Pavement Structure


209c CM 3,201.00 124.07 397,148
(Asphalt)

- Cold Milling SM 13,340.00 75.00 1,000,500

- Cutting of Asphalt with Saw LM 880.00 100.00 88,000

Total of Bill No. 2 104,767,907


CONSTRUCTION OF ADDITIONAL BRIDGE OVER RIVER RAVI

ENGINEER'S ESTIMATE

Bill No. 3 Surface Courses & Pavement

Rate Amount
Item No Item Description Unit Quantity
(Rs) (Rs)

302 Bituminous Prime Coat SM 30,690.00 71.90 2,206,611

303 Bituminous Tack Coat SM 72,060.00 46.55 3,354,393

305 Asphaltic Wearing Course Plant Mix (Class A) CM 2,650.00 13,360.96 35,406,544

Total of Bill No. 3 40,967,548


CONSTRUCTION OF ADDITIONAL BRIDGE OVER RIVER RAVI

ENGINEER'S ESTIMATE

Bill No.4.1 Structure (Ravi Bridge)

Rate Amount
Item No Item Description Unit Quantity
(Rs) (Rs)

401 b (ii) Concrete Class A2 (4000 psi) Transom and Wing Wall CM 656.00 15,447.20 10,133,363

401 b (ii) Concrete Class A2(4000 psi) Diaphragms and Deck slab CM 2,739.00 15,447.20 42,309,881

401 a(i) Concrete Class A1 (3000 psi) Approach Slab CM 50.00 10,935.07 546,754

401 b(ii) Concrete Class A2( 4000 psi) Piers CM 690.00 15,447.20 10,658,568

401 a(i) Concrete Class A1(3000psi) N.J.Barrier CM 247.00 10,935.07 2,700,962

401 b(ii) Concrete Class A2 (4000 psi) Abutment Girder Seat CM 151.00 15,447.20 2,332,527

401 b(ii) Concrete Bearing Pads, Concrete Class A2 CM 11.00 12,183.99 134,024

Concrete Class D1 (5000 psi) Prestressed 'I' Shaped


401d CM 3,874.00 16,025.39 62,082,361
girder

Prestressing Steel (Pre-cast prestressed girder) grade 270


405 a CM 310.00 322,911.00 100,102,410
ksi

405 b Launching of Precast- Prestressed Girders CM 4,650.00 1,561.30 7,260,045

401 f Lean Concrete CM 19.00 7,703.65 146,369


Reinforcement as per AASHTO M-31 Grade-60 for Pile
404 b Ton 1,541.00 120,887.18 186,287,145
Cages.
Reinforcement as per AASHTO M-31 Grade-60 other than
- Ton 1,309.00 104,350.00 136,594,150
pile cages.
Elastomeric Bearing Pads of Specified Size and Requisite Centimeter
406c 4,384,800.00 7.00 30,693,600
standard (European Equivalent) Cube

406 d Free/ Fixed End Steel Support KG 5,040.00 261.00 1,315,440

Construction of Cast inplace Concrete Piles 1500 mm dia


407 k Including Concrete Class A3 (4000 psi) Excluding Steel LM 4,355.00 37,825.57 164,730,343
Reinforcement

407 m Pile Load Test (upto 2.5 times the design load) Each 1.00 780,000 780,000

407 n Pile Proof Load Test (upto 1.5 times the design load) Each 2.00 540,000 1,080,000

407 p MS Steel Linner for Piles 1500mm dia 10mm thick LM 347.00 48,398 16,794,106

SP 416 Providing and fixing CI Pipes100mm dia LM 1,972.00 1,131.31 2,230,943

SP 418 a Galvanized Iron Drain pipe, 100mm dia LM 138.00 2,468.45 340,646

SP 419b Provide and Fixing Steel Hand Railng LM 493.00 4,749.65 2,341,577

Steel Expension Joint Small Movement (Euporean


SP-423 L.M 255.00 55,800.00 14,229,000
Equivalent) Movement upto 25mm

TOTAL OF BILL No. 4.1 795,824,215


CONSTRUCTION OF ADDITIONAL BRIDGE OVER RIVER RAVI

ENGINEER'S ESTIMATE
Bill No.4.1a Structure (Widening of Existing Bridge at Niazi Interchange)
Rate Amount
Item No Item Description Unit Quantity
(Rs) (Rs)
Excavate Unsuitable/Surplus Common Material and
106 a CM 4,200.00 216.39 908,838
removal upto 3 Km Lead.
107 a Structural excavation in common material CM 7,000.00 216.50 1,515,500

107 e Common backfill CM 500.00 103.70 51,850

107di Granular Backfill with Sand CM 7,700.00 487.30 3,752,210

401 b(ii) Deck Slab and Diaphragms, Concrete Class A2 CM 420.00 15,447.20 6,487,824

401 a(i) Approach Slab, Concrete Class A1 CM 90.00 10,935.07 984,156

401 a(ii) Transom Pier Cap, Concrete Class A1 CM 110.00 14,198.64 1,561,850

401 a(ii) Piers, Concrete Class A1 CM 37.00 14,198.64 525,350

401 a(ii) N.J.Barrier, Concrete Class A1 CM 62.00 14,198.64 880,316

401 a(ii) Girder Seat on Abutment, Concrete Class A1 CM 415.00 14,198.64 5,892,436

401 a(ii) Concrete Pads, Concrete Class A1 CM 2.05 14,198.64 29,107

401 a(ii) Pile Cap, Concrete Class A1 CM 184.00 14,198.64 2,612,550

401d Prestressed Girders, Concrete Class D1 CM 556.00 16,025.39 8,910,117

401 f Lean Concrete CM 53.00 7,703.65 408,293


Reinforcement as per AASHTO M-31 Grade-60 for Pile
404 b TON 99.00 120,887.18 11,967,831
Cages.
Reinforcement as per AASHTO M-31 Grade-60 other than
- TON 321.00 104,350.00 33,496,350
pile cages.
Prestressing Steel (Pre-cast prestressed girder) grade 270
405 a TON 27.00 322,911.00 8,718,597
ksi
405 b Launching of Prestressed Girders (32.68 m length) CM 351.00 1,561.30 548,016

- Launching of Prestressed Girders (21.25 m length) CM 205.00 891.00 182,655

Steel Expension Joint Small Movement (Euporean


SP-423 L.M 99.00 55,800.00 5,524,200
Equivalent) Movement upto 25mm
Elastomeric Bearing Pads of Specified Size and Requisite Centimeter
406c 406,000.00 7.00 2,842,000
standard (European Equivalent) Cube

406 d Free End Steel Support KG 1,710.00 261.00 446,310

406 e Fixed End Steel Support KG 1,470.00 261.00 383,670


Cast In place Concrete Piles 1000 mm dia.in Normal soil,
407 a LM 600.00 19,857.07 11,914,241
Concrete Class A3
407 b Pile Load Test (up to 2.5 times the design load) Each 1.00 408,000.00 408,000

407 c Proof Load Test (up to 1.5 times the design load) Each 1.00 336,000.00 336,000

SP 416 Providing and fixing CI Pipes100mm dia LM 100.00 1,131.31 113,131

SP-616a 100 mm dia class "B" PVC Pipe LM 132.00 379.60 50,107

SP 418 a Galvanized Iron Drain pipe, 100mm dia LM 9.15 2,468.45 22,577
CONSTRUCTION OF ADDITIONAL BRIDGE OVER RIVER RAVI

ENGINEER'S ESTIMATE

Bill No.4.1a Structure (Widening of Existing Bridge at Niazi Interchange)

Rate Amount
Item No Item Description Unit Quantity
(Rs) (Rs)

Formation of Embankment with Specified material for


Reinforced earth works completed as per particular
SP 417 a CM 6,130.00 1,588.22 9,735,789
specifications complying only to section 417.4.9.1.
(Synthetic or Dunois-Coated Metallic Systems).

509 a Grouted Riprap Class A CM 500.00 4,578.90 2,289,450

Coarse Aggregate under Beam Seat over Reinforced Earth


202 CM 370.00 3,372.53 1,247,836
Abutment as per specifications.
Screed over Reinforced Earth Abutment, Concrete Class
401 h SM 52.00 10,935.07 568,624
A1
Concrete Leveling Pad of Reinforced Earth Abutment &
401 a(i) CM 19.00 10,935.07 207,766
Wall, Concrete Class A1.

Construction of Reinforced Earth concrete abutment using


panels with Concrete Class D1 & Grade 60 Steel
SP 417 b Reinforcement including supply & installation of the
Reinforced Earth materials like Moulds and Liners (on
loan), Soil Reinforcement Strip, Strip to Pa

A Abutment Wall (Bridge Load-Bearing) Height 0-5 SM 106.00 23,575.00 2,498,950

B Abutment Wall (Bridge Load-Bearing) Height 5-7 SM 569.00 24,725.00 14,068,525

C Abutment Wall (Bridge Load-Bearing) Height 7-11 SM 380.00 26,450.00 10,051,000

SP 419b Provide and Fixing Steel Hand Railng LM 128.00 4,749.65 607,955

TOTAL OF BILL No. 4.1a 152,749,978


CONSTRUCTION OF ADDITIONAL BRIDGE OVER RIVER RAVI

ENGINEER'S ESTIMATE
Bill No.4.2 Structure (Drain / NJB)

Rate Amount
Item No Item Description Unit Quantity
(Rs) (Rs)

107a Structural Excavation in Common Material CM 690.00 216.50 149,385

107di Granular Backfill with sand CM 70.00 487.30 34,111

401b(i) Concrete Class A-2(on Ground) CM 270.00 12,183.99 3,289,677

401b(ii) Concrete Class A2(Elevated) CM 980.00 15,447.20 15,138,256

401b(i) Concrete Class A2 for NJB With Slipform Paver CM 410.00 12,183.99 4,995,436

401f Lean Concrete CM 150.00 7,703.65 1,155,548

404b Reinforcement As per AASHTO M-31 Grade -60 Ton 40.80 104,350.00 4,257,480

Expansion Joint Including Sealant/Filler other than Bridge


406a L.M 60.00 199.89 11,993
joints

410a Brick Masnory CM 170.00 7,196.95 1,223,482

413c Galvanised Mild Steel Grating S.M 80.00 13,898.00 1,111,840

Total of Bill No. 4.2 31,367,208


CONSTRUCTION OF ADDITIONAL BRIDGE OVER RIVER RAVI

ENGINEER'S ESTIMATE
Bill No 5 Drainage & Erosion Works

Rate Amount
Item No Item Description Unit Quantity
(Rs) (Rs)

510a Dismantling and disposal of RCC Structure CM 2,100.00 3,692.50 7,754,250

510b Dismantling and disposal of PCC Structure CM 110.00 2,256.50 248,215

510c Dismantling and disposal of Brick Masonry CM 540.00 871.85 470,799

509a Rip Rap Class "A" CM 1,160.00 2,444.92 2,836,107

509d Grouted Riprap Class "A" CM 660.00 4,578.90 3,022,074

Total of Bill No. 5 14,331,445


CONSTRUCTION OF ADDITIONAL BRIDGE OVER RIVER RAVI

ENGINEER'S ESTIMATE

Bill No.6 Ancillary Works

Rate Amount
Item No Item Description Unit Quantity
(Rs) (Rs)

401a(i) Concrete Class "A1" in haunches around PVC pipes CM 20.00 10,935.07 218,701

601a Pre-Cast Curb (Non-Mountable) LM 2,530.00 1,134.25 2,869,653

601b Pre-Cast Concrete Edge Curb LM 1,430.00 581.26 831,202

607a Traffic Signs, Triangular sides 900 mm with Post Each 5.00 10,830.74 54,154

607b Traffic Signs, Circular dia 900 mm with Post Each 5.00 13,361.33 66,807

607c(i) Traffic Signs, with single post assembly SM 25.00 16,995.67 424,892

607c(ii) Traffic Signs, with double post assembly SM 25.00 20,552.73 513,818

Pavement marking in Thermoplastic paint for lines of 15cm


608a M 10,060.00 105.26 1,058,916
wide

Pavement marking with Thermoplastic paint for Arrows,


608b SM 110.00 701.73 77,190
stops, pedestrian crossing, hatch area etc. as specified

609c Reflectorized pavement Studs (raised Profile Type - Single) Each 2,390.00 395.94 946,297

SP-619 Providing and Fixing of MBS Fencing L.M 880.00 14,641.89 12,884,863

607d Manufacture & Installation of Gantry Sign Type-I Each 2.00 1,531,948 3,063,896

607f Manufacture & Installation of Gantry Sign Type-IV Each 2.00 561,549 1,123,098

SP-614(i) Paving Tiles on Drain slabs SM 2,420.00 980.11 2,371,867

SP-614(ii) Paving Tiles on Compacted Soil SM 1,760.00 1,192.22 2,098,314

SP 617(i) Dismantling and removal of walkways M 1,760.00 132.84 233,798

Dismantling ,removal and stockpiling of kerb stones of


SP 617(ii) M 880.00 64.47 56,734
walkways
Dismantling ,removal and stockpiling of paving tiles of
SP 617(iii) SM 880.00 65.08 57,270
walkways

SP 618(i) Reuse of Kerb stone after removal i/c painting M 100.00 404.26 40,426

SP 618(ii) Reuse of Paving Ttiles after removal SM 100.00 127.63 12,763

- Removal of Existing Steel Railing L.M 1,430.00 400.00 572,000

Total of Bill No. 6 29,576,658


CONSTRUCTION OF ADDITIONAL BRIDGE OVER RIVER RAVI

ENGINEER'S ESTIMATE
Bill No. 7 General Items

Rate Amount
Item No Item Description Unit Quantity
(Rs) (Rs)

701a Provide Survey and Allied Instruments PS - - 750,000

701b Maintain Survey Instruments (including Helpers) Month 10 60,000 600,000

702a Provide Engineer's & Client's Office & at Site PS - - 450,000

702b Furnish & Equip Engineer's & Client's Office PS - - 300,000

702c Operational Cost of Engineer's & Client's Offices Month 10 175,000 1,750,000

703a Provide Material Testing Laboratory PS - - 600,000

703b Operational Cost of Project Laboratory (including Helpers) Month 10 125,000 1,250,000

SP-708 Running and maintence of Vehicles (4 Nos) Month 10 320,000 3,200,000

SP- Office Facilities for Police and Service Department PS - - 1,800,000

Total of Bill No 7 10,700,000


CONSTRUCTION OF ADDITIONAL BRIDGE OVER RIVER RAVI

ENGINEER'S ESTIMATE
Bill No.8 Electrical Works

Rate Amount
Item No Item Description Unit Quantity
(Rs) (Rs)
Supply, installation, testing and commissioning of the
following items of work, including all material, labour, tools
and accessories etc. required for proper completion of each
item as per specification, drawings and/or as directed by
the Engineer.
801(a) 10 m high single arm conical octagonal (hot dip) galvanized Each 99 65,100 6,444,900
steel pole with extension arm luminaire arrangement, base
plate, J-rag bolts and earthing etc. as shown on drawing.

801(b) Road Lighting Pole Foundation Each 99 13,421 1,328,679

802 Road Lighting LED Luminaries 120W make Philips, GE or No. 99 50,975 5,046,525
equivalent suitable for M-2 & M-3 roads of wattage suitable
for the project requirements, fully IP 66 with corrosion
resistant die cast aluminum housing, silicon gas kit,
thermally hardened glass complete with LED drivers, surge
protection and all accessories/ components required for the
proper operation of the system. The luminaries shall be fully
flexible for future upgrades and easy replacements for
maintenance purposes. Contractor to submit lighting design
calculation to determine the adequacy of the wattage and
should adjust the number of LEDs/wattage as per project
lighting requirements.

803(a) PVC pipe/conduit Class-D 100 mm dia with accessories Rm 300 1,158.00 347,400
suitable for laying multi-core cables on road crossings.
803(b) PVC pipe/conduit Class-B 100 mm dia with accessories Rm 3,200 732.00 2,342,400
suitable for laying multi-core cables in new Jersey barriers.
804(a) 4-core 16 mm2 PVC insulated and PVC overall sheathed Rm 3,600 887.95 3,196,620
600/1000 Volt grade unarmoured copper cable (Newage,
Pioneer, Fast or Pakistan Cables) laid direct in ground or
pulled in PVC pipe already laid.

804(b) Single core 16 mm2 PVC insulated 450/750 Volt grade Rm 3,600 254.35 915,660
unarmoured copper cable (Newage, Pioneer, Fast or
Pakistan Cables) laid direct in ground or pulled in PVC pipe
already laid as CPC.

804© 4 Core 25mm2 Cu. PVC/PVC 600/1000V Unarmored Cable Rm 100 1,653.15 165,315
(Imported copper shall be used. Verified documentary
evidence for source of copper & PVC shall be furnished
prior to manufacturing)
CONSTRUCTION OF ADDITIONAL BRIDGE OVER RIVER RAVI

ENGINEER'S ESTIMATE

Bill No.8 Electrical Works

Rate Amount
Item No Item Description Unit Quantity
(Rs) (Rs)
804(d) 3-core 2.5 mm2 PVC insulated and PVC overall sheathed Rm 3,897 166.80 649,960
450/750 Volt grade copper cable (stranded conductor)
(Imported copper shall be used. Verified documentary
evidence for source of copper & PVC shall be furnished
prior to manufacturing) from junction box to the fitting
through the hollow of pole.

805 Road lighting control panel with angle iron frame claded 14 Job 2 260,000 520,000
SWG, sheet steel enclosure having high quality powder
coated paint, color RAL 7032. The LCP shall be complete
with incoming and outgoing MCCBs, Cu busbars, magnetic
contactors, photo-electric switches, meters, indication
lights, construction with IP 54 protection class, door, locking
arrangement etc. and all other accessories as required for
quality work
807(a) 25 mm2 PVC insulated copper earth wires including all Rm 40 457 18,280
fixing accessories as required for earthing of lighting control
panels.
807(b) Earth point comprising of 10 ft. 5/8" dia. (16 mm dia) copper Each 4 6,720 26,880
coated M.S. rods driven in ground near each lighting
control panel. The earthing rods shall be completed with
fixing clamps etc.
807 Supply of 25 kVA, 11/0.415 kV pole mounted transformer, Job 2 325,000 650,000
As per earthing arrangement and all accessories, Installation and
WAPDA Connection Charges with energy meter as per WAPDA
Specs. standards and practice.

Total of Bill No. 8 21,652,619

Note:
The cost of security deposit and obtaining of 11 kV electrical connection with
installation material from WAPDA shall be finalized as per site requirement and
the cost for the same is not included in the above.
CONSTRUCTION OF NEW BRIDGE ALONG EXISTING RAVI BRIDGE (PHASE-II)

ENGINEER'S ESTIMATE

SUMMARY

Amount
Bill No Description
(Rs.)

1 Earthwork and Allied Activities 30,693,835

2 Subbase and Base 91,418,517

3 Surface Courses & Pavement 40,353,730

4.1 Structures (Ravi Bridge) 695,182,305

4.1a Structures (Widening of Existing Bridge at Niazi Interchange) 143,607,194

4.2 Structures (Drain/ NJB ) 30,390,821

5 Drainage & Erosion Works 8,690,235

6 Ancillary Works 30,252,042

7 General Items 10,700,000

8 Electrical Works 22,441,444

Sub Total Cost = 1,103,730,125

Add 4.16% Premium for Mega Project on Sub Total Cost


- 45,470,053
Excluding Bill No. 7

Total Construction Cost = 1,149,200,178

- Traffic Maintenance, Temporary Diversion, Safety Works (etc.) 1,000,000

- Shifting of Utilities (P.S) 5,000,000

- Landscaping and Horticulture work @ 1% of Total Cost 11,492,002

- Contingencies @ 3% of Total Cost 34,155,005

- Consultancy Charges for Design Services @ 1.84% of Total Cost 20,948,403

Consultancy Charges for Construction Supervision @ 2% of Total on Man


- 22,770,004
Month basis

Land Acquisition and Structure Compensation 2.67 Kanal @ 10 Million /


- 26,700,000
Kanal (P.S)

Total Project Cost = 1,271,265,592


CONSTRUCTION OF NEW BRIDGE ALONG EXISTING RAVI BRIDGE (PHASE-II)

ENGINEER'S ESTIMATE
Bill No.8 Electrical Works

Rate Amount
Item No Item Description Unit Quantity
(Rs) (Rs)
Supply, installation, testing and commissioning of the
following items of work, including all material, labour, tools
and accessories etc. required for proper completion of each
item as per specification, drawings and/or as directed by
the Engineer.

801(a) 10 m high single arm conical octagonal (hot dip) galvanized Each 99 65,100 6,444,900
steel pole with extension arm luminaire arrangement, base
plate, J-rag bolts and earthing etc. as shown on drawing.

801(b) Road Lighting Pole Foundation Each 99 13,421 1,328,679

802 Road Lighting LED Luminaries 120W make Philips, GE or No. 99 50,975 5,046,525
equivalent suitable for M-2 & M-3 roads of wattage suitable
for the project requirements, fully IP 66 with corrosion
resistant die cast aluminum housing, silicon gas kit,
thermally hardened glass complete with LED drivers, surge
protection and all accessories/ components required for the
proper operation of the system. The luminaries shall be fully
flexible for future upgrades and easy replacements for
maintenance purposes. Contractor to submit lighting design
calculation to determine the adequacy of the wattage and
should adjust the number of LEDs/wattage as per project
lighting requirements.

803(a) PVC pipe/conduit Class-D 100 mm dia with accessories Rm 300 1,158 347,400
suitable for laying multi-core cables on road crossings.

803(b) PVC pipe/conduit Class-B 100 mm dia with accessories Rm 3,200 732 2,342,400
suitable for laying multi-core cables in new Jersey barriers.

804(a) 4-core 16 mm2 PVC insulated and PVC overall sheathed Rm 3,600 1,164 4,190,400
600/1000 Volt grade unarmoured copper cable (Newage,
Pioneer, Fast or Pakistan Cables) laid direct in ground or
pulled in PVC pipe already laid.

804(b) Single core 16 mm2 PVC insulated 450/750 Volt grade Rm 3,600 293 1,054,800
unarmoured copper cable (Newage, Pioneer, Fast or
Pakistan Cables) laid direct in ground or pulled in PVC pipe
already laid as CPC.

804© 4 Core 25mm2 Cu. PVC/PVC 600/1000V Unarmored Cable Rm 100 1,920 192,000
(Imported copper shall be used. Verified documentary
evidence for source of copper & PVC shall be furnished
prior to manufacturing)
CONSTRUCTION OF NEW BRIDGE ALONG EXISTING RAVI BRIDGE (PHASE-II)

ENGINEER'S ESTIMATE

Bill No.8 Electrical Works

Rate Amount
Item No Item Description Unit Quantity
(Rs) (Rs)
804(d) 3-core 2.5 mm2 PVC insulated and PVC overall sheathed No. 99 2,820 279,180
450/750 Volt grade copper cable (stranded conductor)
(Imported copper shall be used. Verified documentary
evidence for source of copper & PVC shall be furnished
prior to manufacturing) from junction box to the fitting
through the hollow of pole.
805 Road lighting control panel with angle iron frame claded 14 Job 2 260,000 520,000
SWG, sheet steel enclosure having high quality powder
coated paint, color RAL 7032. The LCP shall be complete
with incoming and outgoing MCCBs, Cu busbars, magnetic
contactors, photo-electric switches, meters, indication
lights, construction with IP 54 protection class, door, locking
arrangement etc. and all other accessories as required for
quality work

807(a) 25 mm2 PVC insulated copper earth wires including all Rm 40 457 18,280
fixing accessories as required for earthing of lighting control
panels.

807(b) Earth point comprising of 10 ft. 5/8" dia. (16 mm dia) copper Each 4 6,720 26,880
coated M.S. rods driven in ground near each lighting
control panel. The earthing rods shall be completed with
fixing clamps etc.

807 Supply of 25 kVA, 11/0.415 kV pole mounted transformer, Job 2 325,000 650,000
As per earthing arrangement and all accessories, Installation and
WAPDA Connection Charges with energy meter as per WAPDA
Specs. standards and practice.

Total of Bill No. 8 22,441,444

Note:
The cost of security deposit and obtaining of 11 kV electrical connection with
installation material from WAPDA shall be finalized as per site requirement and
the cost for the same is not included in the above.

Potrebbero piacerti anche