Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
CONTENTS
1. INTRODUCTION ....................................................................................... 4
2. SUB-BASE ................................................................................................ 4
2.1. Preparation ................................................................................................... 4
2.2. The plate bearing test ................................................................................. 5
3. CONCRETE COMPONENTS.................................................................... 7
3.1. Cement .......................................................................................................... 7
3.2. Aggregates.................................................................................................... 7
3.3. Water ............................................................................................................. 7
3.4. Workability .................................................................................................... 7
3.5. Admixtures .................................................................................................... 7
4. CONCRETE .............................................................................................. 8
4.1. Concrete composition ................................................................................. 8
4.2. Notes.............................................................................................................. 8
5. REINFORCEMENT ................................................................................... 9
5.1. Dramix® steel fibres ..................................................................................... 9
5.2. Auxiliary reinforcement ............................................................................... 9
6. JOINTS .................................................................................................... 10
6.1. Expansion and working joints .................................................................. 10
6.2. Isolation joints............................................................................................. 10
7. DESIGN ................................................................................................... 11
8. CONSTRUCTION.................................................................................... 12
8.1. Preparations ............................................................................................... 12
8.2. Pouring and finishing................................................................................. 12
8.3. Post-treatment............................................................................................ 13
8.4. Initial usage................................................................................................. 13
9. CHECKS.................................................................................................. 14
9.1. Self assessment by the flooring contractor............................................ 14
9.2. Checks made by control organisation .................................................... 15
3
WORKING DOCUMENT FOR THE FLOORING CONTRACTOR
Jointless Industrial Floor
1. INTRODUCTION
The aim of this specification is to arrive at an industrial floor using a defined
description of the materials used (concrete, Dramix®, topping …), method of
calculation, placement and finishing method, whereby the final product has a
constant high quality.
2. SUB-BASE
2.1. Preparation
It is assumed that …
If there are fixed points under the floor, adequate solutions have to be found
to avoid the slab cracking under load over the hard point.
4
WORKING DOCUMENT FOR THE FLOORING CONTRACTOR
Jointless Industrial Floor
Granular sub-base.
General
The plate-bearing test is carried out on the finished sub-base and not on
the sub-grade.
The results of these plate-bearing tests are interpreted by N.V. BEKAERT S.A.
or a consultant appointed by BEKAERT.
5
WORKING DOCUMENT FOR THE FLOORING CONTRACTOR
Jointless Industrial Floor
Number
For floor areas less than 3,000 m² 1 plate-bearing test per 500 m² with a
minimum of 3 plate tests.
For floor areas greater than 3,000 m² 6 plate-bearing tests + one plate-
bearing test for each area unit of 1,000 m² over 3,000 m² (e.g. 7,500 m²
Î 6 + (7000 - 3000)/1000 = 10 plate tests).
If significant differences are found in the quality of the sub-base the total floor
area is notionally subdivided into smaller partial areas for which a uniform
sub-base quality is found. For the determination of the number of plate-
bearing tests the above rules are then applied to the partial areas.
The mean value of the test results must be greater than or equal to the
k-value, which is used in the calculation of the (partial) area concerned.
6
WORKING DOCUMENT FOR THE FLOORING CONTRACTOR
Jointless Industrial Floor
3. CONCRETE COMPONENTS
3.1. Cement
The permissible cement types are: CEM III A/42.5 (HK 40). The cement
must conform to BS 12.
3.2. Aggregates
3.3. Water
3.4. Workability
3.5. Admixtures
7
WORKING DOCUMENT FOR THE FLOORING CONTRACTOR
Jointless Industrial Floor
4. CONCRETE
The amount of cement varies between 300 and 340 kg/m³. The choice of
the amount of cement, between these margins, is a function of the
temperature, air humidity etc. during construction.
In principle the cement amount has to be reduced at higher temperatures.
In principle the cement amount has to be reduced by lower air humidity.
The choice of the effective amount of cement, within the margins stated
above, is to be made by the flooring contractor.
The gravel is composed of 2 grades. The grades are in conformity with
the BS 882.
Coarse aggregates or Crushed stone
50% 4/14 40% 2/7
50% 4/28 60% 7/20.
If these grades are not present locally, use can be made of the grades
which are closest to the values above.
4.2. Notes
8
WORKING DOCUMENT FOR THE FLOORING CONTRACTOR
Jointless Industrial Floor
The concrete for a given pour shall be supplied, where possible, from a
single concrete supplier.
Where not possible, special attention should ensure that if two plants are
used: the cement is of the same type and from the same supplier;
the same admixtures are used at the same dosages;
the distances of the two plants from the jobsite are approximately
the same;
where possible, the concrete of the two plants should not be mixed.
5. REINFORCEMENT
5.1. Dramix® steel fibres
The Dramix® steel fibres can be added either at the concrete plant or at the
site.
At the plant: The fibres should be mixed together with the aggregates in
the pan mixer. In this case an excellent distribution is ensured as soon as
all collated fibres have dispersed. If the concrete is made directly in the
truckmixer the fibres should be added as described below.
At the site: BEFORE or during the addition of the fibres the concrete is
brought to the correct consistency. The fibres are added to the concrete
mixer evenly at a rate of 60 kg/min. while the concrete mixer drum is
turning at full mixing speed. After the addition of all the fibres mixing is
continued at full speed for five minutes (or 100 revolutions at full speed).
The correct dosing and addition of the Dramix® steel fibres is the
responsibility of the flooring contractor.
9
WORKING DOCUMENT FOR THE FLOORING CONTRACTOR
Jointless Industrial Floor
The flooring contractor is to indicate the location of the auxiliary
reinforcement on the Engineer's drawing.
6. JOINTS
Only isolation and expansion joints are made in the floor. There are NO
shrinkage joints cut.
The length/width ratio of the floor sections must be less than 3:2 and should
be as nearly square as possible.
The aim of an isolation joint is to make the slab independent of and free from
restraint by the rest of the construction.
Free movement of the slab must be possible.
10
WORKING DOCUMENT FOR THE FLOORING CONTRACTOR
Jointless Industrial Floor
7. DESIGN
The concrete floor is poured onto a stabilised sand and gravel sub-base: a
complete adhesion between the concrete floor and its sub-grade is aimed at.
Shrinkage movement is obstructed and hindered and may give rise to
formation of micro scopie shrinkage cracks distributed uniformly over the
floor surface.
The loading plan is given by the contract principal. The floor is designed
on the basis of these loading and ground investigation data.
11
WORKING DOCUMENT FOR THE FLOORING CONTRACTOR
Jointless Industrial Floor
8. CONSTRUCTION
8.1. Preparations
The connection of the slab to the loading dock must be carried out as
given in the annex.
NO plastic sheeting is spread over the sub-base. Before pouring the floor
the sub-base is wetted at the rate of 10 l/m². This wetting is repeated
continuously depending on the site requirements.
This curing compound protects the concrete against drying out between
pouring and finishing of the floor. Cracks due to plastic shrinkage are
hereby limited.
12
WORKING DOCUMENT FOR THE FLOORING CONTRACTOR
Jointless Industrial Floor
The time between the mixing of the concrete and working on site is a
maximum of 100 min. in conformity with BS 5328.
A topping must be laid on the stiffening concrete at the rate of 3.6 kg/m².
The cement class of the cement for the topping must be the same as that
used in the concrete.
8.3. Post-treatment
Directly after the drying of the curing compound, the floor is placed
under water and covered with a plastic sheet. This plastic film must
remain on the floor for a minimum of 14 days, so that the floor
hardens at 100 % humidity during this time.
In loading the floor the evolution of compressive strength of the concrete has
to be taken into account (conform to BS 1881).
Due to the high joint spacing, the values of the BS 1881 need to be reduced
by 20 %.
13
WORKING DOCUMENT FOR THE FLOORING CONTRACTOR
Jointless Industrial Floor
9. CHECKS
For each site the necessary plate loading tests are carried out as described
in par. 2. The results are entered on pre-printed proformas.
15
®
Dramix
Drawings
These floor plans were developed by a collaboration
between AIB-VINÇOTTE Inter (A.V.I.), international control
consultants, and the BEKAERT company, producer of the
Dramix® steel fibres.
PLAN
LEGEND
Compressible material
thickness 10 mm
Auxiliary reinforcement
5 x ¤ 12 mm – Length: 1.5 m.
CROSS SECTION
Auxiliary reinforcement around column with 2 construction joints
PLAN
LEGEND
Construction joint
Type omega
Compressible material
thickness 2 cm
Auxiliary reinforcement
5 x ¤ 12 mm – Length: 1.5 m.
PLAN
LEGEND
Construction joint
Type omega
Compressible material
thickness 200 mm
Auxiliary reinforcement
5 x ¤ 12 mm – Length: 1.5 m.
CROSS SECTION
Auxiliary reinforcement around column at the edge
PLAN
LEGEND
Compressible material
thickn. 20 mm (column) - 10 mm (wall)
Auxiliary reinforcement
5 x ¤ 12 mm – Length: 1.5 m.
CROSS SECTION
Auxiliary reinforcement around column at the edge
PLAN
LEGEND
Compressible material
thickn. 20 mm (column) - 10 mm (wall)
Auxiliary reinforcement
5 x ¤ mm – Length: 1.5 m.
CROSS SECTION
Auxiliary reinforcement around column at the edge
with 1 construction joint
PLAN
LEGEND
Compressible material
thickn. 20 mm (column) - 10 mm (wall)
Auxiliary reinforcement
5 x ¤ 12 mm – Length: 1.5 m.
CROSS SECTION
Auxiliary reinforcement around an inspection shaft
PLAN
LEGEND
Compressible material
thickness 20 mm
Auxiliary reinforcement
3 x ¤ 12 mm – Length: 1.5 m.
Brick
CROSS SECTION
Auxiliary reinforcement at corners
Auxiliary reinforcement
10 x ¤ 12 mm – Length: 1.5 m.
concrete coverage = 5 cm
Wall
Expansion joint
Type omega
Auxiliary reinforcement at docking boards
PLAN
LEGEND
Brick
CROSS SECTION