III.1 Mechanical Main Equipment 51.559% 49.79%
III.1.1 Gas Turbine Generator Erection 66.273% 66.684%
III.1.1.1 Gas Turbine Generator #1 50.000% 50.310%
III.1.1.1.1 Pre-alignment of Gas turbine and driven equipment 50.000% 50.000%
III.1.1.1.1.1 Gas turbine skid & Generator positioning 30.000% 100.000% 0.000% 100.000% 30.000%
III.1.1.1.1.2 Gas Turbine, generator & gearbox pre-alignment 70.000% 100.000% 0.000% 100.000% 70.000%
III.1.1.1.2 Installation of auxiliary systems and ducting 31.000% 31.620%
III.1.1.1.2.1 Walkways & Stairs 15.000% 100.000% 0.000% 100.000% 15.000%
III.1.1.1.2.2 Enclosure installation 20.000% 100.000% 0.000% 100.000% 20.000%
III.1.1.1.2.3 Ventilation system 20.000% 100.000% 0.000% 100.000% 20.000%
III.1.1.1.2.4 Air intake system 20.000% 100.000% 0.000% 100.000% 20.000%
III.1.1.1.2.5 Exhaust system 10.000% 100.000% 0.000% 100.000% 10.000%
III.1.1.1.2.6 Auxiliary & Process systems 10.000% 100.000% 0.000% 100.000% 10.000%
III.1.1.1.2.7 Fire fighting system 7.000% 100.000% 0.000% 100.000% 7.000%
III.1.1.1.3 Installation of instrumentation 5.000% 100.000% 0.000% 100.000% 5.000%
III.1.1.1.4 Installation of Piping and tubing 5.000% 100.000% 0.000% 100.000% 5.000%
III.1.1.1.5 Electrical installation and cabling 3.000% 100.000% 0.000% 100.000% 3.000%
III.1.1.1.6 NDT & Hidrotest 2.000% 100.000% 0.000% 100.000% 2.000%
III.1.1.1.7 String Alignment 4.000% 100.000% 0.000% 100.000% 4.000%
III.1.1.2 Gas Turbine Generator #2 50.000% 50.310%
III.1.1.1.1 Pre-alignment of Gas turbine and driven equipment 50.000% 50.000%
III.1.1.1.1.1 Gas turbine skid & Generator positioning 30.000% 100.000% 0.000% 100.000% 30.000%
III.1.1.1.1.2 Gas Turbine, generator & gearbox pre-alignment 70.000% 100.000% 0.000% 100.000% 70.000%
III.1.1.1.2 Installation of auxiliary systems and ducting 31.000% 31.620%
III.1.1.1.2.1 Walkways & Stairs 10.000% 100.000% 0.000% 100.000% 10.000%
III.1.1.1.2.2 Enclosure installation 25.000% 100.000% 0.000% 100.000% 25.000%
III.1.1.1.2.3 Ventilation system 20.000% 100.000% 0.000% 100.000% 20.000%
III.1.1.1.2.4 Air intake system 20.000% 100.000% 0.000% 100.000% 20.000%
III.1.1.1.2.5 Exhaust system 10.000% 100.000% 0.000% 100.000% 10.000%
III.1.1.1.2.6 Auxiliary & Process systems 10.000% 100.000% 0.000% 100.000% 10.000%
III.1.1.1.2.7 Fire fighting system 7.000% 100.000% 0.000% 100.000% 7.000%
III.1.1.1.3 Installation of instrumentation 5.000% 100.000% 0.000% 100.000% 5.000%
III.1.1.1.4 Installation of Piping and tubing 5.000% 100.000% 0.000% 100.000% 5.000%
III.1.1.1.5 Electrical installation and cabling 3.000% 100.000% 0.000% 100.000% 3.000%
III.1.1.1.6 NDT & Hidrotest 2.000% 100.000% 0.000% 100.000% 2.000%
III.1.1.1.7 String Alignment 4.000% 100.000% 0.000% 100.000% 4.000%
III.1.2 Bypass Stack 2.696% 2.696%
III.1.2.1 Bypass Stack #1 50.000% 50.000%
III.1.2.1.1 Diverter Damper erection 20.000% 100.000% 0.000% 100.000% 20.00%
III.1.2.1.2 Lower transition onto top of diverter 5.000% 100.000% 0.000% 100.000% 5.00%
III.1.2.1.3 GT Expansion Joint, transition duct, and extension duct 10.000% 100.000% 0.000% 100.000% 10.00%
III.1.2.1.4 Support Structure over diverter 10.000% 100.000% 0.000% 100.000% 10.00%
III.1.2.1.5 Silencer & Upper transition duct onto support structure 10.000% 100.000% 0.000% 100.000% 10.00%
III.1.2.1.6 Bypass expansion joint belt between silencer and lower transition 2.500% 100.000% 0.000% 100.000% 2.50%
III.1.2.1.7 Stack section onto upper transition duct 17.500% 100.000% 0.000% 100.000% 17.50%
III.1.2.1.8 Access ladder & platforms 10.000% 100.000% 0.000% 100.000% 10.00%
III.1.2.1.9 HRSG expansion joint and transition duct 10.000% 100.000% 0.000% 100.000% 10.00%
III.1.2.1.10 Auxiliary equipment (HPU, Fan, Control panel) 5.000% 100.000% 0.000% 100.000% 5.00%
III.1.2.2 Bypass Stack #2 50.000% 50.000%
III.1.2.2.1 Diverter Damper erection 20.000% 100.000% 0.000% 100.000% 20.00%
III.1.2.2.2 Lower transition onto top of diverter 5.000% 100.000% 0.000% 100.000% 5.00%
III.1.2.2.3 GT Expansion Joint, transition duct, and extension duct 10.000% 100.000% 0.000% 100.000% 10.00%
III.1.2.2.4 Support Structure over diverter 10.000% 100.000% 0.000% 100.000% 10.00%
III.1.2.2.5 Silencer & Upper transition duct onto support structure 10.000% 100.000% 0.000% 100.000% 10.00%
III.1.2.2.6 Bypass expansion joint belt between silencer and lower transition 2.500% 100.000% 0.000% 100.000% 2.50%
III.1.2.2.7 Stack section onto upper transition duct 17.500% 100.000% 0.000% 100.000% 17.50%
III.1.2.2.8 Access ladder & platforms 10.000% 100.000% 0.000% 100.000% 10.00%
III.1.2.2.9 HRSG expansion joint and transition duct 10.000% 100.000% 0.000% 100.000% 10.00%
III.1.2.2.10 Auxiliary equipment (HPU, Fan, Control panel) 5.000% 100.000% 0.000% 100.000% 5.00%

III.1.3 Heat Recovery Steam Generator 16.066% 15.130%


III.1.3.1 Heat Recovery Steam Generator Unit #1 50.000% 47.1983%
III.1.3.1.1 Erection HRSG Modules 18.000% 100.000% 0.000% 100.000% 18.000%
III.1.3.1.2 Installation steam drums/daerator + downcomer 15.000% 100.000% 0.000% 100.000% 15.000%
III.1.3.1.3 Erection of staircase, platform, and ladders 7.500% 100.000% 0.000% 100.000% 7.500%
III.1.3.1.4 Intermediate ducting & interconnecting piping 10.000% 100.000% 0.000% 100.000% 10.000%
III.1.3.1.5 Erection Inlet Duct 9.500% 100.000% 0.000% 100.000% 9.500%
III.1.3.1.6 Erection of stack including platforms, damper, silencer and ladders 10.000% 100.000% 0.000% 100.000% 10.000%
III.1.3.1.7 Piping (incl. valves, supports, hangers, etc) 10.000% 99.105% 0.000% 99.105% 9.911%
III.1.3.1.8 Installation of Tanks/vessels, blow-off silencers 3.000% 100.000% 0.000% 100.000% 3.000%
III.1.3.1.9 Hydrostatic testing 5.000% 0.000% 0.000% 0.000% 0.000%
III.1.3.1.10 External insulation piping and drums (BOP) 2.500% 0.000% 0.000% 0.000% 0.000%
III.1.3.1.11 Touch-up and painting 2.500% 100.000% 0.000% 100.000% 2.500%
III.1.3.1.12 Auxiliary equipment (pumps, chemical dosing, etc) 3.000% 100.000% 0.000% 100.000% 3.000%
III.1.3.1.14 Controls, Electrical & Instrumentation installation 4.000% 99.650% 0.000% 99.650% 3.986%
III.1.3.2 Heat Recovery Steam Generator Unit #2 50.000% 46.9746%
III.1.3.1.1 Erection HRSG Modules 18.000% 100.000% 0.000% 100.000% 18.000%
III.1.3.1.2 Installation steam drums/daerator + downcomer 15.000% 100.000% 0.000% 100.000% 15.000%
III.1.3.1.3 Erection of staircase, platform, and ladders 7.500% 100.000% 0.000% 100.000% 7.500%
III.1.3.1.4 Intermediate ducting & interconnecting piping 10.000% 100.000% 0.000% 100.000% 10.000%
III.1.3.1.5 Erection Inlet Duct 9.500% 100.000% 0.000% 100.000% 9.500%
III.1.3.1.6 Erection of stack including platforms, damper, silencer and ladders 10.000% 100.000% 0.000% 100.000% 10.000%
III.1.3.1.7 Piping (incl. valves, supports, hangers, etc) 10.000% 98.580% 0.000% 98.580% 9.858%
III.1.3.1.8 Installation of Tanks/vessels, blow-off silencers 3.000% 100.000% 0.000% 100.000% 3.000%
III.1.3.1.9 Hydrostatic testing 5.000% 0.000% 0.000% 0.000% 0.000%
III.1.3.1.10 External insulation piping and drums (BOP) 2.500% 0.000% 0.000% 0.000% 0.000%
III.1.3.1.11 Touch-up and painting 2.500% 89.060% 0.000% 89.060% 2.227%
III.1.3.1.12 Auxiliary equipment (pumps, chemical dosing, etc) 3.000% 100.000% 0.000% 100.000% 3.000%
III.1.3.1.14 Controls, Electrical & Instrumentation installation 4.000% 96.615% 0.000% 96.615% 3.865%
III.1.4 Steam Turbine 14.965% 11.47%
III.1.4.1 Pre alignment & Levelling Turbo set 20.000% 20.00%
III.1.4.1.1 Generator 25.000% 100.000% 0.000% 100.000% 25.0000%
III.1.4.1.2 Gearbox 25.000% 100.000% 0.000% 100.000% 25.0000%
III.1.4.1.3 Turbine 25.000% 100.000% 0.000% 100.000% 25.0000%
III.1.4.1.4 Condenser 25.000% 100.000% 0.000% 100.000% 25.0000%
III.1.4.2 Installation of Accessories 20.000% 90.300% 0.000% 90.300% 18.06%
III.1.4.3 Filling oil tank 5.000% 0.000% 0.000% 0.000% 0.00%
III.1.4.4 Installation of piping system 25.000% 70.000% 0.000% 70.000% 17.50%
III.1.4.5 Installation of electric equipment 15.000% 0.000% 0.000% 0.000% 0.00%
III.1.4.6 Final Alignment 10.000% 0.000% 0.000% 0.000% 0.00%
III.1.4.7 Checking & Readiness for Operation 5.000% 0.000% 0.000% 0.000% 0.00%

III.2 Mechanical Balance of Plant 12.168% 8.64%


III.2.1 Condenser, Condesate Pump, Feed Water Heating Plant Complete with Auxiliary 30.895% 30.90%
III.2.1.1 Condenser & Hotwell 60.000% 60.000%
III.2.1.1.1 Mounting on foundation 50.000% 100.000% 0.000% 100.000% 50.000%
III.2.1.1.2 Installing Sliding plate, sole plate, and others support 10.000% 100.000% 0.000% 100.000% 10.000%
III.2.1.1.3 Installing Piping 40.000% 40.000%
III.2.1.1.1.1 Venting Condenser 50.000% 100.000% 0.000% 100.000% 50.000%
III.2.1.1.1.2 Draining Condenser 50.000% 100.000% 0.000% 100.000% 50.000%
III.2.1.2 Condensate Pump 10.000% 100.000% 0.000% 100.000% 10.00%
III.2.1.3 Boiler Feed Water Pump 30.000% 100.000% 0.000% 100.000% 30.000%
III.2.2 Sea Water Cooling System with Auxiliary 10.647% 0.000% 0.000% 0.000% 0.00%
III.2.3 Sea Water Pump, Make Up Pump System and Auxiliary 1.961% 45.000% 0.000% 45.000% 0.88%
III.2.4 Sea Water Intake System, Sea Water Intake Pump Complete with Auxiliary 1.961% 39.650% 0.000% 39.650% 0.78%
III.2.5 Complete Plant Water System, Water Treatment System, Closed Cooling System and Auxiliary 1.961% 98.920% 0.000% 98.920% 1.94%
III.2.6 Drainage and Waste Water Treatment System Complete with Auxiliary 3.971% 0.000% 0.000% 0.000% 0.00%
III.2.7 Fire Protection system Complete with Auxiliary 6.890% 98.350% 0.000% 98.350% 6.78%
III.2.8 Compress Air System Complete With Auxiliary 3.356% 99.410% 0.000% 99.410% 3.34%
III.2.9 Chemical Feed System complete with Auxiliary 2.817% 0.000% 0.000% 0.000% 0.00%
III.2.10 Sampling Rack System complete with Auxiliary 2.552% 50.000% 0.000% 50.000% 1.28%
III.2.11 Laboratory and Instrument complete with auxiliary 2.324% 50.000% 0.000% 50.000% 1.16%
III.2.12 Chlorination System Complete With Auxiliary system 3.586% 0.000% 0.000% 0.000% 0.00%
III.2.13 Air Conditioning and Ventilation Complete with Auxiliary 3.730% 100.000% 0.000% 100.000% 3.73%
III.2.14 Crane and Hoist Complete with Auxiliary 4.416% 100.000% 0.000% 100.000% 4.42%
III.2.15 Natural Gas System Complete with Auxiliary 12.464% 100.000% 0.000% 100.000% 12.46%
III.2.16 Workshop and Machinery Equipment 2.548% 15.000% 0.000% 15.000% 0.38%
III.2.17 Steam and Water Analysis System 1.961% 50.000% 0.000% 50.000% 0.98%
III.2.18 Overhead Crane 1.961% 100.000% 0.000% 100.000% 1.96%
III.3 Electrical Main Equipment 6.385% 6.423%
III.3.1 150 KV Switchayrd 42.358% 59.30%
III.3.1.1 Gantry Steel & apparatus support Installations 40.00% 100.000% 0.000% 100.000% 40.000%
III.3.1.2 Apparatus Installations 60.00% 100.000%
III.3.1.2.1 Cable Head Installations 10.000% 100.000% 0.000% 100.000% 10.000%
III.3.1.2.2 Lightning Arrester Installations 10.000% 100.000% 0.000% 100.000% 10.000%
III.3.1.2.3 CVT Installations 20.000% 100.000% 0.000% 100.000% 20.000%
III.3.1.2.4 DSE Installations 20.000% 100.000% 0.000% 100.000% 20.000%
III.3.1.2.5 CT Installations 10.000% 100.000% 0.000% 100.000% 10.000%
III.3.1.2.6 Conductor Installations 20.000% 100.000% 0.000% 100.000% 20.000%
III.3.1.2.7 CRP Installations 5.000% 100.000% 0.000% 100.000% 5.000%
III.3.1.2.8 Other Accessories, etc 5.000% 100.000% 0.000% 100.000% 5.000%
III.3.2 GSU Transformer for GTG 23.563% 23.56%
III.3.2.1 GSU Transformer for GTG#1 50.00% 50.000%
III.3.2.1.1 HV Bushing Installations 20.000% 100.000% 0.000% 100.000% 20.00%
III.3.2.1.2 LV Bushing Installations 20.000% 100.000% 0.000% 100.000% 20.00%
III.3.2.1.3 Tertier Bushing & Cable Box Installations 15.000% 100.000% 0.000% 100.000% 15.00%
III.3.2.1.4 Conservator Installations 7.500% 100.000% 0.000% 100.000% 7.50%
III.3.2.1.5 Radiator Installations 15.000% 100.000% 0.000% 100.000% 15.00%
III.3.2.1.6 Piping & Other Accessories 2.500% 100.000% 0.000% 100.000% 2.50%
III.3.2.1.7 Oil Purifier 20.000% 100.000% 0.000% 100.000% 20.00%
III.3.2.1 GSU Transformer for GTG#2 50.00% 50.000%
III.3.2.1.1 HV Bushing Installations 20.000% 100.000% 0.000% 100.000% 20.00%
III.3.2.1.2 LV Bushing Installations 20.000% 100.000% 0.00% 100.000% 20.00%
III.3.2.1.3 Tertier Bushing Installations 15.000% 100.000% 0.000% 100.000% 15.00%
III.3.2.1.4 Conservator Installations 7.500% 100.000% 0.000% 100.000% 7.50%
III.3.2.1.5 Radiator Installations 15.000% 100.000% 0.000% 100.000% 15.00%
III.3.2.1.6 Piping & Other Accessories 2.500% 100.000% 0.000% 100.000% 2.50%
III.3.2.1.7 Oil Purifier 20.000% 100.000% 0.000% 100.000% 20.00%
III.3.3 Generator Circuit Breaker (GCB) for GTG 11.965% 6.49%
III.3.2.1 Generator Circuit Breaker (GCB) for GTG#1 50.00% 27.125%
III.3.2.1.1 Mounting on foundation 20.000% 100.000% 0.000% 100.000% 20.00%
III.3.2.1.2 Earth Bus Connection 20.000% 100.000% 0.000% 100.000% 20.00%
III.3.2.1.3 Other Accessories, etc 15.000% 95.000% 0.000% 95.000% 14.25%
III.3.2.1 Generator Circuit Breaker (GCB) for GTG#2 50.00% 27.125%
III.3.2.1.1 Mounting on foundation 20.000% 100.000% 0.000% 100.000% 20.00%
III.3.2.1.2 Earth Bus Connection 20.000% 100.000% 0.000% 100.000% 20.00%
III.3.2.1.3 Other Accessories, etc 15.000% 95.000% 0.000% 95.000% 14.25%
III.3.4 GSU Transformer for STG 13.957% 11.86%
III.3.2.1.1 HV Bushing Installations 20.000% 100.000% 0.000% 100.000% 20.00%
III.3.2.1.2 LV Bushing Installations 20.000% 100.000% 0.000% 100.000% 20.00%
III.3.2.1.3 Conservator Installations 7.500% 100.000% 0.000% 100.000% 7.50%
III.3.2.1.4 Radiator Installations 15.000% 100.000% 0.000% 100.000% 15.00%
III.3.2.1.5 Piping & Other Accessories 2.500% 100.000% 0.000% 100.000% 2.50%
III.3.2.1.6 Oil Purifier 20.000% 100.000% 0.000% 100.000% 20.00%
III.3.5 Generator Circuit Breaker for STG 8.158% 0.000% 0.000% 0.000% 0.000%
III.4 Electrical Balance of Plant 8.000% 7.040%
III.4.1 MV Switchgear 10.601% 11.578% 10.47%
III.4.1.1 Mounting Panel & Busbar Connection 50.00% 100.000% 0.000% 100.000% 50.00%
III.4.1.2 Termination Power, Control & Instrument Cable 50.00% 97.500% 0.000% 97.500% 48.75%
III.4.2 LV Switchgear 9.151% 90.000% 0.000% 90.000% 8.24%
III.4.3 UAT and Station Service Transformer 5.550% 5.550%
III.4.3.1 UAT #1 25.00% 100.000% 0.000% 100.000% 25.0%
III.4.3.2 UAT #2 25.00% 100.000% 0.000% 100.000% 25.0%
III.4.3.3 SST #1 25.00% 100.000% 0.000% 100.000% 25.0%
III.4.3.4 SST #2 25.00% 100.000% 0.000% 100.000% 25.0%
III.4.4 DC System and UPS 4.244% 100.000% 0.000% 100.000% 4.244%
III.4.5 Lighting and Distribution Panel 5.246% 86.050% 0.000% 86.050% 4.514%
III.4.6 Emergency Diesel Generator 10.925% 99.000% 0.000% 99.000% 10.816%
III.4.7 Distributed Control System (DCS) and Control Emission Monitoring System (CEMS) 22.921% 66.450% 0.000% 66.450% 15.231%
III.4.8 CCTV, Fire Detection System and Plant Telecommunication System 3.971% 96.593% 0.000% 96.59% 3.836%
III.4.9 LV Cable, MV Cable, Control Cable and Busduct 18.567% 15.67%
III.4.9.1 HV Cable 16.67% 100.000% 0.00% 100.000% 16.667%
III.4.9.2 MV Cable 16.67% 70.000% 0.000% 70.000% 11.667%
III.4.9.3 LV Cable 16.67% 65.950% 0.000% 65.950% 10.992%
III.4.9.4 Control & Instrument Cable 16.67% 70.500% 0.000% 70.500% 11.750%
III.4.9.5 IPBD 16.67% 100.000% 0.000% 100.000% 16.667%
III.4.9.6 NSPBD 16.67% 100.000% 0.00% 100.000% 16.667%
III.4.10 Lightning Protection and Grounding System 4.702% 93.820% 0.000% 93.820% 4.411%
III.4.11 Power Plant Metering and Protection Panel 4.122% 95.000% 0.000% 95.000% 3.916%
III.5 Civil, Structure & Architechtural Works 21.888% 20.712%
III.5.1 Civil Work for Gas Turbine Generator 12.363% 12.363%
III.5.1.1 Gas Turbine Generator #1 Foundation 50.000% 50.000%
III.5.1.1.1 Excavation Works for Foundation 5.790% 100.000% 0.000% 100.000% 5.790%
III.5.1.1.2 Lean Concrete 1.910% 100.000% 0.000% 100.000% 1.910%
III.5.1.1.3 Reinforcement Bar 35.380% 35.380%
III.5.1.1.3.1 Besi D25 100.000% 100.000% 0.000% 100.000% 100.000%
III.5.1.1.4 Formwork 2.020% 100.000% 0.000% 100.000% 2.020%
III.5.1.1.5 Anchor bolt,Embedded Plate & Misc Equipment Installation 3.900% 3.900%
III.5.1.1.5.1 Anchor bolt 12.941% 100.000% 0.000% 100.000% 12.941%
III.5.1.1.5.2 Embedded Plate 87.059% 100.000% 0.000% 100.000% 87.059%
III.5.1.1.6 Pouring Foundation 47.680% 100.000% 0.000% 100.000% 47.680%
III.5.1.1.7 Backfilling 3.320% 100.000% 0.000% 100.000% 3.320%
III.5.1.2 Gas Turbine Generator #2 Foundation 50.000% 50.000%
III.5.1.2.1 Excavation Works for Foundation 5.790% 100.000% 0.000% 100.000% 5.790%
III.5.1.2.2 Lean Concrete 1.910% 100.000% 0.000% 100.000% 1.910%
III.5.1.2.3 Reinforcement Bar 35.380% 35.380%
III.5.1.2.3.1 Besi D25 100.000% 100.000% 0.000% 100.000% 100.000%
III.5.1.2.4 Formwork 2.020% 100.000% 0.000% 100.000% 2.020%
III.5.1.2.5 Anchor bolt,Embedded Plate & Misc Equipment Installation 3.900% 3.900%
III.5.1.2.5.1 Anchor bolt 27.907% 100.000% 0.000% 100.000% 27.907%
III.5.1.2.5.2 Embedded Plate 72.093% 100.000% 0.000% 100.000% 72.093%
III.5.1.2.6 Pouring Foundation 47.680% 100.000% 0.000% 100.000% 47.680%
III.5.1.2.7 Backfilling 3.320% 100.000% 0.000% 100.000% 3.320%
TOTAL CONSTRUCTION GAS TURBINE GENERATOR WORKS
III.5.2 Civil Work for Ducting, Dumper and By Pass Stack & Auxiliary 2.101% 2.101%
II.5.2.1 Bypass Stack 1 50.000% 50.000%
II.5.2.1.1 Lean Concrete 2.300% 100.000% 0.000% 100.000% 2.300%
II.5.2.1.2 Reinforcement Bar 34.340% 100.000% 0.000% 100.000% 34.340%
II.5.2.1.3 Formwork 8.432% 100.000% 0.000% 100.000% 8.432%
II.5.2.1.4 Anchor Bolt & Misc Equipment 15.000% 100.000% 0.000% 100.000% 15.000%
II.5.2.1.5 Pouring Concrete 34.410% 100.000% 0.000% 100.000% 34.410%
II.5.2.1.6 Backfilling 5.518% 100.000% 0.000% 100.000% 5.518%
II.5.2.1 Bypass Stack 2 50.000% 50.000%
II.5.2.1.1 Lean Concrete 2.300% 100.000% 0.000% 100.000% 2.300%
II.5.2.1.2 Reinforcement Bar 34.340% 100.000% 0.000% 100.000% 34.340%
II.5.2.1.3 Formwork 8.432% 100.000% 0.000% 100.000% 8.432%
II.5.2.1.4 Anchor Bolt & Misc Equipment 15.000% 100.000% 0.000% 100.000% 15.000%
II.5.2.1.5 Pouring Concrete 34.410% 100.000% 0.000% 100.000% 34.410%
II.5.2.1.6 Backfilling 5.518% 100.000% 0.000% 100.000% 5.518%
III.5.3 Civil Work for HRSG Complete with Auxiliary Equipment 2.177% 2.177%
III.5.3.1 Heat Recovery Steam Generator #1 Foundation 50.000% 50.020%
III.5.3.1.1 Excavation Works for Foundation 2.900% 100.000% 0.000% 100.000% 2.900%
III.5.3.1.2 Lean Concrete 1.860% 100.000% 0.000% 100.000% 1.860%
III.5.3.1.3 Reinforcement Bar 36.000% 36.000%
III.5.3.1.3.1 Besi D10 29.856% 100.000% 0.000% 100.000% 29.856%
III.5.3.1.3.2 Besi D13 19.904% 100.000% 0.000% 100.000% 19.904%
III.5.3.1.3.3 Besi D16 2.677% 100.000% 0.000% 100.000% 2.677%
III.5.3.1.3.4 Besi D19 5.903% 100.000% 0.000% 100.000% 5.903%
III.5.3.1.3.5 Besi D25 35.278% 100.000% 0.000% 100.000% 35.278%
III.5.3.1.3.6 Besi D32 6.383% 100.000% 0.000% 100.000% 6.383%
III.5.3.1.4 Formwork 1.400% 100.000% 0.000% 100.000% 1.400%
III.5.3.1.5 Anchor bolt,Embedded Plate & Misc Equipment Installation 2.860% 2.860%
III.5.3.1.5.1 Anchor bolt 50.000% 100.000% 0.000% 100.000% 50.000%
III.5.3.1.5.2 Stack Template 50.000% 100.000% 0.000% 100.000% 50.000%
III.5.3.1.6 Pouring Foundation 53.460% 100.000% 0.000% 100.000% 53.460%
III.5.3.1.7 Backfilling 1.560% 100.000% 0.000% 100.000% 1.560%
III.5.3.2 Heat Recovery Steam Generator #2 Foundation 50.000% 50.020%
III.5.3.2.1 Excavation Works for Foundation 2.900% 100.000% 0.000% 100.000% 2.900%
III.5.3.2.2 Lean Concrete 1.860% 100.000% 0.000% 100.000% 1.860%
III.5.3.2.3 Reinforcement Bar 36.000% 36.000%
III.5.3.2.3.1 Besi D10 29.856% 100.000% 0.000% 100.000% 29.856%
III.5.3.2.3.2 Besi D13 19.904% 100.000% 0.000% 100.000% 19.904%
III.5.3.2.3.3 Besi D16 2.677% 100.000% 0.000% 100.000% 2.677%
III.5.3.2.3.4 Besi D19 5.903% 100.000% 0.000% 100.000% 5.903%
III.5.3.2.3.5 Besi D25 35.278% 100.000% 0.000% 100.000% 35.278%
III.5.3.2.3.6 Besi D32 6.383% 100.000% 0.000% 100.000% 6.383%
III.5.3.2.4 Formwork 1.400% 100.000% 0.000% 100.000% 1.400%
III.5.3.2.5 Anchor bolt,Embedded Plate & Misc Equipment Installation 2.860% 2.860%
III.5.3.1.5.1 Anchor bolt 50.000% 100.000% 0.000% 100.000% 50.000%
III.5.3.1.5.2 Stack Template 50.000% 100.000% 0.000% 100.000% 50.000%
III.5.3.2.6 Pouring Foundation 53.460% 100.000% 0.000% 100.000% 53.460%
III.5.3.2.7 Backfilling 1.560% 100.000% 0.000% 100.000% 1.560%
TOTAL CONSTRUCTION HEAT RECOVERY STEAM GENERATOR WORKS
III.5.4 Civil Work for Steam Turbine, HRSG Feed Pump, Complete with Auxiliary Equipment 2.177% 2.177%
III.5.4.1 Excavation Works for foundation 15.000% 100.000% 0.000% 100.000% 15.000%
III.5.4.2 Lean Concrete 5.000% 100.000% 0.000% 100.000% 5.000%
III.5.4.3 Reinforcement Bar 25.000% 100.000% 0.000% 100.000% 25.000%
III.5.4.4 Formwork 10.000% 100.000% 0.000% 100.000% 10.000%
III.5.4.5 Anchor bolt,Embedded Plate & Misc Equipment Installation 15.000% 100.000% 0.000% 100.000% 15.000%
III.5.4.6 Pouring Foundation 25.000% 100.000% 0.000% 100.000% 25.000%
III.5.4.7 Backfilling 5.000% 100.000% 0.000% 100.000% 5.000%
III.5.5 Civil Work for Condenser and Condensate Pump, Feed Water Heating Plant Complete with Aux
2.177% 2.177%
III.5.5.1 Excavation Works for foundation 10.000% 100.000% 0.000% 100.000% 10.000%
III.5.5.2 Lean Concrete 10.000% 100.000% 0.000% 100.000% 10.000%
III.5.5.3 Reinforcement Bar 30.000% 100.000% 0.000% 100.000% 30.000%
III.5.5.4 Formwork 10.000% 100.000% 0.000% 100.000% 10.000%
III.5.5.5 Pouring Foundation 30.000% 100.000% 0.000% 100.000% 30.000%
III.5.5.6 Backfilling 10.000% 100.000% 0.000% 100.000% 10.000%
III.5.6 Civil Work for Sea Water Cooling System 2.101% 2.10%
III.5.6.1 Excavation Works for foundation 10.000% 100.000% 0.000% 100.000% 10.000%
III.5.6.2 Lean Concrete 10.000% 100.000% 0.000% 100.000% 10.000%
III.5.6.3 Reinforcement Bar 30.000% 100.000% 0.000% 100.000% 30.000%
III.5.6.4 Formwork 10.000% 100.000% 0.000% 100.000% 10.000%
III.5.6.5 Pouring Foundation 30.000% 100.000% 0.000% 100.000% 30.000%
III.5.6.6 Backfilling 10.000% 100.000% 0.000% 100.000% 10.000%
III.5.7 Civil Work for Sea Water Pond System and Make Up Pump System 11.414% 11.41%
III.5.7.1 Excavation Works for foundation 10.000% 100.000% 0.00% 100.000% 10.0%
III.5.7.2 Lean Concrete 10.000% 100.000% 0.00% 100.000% 10.0%
III.5.7.3 Reinforcement Bar 25.000% 100.000% 0.00% 100.000% 25.0%
III.5.7.4 Formwork 10.000% 100.000% 0.00% 100.000% 10.0%
III.5.7.5 Pouring Foundation 30.000% 100.000% 0.00% 100.000% 30.0%
III.5.7.6 Water Stop Installing 5.000% 100.000% 0.00% 100.000% 5.0%
III.5.7.7 Backfilling 10.000% 100.000% 0.00% 100.000% 10.0%
III.5.8 Civil Work for Sea Water Intake System and Sea Water Intake Pump Complete 6.786% 6.76%
III.5.8.1 Excavation Works for foundation 25.000% 100.000% 0.00% 100.000% 25.000%
III.5.8.2 Lean Concrete 5.000% 100.000% 0.000% 100.000% 5.000%
III.5.8.3 Reinforcement Bar 25.000% 99.500% 0.000% 99.500% 24.875%
III.5.8.4 Formwork 10.000% 99.500% 0.000% 99.500% 9.950%
III.5.8.5 Pouring Foundation 30.000% 99.500% 0.000% 99.500% 29.850%
III.5.8.6 Backfilling 5.000% 100.000% 0.000% 100.000% 5.000%
III.5.9 Civil Work for Plant Water System, Water Treatment System and Closed 1.499% 1.50%
III.5.9.1 Excavation Works for foundation 10.000% 100.000% 0.000% 100.000% 10.00%
III.5.9.2 Lean Concrete 10.000% 100.000% 0.000% 100.000% 10.00%
III.5.9.3 Reinforcement Bar 30.000% 100.000% 0.000% 100.000% 30.00%
III.5.9.4 Formwork 10.000% 100.000% 0.000% 100.000% 10.00%
III.5.9.5 Pouring Foundation 30.000% 100.000% 0.000% 100.000% 30.00%
III.5.9.6 Backfilling 10.000% 100.000% 0.000% 100.000% 10.00%
III.5.10 Civil Work for Waste Water Treatment System 1.499% 2.66%
III.5.10.1 Excavation Works for foundation 10.000% 99.400% 0.000% 99.400% 9.940%
III.5.10.2 Lean Concrete 10.000% 80.000% 0.000% 80.000% 8.000%
III.5.10.3 Reinforcement Bar 30.000% 92.200% 0.000% 92.200% 27.660%
III.5.10.4 Formwork 10.000% 86.100% 0.000% 86.100% 8.610%
III.5.10.5 Pouring Foundation 30.000% 76.770% 0.000% 76.770% 23.031%
III.5.10.6 Backfilling 10.000% 100.000% 0.000% 100.000% 100.000%
III.5.11 Civil Work for Fire Protection System 1.499% 1.46%
III.5.11.1 Excavation Works for foundation 10.000% 100.000% 0.000% 100.000% 10.00%
III.5.11.2 Lean Concrete 10.000% 100.000% 0.000% 100.000% 10.00%
III.5.11.3 Reinforcement Bar 30.000% 100.000% 0.000% 100.000% 30.00%
III.5.11.4 Formwork 10.000% 100.000% 0.000% 100.000% 10.00%
III.5.11.5 Pouring Foundation 30.000% 100.000% 0.000% 100.000% 30.00%
III.5.11.6 Backfilling 10.000% 73.000% 0.000% 73.000% 7.30%
III.5.12 Civil Work for Compressed Air System 1.499% 1.50%
III.5.12.1 Excavation Works for foundation 10.000% 100.000% 0.000% 100.000% 10.0%
III.5.12.2 Lean Concrete 10.000% 100.000% 0.000% 100.000% 10.0%
III.5.12.3 Reinforcement Bar 30.000% 100.000% 0.000% 100.000% 30.0%
III.5.12.4 Formwork 10.000% 100.000% 0.000% 100.000% 10.0%
III.5.12.5 Pouring Foundation 30.000% 100.000% 0.000% 100.000% 30.0%
III.5.12.6 Backfilling 10.000% 100.000% 0.000% 100.000% 10.0%
III.5.13 Civil Work for Chemical Feed System Complete 1.499% 0.000%
III.5.13.1 Excavation Works for foundation 10.000% 100.000% 0.000% 100.000% 100.000%
III.5.13.2 Lean Concrete 10.000% 50.000% 0.000% 50.000% 25.000%
III.5.13.3 Reinforcement Bar 30.000% 25.000% 0.000% 25.000% 6.250%
III.5.13.4 Formwork 10.000% 25.000% 0.000% 25.000% 6.250%
III.5.13.5 Pouring Foundation 30.000% 25.000% 0.000% 25.000% 6.250%
III.5.13.6 Backfilling 10.000% 0.000% 0.000% 0.000% 0.000%
III.5.14 Sampling Rack System Complete with Auxiliary 1.499% 1.499%
III.5.14.1 Excavation Works for foundation 10.000% 100.000% 0.000% 100.000% 10.0%
III.5.14.2 Lean Concrete 10.000% 100.000% 0.000% 100.000% 10.0%
III.5.14.3 Reinforcement Bar 30.000% 100.000% 0.000% 100.000% 30.0%
III.5.14.4 Formwork 10.000% 100.000% 0.000% 100.000% 10.0%
III.5.14.5 Pouring Foundation 30.000% 100.000% 0.000% 100.000% 30.0%
III.5.14.6 Backfilling 10.000% 100.000% 0.000% 100.000% 10.0%
III.5.15 Civil Work for Laboratory and Instrument Complete 1.499% 1.499%
III.5.15.1 Excavation Works for foundation 10.000% 100.000% 0.000% 100.000% 10.0%
III.5.15.2 Lean Concrete 10.000% 100.000% 0.000% 100.000% 10.0%
III.5.15.3 Reinforcement Bar 30.000% 100.000% 0.000% 100.000% 30.0%
III.5.15.4 Formwork 10.000% 100.000% 0.000% 100.000% 10.0%
III.5.15.5 Pouring Foundation 30.000% 100.000% 0.000% 100.000% 30.0%
III.5.15.6 Backfilling 10.000% 100.000% 0.000% 100.000% 10.0%
III.5.16 Civil Work for Chlorination System 1.499% 0.000%
III.5.16.1 Excavation Works for foundation 10.000% 100.000% 0.00% 100.000% 100.000%
III.5.16.2 Lean Concrete 10.000% 100.000% 0.000% 100.000% 100.000%
III.5.16.3 Reinforcement Bar 30.000% 98.000% 0.000% 98.000% 96.040%
III.5.16.4 Formwork 10.000% 98.000% 0.000% 98.000% 96.040%
III.5.16.5 Pouring Foundation 30.000% 98.000% 0.000% 98.000% 96.040%
III.5.16.6 Backfilling 10.000% 0.000% 0.000% 0.000% 0.000%
III.5.18 Civil Work for Crane and Hoist Complete 1.499% 1.499%
III.5.18.1 Excavation Works for foundation 10.000% 100.000% 0.000% 100.000% 10.0%
III.5.18.2 Lean Concrete 10.000% 100.000% 0.000% 100.000% 10.0%
III.5.18.3 Reinforcement Bar 30.000% 100.000% 0.000% 100.000% 30.0%
III.5.18.4 Formwork 10.000% 100.000% 0.000% 100.000% 10.0%
III.5.18.5 Pouring Foundation 30.000% 100.000% 0.000% 100.000% 30.0%
III.5.18.6 Backfilling 10.000% 100.000% 0.000% 100.000% 10.0%
III.5.19 Civil Work for Natural Gas System Complete 1.499% 1.499%
III.5.19.1 Excavation Works for foundation 10.000% 100.000% 0.000% 100.000% 10.000%
III.5.19.2 Lean Concrete 10.000% 100.000% 0.000% 100.000% 10.000%
III.5.19.3 Reinforcement Bar 30.000% 100.000% 0.000% 100.000% 30.000%
III.5.19.4 Formwork 10.000% 100.000% 0.000% 100.000% 10.000%
III.5.19.5 Pouring Foundation 30.000% 100.000% 0.000% 100.000% 30.000%
III.5.19.6 Backfilling 10.000% 100.000% 0.000% 100.000% 10.000%
III.5.20 Civil Work for Workshop and Machinery Equipment 1.499% 1.356%
III.5.20.1 Sub Structure 50.000% 50.000%
III.5.20.1.1 Excavation Works for Foundation 10.000% 100.000% 0.000% 100.000% 10.000%
III.5.20.1.2 Lean Concrete 10.000% 100.000% 0.000% 100.000% 10.000%
III.5.20.1.3 Reinforcement Bar (Sub Structure) 30.000% 100.000% 0.000% 100.000% 30.000%
III.5.20.1.4 Formwork 10.000% 100.000% 0.000% 100.000% 10.000%
III.5.20.1.5 Pouring Foundation 30.000% 100.000% 0.000% 100.000% 30.000%
III.5.20.1.6 Backfilling 10.000% 100.000% 0.000% 100.000% 10.000%
III.5.20.2 Structure & Architecture 50.000% 40.443%
III.5.20.2.1 Lean Concrete 5.000% 100.000% 0.000% 100.000% 5.000%
III.5.20.2.2 Reinforcement Bar 15.000% 100.000% 0.000% 100.000% 3.262%
III.5.20.2.3 Formwork 5.000% 100.000% 0.000% 100.000% 3.262%
III.5.20.2.4 Installing anchor bolt 10.000% 100.000% 0.000% 100.000% 3.262%
III.5.20.2.5 Concrete K-300 10.000% 100.000% 0.000% 100.000% 10.000%
III.5.20.2.6 Steel Structure 45.000% 100.000% 0.000% 100.000% 45.000%
III.5.20.2.7 Installing brickwall, Door & Window 5.000% 100.000% 0.000% 100.000% 5.000%
III.5.20.2.8 Painting 5.000% 100.000% 22.000% 122.000% 6.100%
III.5.21 Access Road & Drainage 34.004% 31.354%
III.5.21.1 Access Road 70.000% 65.703%
III.5.21.1.1 Levelling 20.860% 100.000% 0.000% 100.000% 20.860%
III.5.21.1.2 Formwork 7.870% 90.000% 0.000% 90.000% 7.083%
III.5.21.1.3 Reinforcement Bar 14.360% 12.924%
III.5.21.1.3.1 Besi D16 14.765% 90.000% 0.000% 90.000% 13.289%
III.5.21.1.3.2 Besi D25 85.235% 90.000% 0.000% 90.000% 76.711%
III.5.21.1.4 Pouring Concrete 49.510% 93.100% 0.000% 93.100% 46.094%
III.5.21.1.5 Pedestrian 7.500% 92.000% 0.000% 92.000% 6.900%
III.5.21.2 Drainage 30.000% 26.505%
III.5.21.2.1 U-Ditch Fabrication 47.960% 89.400% 0.000% 89.400% 42.876%
III.5.21.2.2 U-Installation 47.960% 87.800% 0.000% 87.800% 42.109%
III.5.21.2.3 Concrete Culvert 4.080% 82.500% 0.000% 82.500% 3.366%
TOTAL ACCESS ROAD & DRAINAGE WORKS
III.5.22 Others Building 8.208% 91.750% 7.531%
III.5.22.1 Perimeter wall 20.000% 97.000% 0.000% 97.000% 19.400%
III.5.22.2 Guard House & Entrance Gate 5.000% 0.000% 0.000% 0.000% 0.000%
III.5.22.3 Mosque 10.000% 10.000%
III.5.22.3.1 Excavation Works for Foundation 5.000% 100.000% 0.000% 100.000% 5.000%
III.5.22.3.2 Lean Concrete 5.000% 100.000% 0.000% 100.000% 5.000%
III.5.22.3.3 Reinforcement Bar 25.000% 25.000%
III.5.22.3.3.1 Besi P8 38.506% 100.000% 0.000% 100.000% 38.506%
III.5.22.3.3.2 Besi D10 21.121% 100.000% 0.000% 100.000% 21.121%
III.5.22.3.3.3 Besi D13 40.374% 100.000% 0.000% 100.000% 40.374%
III.5.22.3.4 Formwork 5.000% 100.000% 0.000% 100.000% 5.000%
III.5.22.3.5 Pouring 25.000% 100.000% 0.000% 100.000% 25.000%
III.5.22.3.6 Backfilling 5.000% 100.000% 0.000% 100.000% 5.000%
III.5.22.3.7 Installing Wall 30.000% 100.000% 0.000% 100.000% 30.000%
III.5.22.4 EAC Building 50.000% 50.000%
III.5.22.4.1 Sub Structure 15.000% 15.000%
III.5.22.4.1.1 Excavation Works for Foundation 10.000% 100.000% 0.000% 100.000% 10.000%
III.5.22.4.1.2 Lean Concrete 10.000% 100.000% 0.000% 100.000% 10.000%
III.5.22.4.1.3 Reinforcement Bar (Sub Structure) 30.000% 100.000% 0.000% 100.000% 30.000%
III.5.22.4.1.4 Formwork 10.000% 100.000% 0.000% 100.000% 10.000%
III.5.22.4.1.5 Pouring Foundation 30.000% 100.000% 0.000% 100.000% 30.000%
III.5.22.4.1.6 Backfilling 10.000% 100.000% 0.000% 100.000% 10.000%
III.5.22.4.2 Structure & Architchture 85.000% 85.000%
III.5.22.4.2.1 Concrete 25.000% 100.000% 0.00% 100.000% 25.000%
III.5.22.4.2.2 Formwork 20.000% 100.000% 0.00% 100.000% 20.000%
III.5.22.4.2.3 Reinforcement Bar 30.000% 100.000% 0.00% 100.000% 30.000%
III.5.22.4.2.4 Brickwall 10.000% 100.000% 0.00% 100.000% 10.000%
III.5.22.4.2.5 Plastering 5.000% 100.000% 0.00% 100.000% 5.000%
III.5.22.4.2.6 Installing door & window 5.000% 100.000% 0.00% 100.000% 5.000%
III.5.22.4.2.7 Painting 5.000% 100.000% 0.00% 100.000% 5.000%
III.5.22.5 Civil Work for Switchyard 8.000% 8.000%
III.5.22.7.1 Foundation Gantry 70.000% 70.000%
III.5.22.7.1.1 Excavation Works for Foundation 15.000% 100.000% 0.000% 100.000% 15.000%
III.5.22.7.1.2 Lean Concrete foundation 5.000% 100.000% 0.000% 100.000% 5.000%
III.5.22.7.1.3 Reinforcement Bar Foundation 30.000% 100.000% 0.000% 100.000% 30.000%
III.5.22.7.1.4 Anchor Bolt Foundation 5.000% 100.000% 0.000% 100.000% 5.000%
III.5.22.7.1.5 Formwork 20.000% 100.000% 0.000% 100.000% 20.000%
III.5.22.7.1.6 Pouring Foundation 25.000% 100.000% 0.000% 100.000% 25.000%
III.5.22.7.2 Cable Trench 30.000% 30.000%
III.5.22.7.2.1 Excavation Works 15.000% 100.000% 0.000% 100.000% 15.000%
III.5.22.7.2.2 Lean Concrete 5.000% 100.000% 0.000% 100.000% 5.000%
III.5.22.7.2.3 Reinforcement Bar 35.000% 100.000% 0.000% 100.000% 35.000%
III.5.22.7.2.5 Formwork 20.000% 100.000% 0.000% 100.000% 20.000%
III.5.22.7.2.6 Pouring Concrete 25.000% 100.000% 0.000% 100.000% 25.000%
III.5.22.9 Slope Protection 3.000% 70.000% 0.000% 70.000% 2.100%
III.5.22.10 Plant Gravel 2.000% 78.500% 0.000% 78.500% 1.570%
III.5.22.11 Plant Grass 2.000% 34.000% 0.000% 34.000% 0.680%