Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
Process Overview
The Desalter is the second part of a two stage desalting process. Feed to
the desalting process has already had some of the H2S and sour water
removed. The water and oil mixture is piped into the Desalter vessel
through inlet distributor system to pass it through the electrostatic
field. This case study focuses on the use of a thermal spray lining for
corrosion protection of the desalter to produce a dehydrated, desalted
crude oil.
Value Proposition
IGS’ ability to protect the vessel shell and limit production losses was a key driver for the client. The use of the IGS 5620
Metalspray™ HVTS process was deemed more economical when compared to weld metal overlay due to time
sensitivity. The cost of the weld metal overlay would have been approximately $12MM more that the cost of the IGS
5620 Metalspray™, thus saving the plant a considerable amount of money on the installed corrosion resistant material
installation. Costs savings of approximately $10MM will be realized over a four-year period versus organic lining due
to reduced outage time related to repairs, inspection and turnaround time savings of repeated re-application/repair of
the previous organic system. (This calculation is derived from the expected duration of the repair/replacement of the
organic system at the inspection intervals and further maintenance due to recurring corrosion). As similar scope was
performed on three other vessels in the turnaround, the use of this maintenance approach shaved 3 days off the critical
path schedule with a saving of $75MM.
www.integratedglobal.com