Sei sulla pagina 1di 6

1. Final authority within the Project?

Project Board Project Board

2. Responsible for the day-to-day running of a


Project Manager
project? Project Manger
Corporate, Programme Management, or
3. Project Board’s “Boss”? Customer Corporate, Programme Management, or Custom

4. How many Project Managers in PRINCE2 One


- based on roles not jobs
- one person can have more than one roles
5. Project Management team? - roles identify individual’s responsibilities within
the Project Team (senior mechanic is job not a
role and team manager is a role not a job)
6. PRINCE2® project? suitable for all types of project
Temporary organisation to deliver one or more
7. Describes a PRINCE2® project?
business products to an agreed business case.
Repeatable (Continuing, Repeatable, and
8. NOT a characteristic of a PRINCE2® project? Permanent are all features of Business as Usual
(BAU).
Profits (six areas that the method will control -
9. PRINCE2® method not specifically controls? Costs, Timescales, Quality, Scope, Risk, and
Benefits)
Manage (Manage” is not part of the diagram
10. NOT one of the four steps in PRINCE2®’s view of because the diagram is about management)-
project management? plan, delegates and control steps in project
management
Techniques (No techniques are mandatory,
11. NOT one of the four “integrated elements” of a many techniques i.e. Product Based Planning,
PRINCE2® project? Quality Review etc.) Principles, Themes,
Processes are elements of PRINCE2®
12. True statement about the PRINCE2® principles? PRINCE2® all principles must be satisfied
Risk (Defined Roles and Responsibilities, Focus
13. Following is a Theme NOT a Principle? on Products and Manage by stages are
principles)

14. Theme is concerned with uncertainty? Risk

15. Themes support the “Focus On Products” principle? Quality

16. Theme supports Defined Roles & Responsibilities


Organisation
principle?
The Change theme acknowledges that change
is inevitable and must be controlled if the project
17. Statement about the Change Theme is TRUE?
is to be successful. (Change Theme is about
controlling change not preventing it).
Project should have a Benefit Review Approach

(Business Case should evolve and updated


18. How does the Business Case theme support the throughout the life of the project (as part of the
principle of Continued Business Justification? PID (Project Initiation Documentation) it is
considered for update in the Managing a Stage
Boundary process)

19. Theme provides a solution to the problem of the


Plans
planning horizon?
Starting Up a Project
(Starting up a Project (SU) identifies the
20. Pre-project activities? activities which the Project Team should perform
before the official start of the project. The aim is
to identify and prevent ill-conceived projects).

1 of 6
The Mandate
(The Project Mandate should provide the terms
of reference for the project and should contain
21. Product triggers a PRINCE2® project?
sufficient information to identify at least the
prospective executive of the Project Board).

22. First activity performed by the Project Board? Authorising Initiation (see diagram)
Authorising Initiation
(Authorising a Project is the second activity and
comes at the end of the initiation stage as the
project progresses).
23. Which affirmative decision by the Project Board
marks the point at which a PRINCE2® project starts?
Each Stage Plan (or replacement for a Stage
Plan – i.e. an Exception Plan) needs to be
authorised by the Board before the PM has the
authority to run it
Authorising a Project
(During the Starting up a Project (SU) process
we aim to identify any good and obvious
reasons why the project should not commence.
We also generate a crude picture of how the
24. Which is the first activity in which the Project Board project will flow. We need enough detail to justify
asks themselves? “Do we have a valid Business the cost of more detailed planning in the
Case?” Initiation Stage)

The PID is an output from the Initiating a Project


activity and is presented to the Board at the end
of the Initiation stage. The Board first examine
the PID in the Authorising a Project activity.
In Authorising a Stage or Exception Plan the
Board authorise each stage (after the Initiation
Stage)
25. How does the Directing a Project activity support the
Manage By Stages principle?
Giving Ad Hoc Direction is the activity that
allows spontaneous communication between the
PM and the Board – not authorising stages.
26. Project activity is conducted at the end of the
Authorising Initiation
Starting up a Project process?

27. Project activity is conducted at the end of the


Authorising a Project
Initiating a Project process?
Directing a Project
28. Process is NOT the responsibility of the Project
(The Directing a Project process is the
Manager?
responsibility of the Project Board).
29. Two Directing a Project activities that happen before
Authorising Initiation & Authorising a Project.
the Controlling a Stage process?

30. Created after the Board approves Initiation? The Quality Management Approach
The Outline Business Case
31. Which one of the following is created before the
(The Project Brief is needed by the Project
Board approves Initiation?
Board to Authorise (approve) Initiation).
The Quality Log is created in the Directing a
Project process- NOT

Nothing is created in the Directing a Project


process.
32. Statement is NOT true about Logs and Registers?
Two Logs (PM’s Daily Log and the Lessons Log)
are created in the SU (Starting up a Project)
process and three Registers (Quality, Risk, and
Issue) are created in the IP (Initiating a Project),

Daily Log is to capture informal issues.

2 of 6
33. How does the Starting Up process support the Learn
The Lessons Log is created
from Experience principle?
The Initiation Stage Plan is created
34. How does the Starting Up a Project process support
the Manage By Stages principle? This is the plan for the first stage of the project,
supporting the principle.
The Project Management Team is appointed

Activities within SU process:


35. How does the Starting Up process support the
- Outline Business Case is created
Defined Roles & Responsibilities principle?
- Lessons Log is created
- Project Management Team is appointed
- Next Stage Plan is created
The Project Plan is created

36. How does the Initiating a Project process support Each plan and each report has a lessons section
the Learn from Experience principle? which supports the Learn from Experience
principle, to avoid planning delivery strategies
that encountered problems in the past.
The Full Business Case is created.
37. How does the Initiating a Project process support
the Continued Business Justification principle? Continued Business Justification is all about
benefits.
The Communication Management Approach is
created.

38. How does the Initiating a Project process support The Principle of Roles & Responsibilities is all
the Defined Roles & Responsibilities principle? about who has what accountability and
responsibility within the project and how team
members will communicate (which is recorded in
the Communications Management Approach).
The PID is assembled.
39. How does the Initiating a Project process support
The PID contains details of how the method is to
the Tailor to Suit the Project Environment principle?
be tailored for a specific project. (Activity 1 of the
IP process).
Authorising Initiation

Ad Hoc Direction is the activity in which the


Project Board to make themselves available to
the PM for “any other business”, two-way
communication between the PM and their
40. Which one of the following Directing a Project
“Bosses” (the Board).
activity is used to accept Highlight, Issue, and
Exception reports?
• Keep the Board posted with developments
during the life of the project
• Have them make quick decisions on issues as
they arise
• Lets the Board contact the PM if they need to.

Authorising a Stage or Exception Plan

The activity covers two sets of circumstances:


either the end of the stage has been reached
naturally, or the Board has requested a
premature termination of the current stage by
asking the PM to create a replacement (i.e. an
41. Which of the following is a Directing a Project activity
Exception Plan). Both are created in much the
that is conducted at the end of the Managing a
same way in the Managing a Stage Boundary
Stage Boundary process?
process.

The Board consider and authorise these plans in


the Authorising a Stage or Exception plan
activity in the Directing a Project process.

Authorising a Work Package is an activity of the

3 of 6
Controlling a Stage process.

CS (controlling a Stage), SB (Managing a Stage


Boundary), MP (Managing Product Delivery),
42. Which processes are considered part of a CP (closing Project)
PRINCE2® project lifecycle delivery?
Starting up a Project (SU) Process is a pre-
project process. Therefore, the project has not
started and is not part of the project lifecycle.
Work Packages

Checkpoint reports are created in Managing


Product Delivery.

Highlight Reports are created in Controlling a


Stage but the manual does not talk about
43. Which one of the following products is created and
authorising them. The frequency of these will be
authorised in the Controlling a Stage process?
defined by the Project Executive and
documented in the Communication Management
Approach.

Next Stage Plans and End Stage Reports are


created in the Managing Stage a Boundary
process.
Authorising a Work Package
44. Which of the following is NOT a Project Board
activity? Project Managers (create) and authorise work
packages in the Controlling a Stage process.
The Specialist products are created

Stage Plans are created in the Managing Stage


Boundary process.
Highlight reports and work packages are created
in the Controlling a Stage process

In PRINCE2®, the Team Manager is not given


45. How does the Managing Product Delivery process full access to all the project’s management
support the Focus on Products principle? products. All the TM sees is a Work Package
and the Quality Register. The TM has no need
to see such things as the Business Case or
Strategies as these are irrelevant to the tasks
they have to perform. We use the term
“controlled link” to describe the fact that the TM
is isolated from the PRINCE2® method in the
Managing Product Delivery (MP) process, and
so may be unaware of the method.
The Next Stage Plan is created

The Next Stage Plan will identify any new


products needed for that stage

46. How does the Managing a Stage Boundary process Stage tolerances are proposed but not set in
support the Focus on Products principle? the Managing a Stage Boundary process. Stage
Tolerances are specifically set in the Directing a
Project process by the project board.
The End Project Report is created in the Closing
a Project (CP) process, not the Managing a
Stage Boundary process.
The Next Stage plan is created

Stage Tolerances are proposed in Managing a


47. How does the Managing a Stage Boundary process Stage Boundary but are set in Directing a
support the Manage By Stages principle? Project (in any case, this supports the Manage
By Exception principle not Manage By Stages).
The Next Stage Plan is authorised in Directing a
Project.

4 of 6
The End Stage Report is created in Managing
Stage Boundary but this has no bearing on
Manage By Stages
The Next Stage plan and the End Stage report
are created.

Both the Next Stage Plan and the End Stage


Report have a lessons section in them.
48. How does the Managing Stage Boundary process
Stage Tolerances are set by the Project Board in
support the Learn From Experience principle?
the DP process.
The PID does not contain the Lessons Log, so
lessons learned do not appear in here.
The Next Stage Plan is authorised by the Project
Board in the Directing a Project process.
The Business Case and the Benefits
Management Approach are updated if
necessary.

Continued Business Justification is supported by


the Business Case and the Benefits
49. How does the Managing Stage Boundary Process Management Approach.
support the Continued Business Justification The Outline Business Case is created in Starting
principle? Up a Project (SU) not Managing Stage
Boundary (SB).
Requesting Stage Tolerance supports the
Manage By Exception principle.
The Next Stage plan supports Manage by Stage
principle and the End Stage report further
supports the Learn from Experience principle.
The Business Case is constantly checked for
validity as the stage progresses.

The Next Stage Plan & the End Stage Report


are created in Managing a Stage Boundary (SB)
and the Business Case & Benefits Management
50. How does the Controlling a Stage Process support
Approach is updated there.
the Continued Business Justification principle?
The Outline Business Case is created in Starting
up a Project (SU). Ultimately, this will be
superseded by the Detailed Business Case.
Note: The Business Case is only updated in SU,
IP & SB processes not in CS (Controlling a
Stage).
When performing an impact assessment on new
issues or risks the PM checks for the impact on
the Business Case

Continued Business Justification is supported in


PRINCE2® projects by means of the Benefits
51. How does the Controlling a Stage Process support
Management Approach and the Business Case.
the Continued Business Justification principle?
The Business Case is NOT updated in CS
(Controlling a Stage). However, it is monitored
by the PM to make sure that it is still valid and it
is used as part of the procedure to assess
issues and risks.
Work Packages and their tolerances are set by
the PM

Stage Tolerance is requested in Managing


52. How does the Controlling a Stage Process support Stage Boundary (and is set in Directing a Project
the Manage by Exception principle? by the Executive).

The Change Control Approach is created in the


Initiating a Project (IP) process along with the
Issue Register.

5 of 6
A Work Package will have its tolerance set in the
Controlling a Stage process by the PM as part of
Authorising a Work Package.

Highlight Reports are created.

Highlight & Checkpoint reports both have a


Lessons Learned section, however the
Checkpoint report is created in the Managing
Product Delivery process not in the Controlling a
53. How does the Controlling a Stage Process support
Stage process.
the Learn from Experience principle?
Work Package tolerance is set in Controlling a
Stage however this supports the Manage By
Exception principle.
The Lessons Report is created in the Closing a
Project process.
Checkpoint reports are created

Highlight & Checkpoint reports both have a


Lessons Learned section however the Highlight
report is created in the Controlling a Stage (CS)
54. How does the Managing Product Delivery Process process not Managing Product Delivery (MP).
support the Learn from Experience principle?
Work Package tolerance is set in the Controlling
a Stage (CS) process and this supports the
Manage By Exception principle.
The Lessons Report is created in Closing a
Project (CP) process.
Highlight Reports are created
55. Which one of the following is NOT a way that the
Managing Product Delivery process supports the
Highlight reports are created in the Controlling a
Focus on Products principle?
Stage (CS) process
56. In which Directing a Project (DP) activity does the
Authorising Project Closure
Project Board consider if the project is truly at an
end and authorise the Project Manager to disband
it?
Authorise Project Closure

57. Which of the following is NOT an activity of Closing This is an activity of the Directing a Project
a Project? process. All the other options are activities
described in the manual as being part of the
Closing a Project Process.
Follow on actions

58. Which of the following is NOT an activity of Closing Follow On Actions are an output, not an activity
a Project ? from the Closing a Project process. They come
specifically from the activity of Hand over
products.
Communication Management Approach

The Communications Management Approach


deals with identifying stakeholders and their
59. Which one of the following Management
communication needs (both internal to the
Approaches is used in the Closing a Project (CP)
project and external).
process to identify whom the PM should contact to
inform that a project is being disbanded?
During the project closure activities, the PM may
well be interested in communicating with all
stakeholders who may be interested in the fact
that the project is closing.
60.

6 of 6

Potrebbero piacerti anche