Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
• Parabolic trough (PT) and linear Fresnel systems typically apply certain
modular length patterns to one particular loop, which then would be
applied in serial/parallel arrangements. Most PT plants today require
about 40 × 300 m for one single loop, with 100+ loops for a simple
50 MWe plant in Spain, while a linear Fresnel loop could require a
straight 25 × 1000 m for one loop, with 22+ loops for a simple 50 MWe
plant in Spain. New developments on PT aim at larger aperture width.
• Solar tower plants are preferably built on circular or semi-circular
shaped footprints, but also rectangular fields are feasible.
• Additional space for service roads surrounding the solar field, fencing,
possible wind-breaking measures (earth banks, walls or vegetation)
should be considered at the boundary of the plant.
• Depending on the outcome of the environmental impact assessments,
specific requirements could be imposed on a plant, which require addi-
tional efforts.
With these patterns, one can see how a plant layout could fit into a given
land plot and its usually non-technical provided borders. However, with a
preselected technology the requirements for a solar project site can be more
specifically defined.
Ownership structures
The legal situation of the required property is also a crucial selection crite-
rion. When approaching the legal side of ownership structures the following
questions should be considered: Is the land public or private? Will it be a
direct purchase or a purchase option or a lease option? How secure is the
land for the project throughout a possibly lengthy development process?
Also depending on the type of financing, the required legal certainty on the
complete property becomes a crucial matter, as agreements with all owners
have to be completed and the surface rights for the installation of the CSP
system should be recorded in the title of the land.
Electricity grid
The generated power must be evacuated from the plant; therefore it needs
to tie into a high voltage (HV) electricity line with sufficient voltage level.
Projects of more than 20 MW capacity usually have to look for lines of
60–400 kV, depending on the applicable grid code and network voltage levels.
Road network
The connection to the road network serves two purposes. During construc-
tion of the plant, all materials have to be transported to the project site by
trucks. As this includes heavy equipment, the route for heavy hauling (e.g.
the capacity of road bridges from ports of landing for overseas shipments)
has to be considered. Some improvements required specifically for con-
struction transport can be on a temporary basis.
For operation of the plant, access roads should be erected as permanent
structures. They should suffice for all regular trucking of materials and
during maintenance periods. It should be considered that, during the 20–40
year operation period, major overhauls of steam turbines and generators
would be made, in addition to possible future improvements to the instal-
lation. It will be a strategic decision between actual needs and benefits for
further requirements. The cost and authorization effort for this road will
also depend on the distance to the existing public road network.
Fuel availability
For most CSP plants, some small degree of supplemental fossil fuel firing
is considered. Fuel availability and specific cost for transporting it to the
project should be considered. For larger fossil fuel shares, such as an ISCC
(integrated solar combined cycle) system, the fuel sourcing becomes a much
more significant aspect for the feasibility of the project. It may mandate, as