Sei sulla pagina 1di 6

OTe 6927

Design Enhancements for Offshore Platform Fire Systems


R.E. Dailey and R.E. Mayhew, Exxon Co. USA

Copyright 1992, Offshore Technology Conference

This paper was presented at the 24th Annual OTC In Houston, Texas, May 4-7, 1992.

This paper was selected for presentation by the OTC Program Committee following review of information contained in an abstract submitted by the author(s). Contents of the paper,
as presented, have not been reviewed by the Offshore Technology Conference and are subject to correction by the author(s). The material, as presented, does not necessarily reflect
any position of the Offshore Technology Conference or its officers. Permission to copy is restricted to an abstract of not more than 300 words. Illustrations may not be copied. The
abstract should contain conspicuous acknowledgment of where and by whom the paper is presented.

ABSTRACT "Emp1oyees are expected to


utilize provided equipment and
Existing firewater/deluge systems on open Gulf training to protect themselves,
of Mexico type offshore platforms were their fellow employees and, if
evaluated to improve their operation and practical, the facil ity by
reliability, and to reduce maintenance. controll ing a fire in its
Pumps, fi rewater systems and deluge systems incipient stage. The Company
were upgraded to meet performance and does n2i expect employees to
reliability criteria developed from field and fight severe or escalating fires
fire testing as well as survey data. Upgraded or to use equipment for which
systems utilize bronze pumps and valving; they have not been trained."
fi bergl ass and all oy pi pi ng; and a central
manifold design. Deluge nozzle placement The firewater systems provided are typically
changed from impingement spray similar to NFPA fed by auto-start diesel engine driven pumps
15 requirements to area/density spray similar and contain both manual fire equipment (hose
to NFPA 13 requirements and coverage was reels and monitors) and automatic deluge
increased. Principles of material selection (water spray) segments. The deluge is
and nozzle placement are applicable to all provided to both assist manual fire fighting
offshore facilities where reliable automatic and prevent escalation.
fire control is desired.
FIRE PUMPS
INTRODUCTION
Dual, 100% capacity, fire pumps are provided
The size and nature of an offshore firewater except on gas platforms that can be shut down
protection system depends to a large extent on when a pump is out of service. In such cases,
the operator's emergency response philosophy, facility blowdown is an alternative means of
but if a firewater system is employed, common preventing escalation and only one pump is
prob1ems can be encountered. The author's installed. If possible, pumps are located on
company offshore fire response guideline different deck levels to prevent a pool fire
states: from affecting both pumps. A1so, when
possible, at least one of the pumps is located
in or adjacent to the muster or safe area.
Pumps are vertical turbine design driven
through a right angle gear, and ratings are
either 1500 or 2500 gpm at 140 psi cellar deck
level discharge pressure. Size is dependent
on total deluge area, and head-capacity curves
meet NFPA 20 requirements. This means that
References and illustrations at end of paper. end-of-curve performance is 2250 or 3750 gpm

485
2 DESIGN ENHANCEMENTS FOR OFFSHORE PLATFORM FIRE SYSTEMS OTC 6927

at 90 psi which, without hose and monitor use, by an electric submersible jockey pump.
wi 11 cover several del uge zones as will be
explained later. Materials
A review of test and maintenance records Historically, industry fire systems in the
indicated that the average time between Gulf of Mexico were constructed of internally
overhauls was 3 years for the coated cast iron coated carbon steel pipe for sizes 6" and
pumps in general use. A smaller sampling of larger, and galvanized steel pipe for sizes 4"
nickel aluminum bronze pumps was averaging 10 and smaller. Valves 6" and larger were bronze
years between overhauls which coincides with trimmed cast iron gates, while valves 4" and
manufacturer's experience overseas. Nickel smaller were carbon steel body, stainless
a1umi num bronze pump assembl i es cost three steel trim ball type. This combination of
times as much as the cast iron assemblies, but materi a1s stood up very well from external
the longer time between overhauls makes the appearances, but functioning was not as
investment attractive and the greater reliable as desired without high levels of
reliability is a safety bonus. maintenance. Plugging of nozzles with failed
internal coating or marine foul ing was
frequent necessitating frequent flushing. The
FIREWATER SYSTEM cast iron gate valves soon froze in position,
and the ball valves soon leaked necessitating
Conn gurati on frequent replacement. For new platforms and
for retrofits on longer life (10+ years)
Since the mid-1970's, when water depth made existing platforms, we selected 90-10 copper-
separate quarters templates impractical, fire nickel pipe and fittings because of its
systems have been designed as segmented loops resistance to marine fouling. Earlier
just as in gas plants and refineries. Hose retrofi t jobs were all wel ded and fl anged.
reels, monitors and deluge zones were Currently, we are using welded and mechanical
distributed around the loop so that if a grooved fittings as Cu-Ni fl anges are very
portion was damaged it could theoretically be expensive. For retrofit to shorter life
isolated with loss of only 25% of design platforms, we selected Fiberglass Reinforced
capability. A fresh look at this design Pl ast ic (FRP) pi pe. Industry and our own
uncovered several desirable improvements tests indicate that FRP has the required
considering the close confines of a platform. strength and fire resistance when water
For instance, a really serious incident could filled, and it does not support heavy marine
make it difficult to reach the segmenting fouling. All valves are aluminum bronze,
block valves. New and replacement systems angle disc resilient seat butterfly type for
utilize a manifold design (Fig. 1), with the 6-inch and larger and ball type for 4" and
manifold located in or adjacent to the muster smaller. Although our experience with these
area. Where a replacement system could not be selections is just over one year, performance
justified, power actuated loop isolating has met expectations, and overseas affiliates
valves were installed with the control located have had excellent experience with these
in a safe area at or near the muster area. material selections over a number of years.
Manifolds
AUTOMATIC DELUGE SYSTEMS
Manifolds offer several advantages over loop
designs: Area Coverage
• Damaged sections of the system can be Existing deluge systems covered wellbays,
safely isolated headers and diesel fuel storage tanks and were
Fresh water test/flush/treatment is designed for impingement spray per NFPA 15
simpl ified (Fig. 2). Our philosophy for new and upgraded
Del uge control can be manually over- platforms now requires coverage of all
ridden if required hydrocarbon handl i ng areas to guard against
escalation, especially to pipeline areas.
Man i fo1ds are des igned wi th two fi re main Based on both published literature and testing
take-offs (one main each side of platform) to performed at our fire school, we set new rate
feed hoses and monitors so that they can be goals at 0.75 gpm/sq. ft. plan area in
isolated if damaged. Hose reels are arranged wellbays and pipeline areas and 0.25 gpm/sq.
on the mains such that any point can be ft. for all other areas. The platforms were
reached with two hoses. This is intended to divided into deluge zones and the maximum size
allow an upwind fire attack, but it also zone was set at pump design capacity less a
provides redundancy in the event one main monitor nozzle (500 gpm) and a hose line (100
should be lost. Monitors, to the extent that gpm). Nozzle layout was by area/density per
they could be effective, are also installed on NFPA 13 (Fig. 3) as our testing indicated much
the mains. The manifold and manual mains are higher heat removal overall witt. this
kept water filled and pressurized to 50-60 psi arrangement. The nozzles selected yield rates

486
OTC 6927 R. E. DAILEY, R. E. MAYHEW 3

of 0.8-0.9 gpm/sq. ft. in wel 1bays and pressure of 80 psi, nozzles with 3/4" or
pipeline areas and 0.3-0.4 gpm/sq. ft. in all larger orifices, all of the coarse bands are
other areas, depending on the pattern overlap. drawn together and enclose a cone of fine fog.
Thi s behavi or greatly increases wi nd dri ft
The initial reason for investigating the resistance and enhances heat removal also.
change to area coverage was the decision to Testing at our fire school indicated that two
utilize 1/2" minimum orifice nozzles rather 1-1/2" orifice nozzles positioned to deliver
than our 3/8" previous standard. To get 0.8 gpm/sq. ft. into our 20' x 20' mock
complete impingement spray coverage with this wellbay were capable of encapsulating and
size nozzle within the space constraints of an extinguishing a simulated wellhead fire of 12
offshore platform would require huge volumes MMCF/D, the maximum capacity of this
of fi rewater wi th dens ities far above the evolution.
recommended 0.25 gpm/sq. ft. The heat removal
efficiency would also be very low since Hydrauljc Design
flame/water contact would occur only on the
sprayed surface where flame impinged. Another Piping hydraulic design for deluge system
factor considered is the considerable length upgrades was based on keeping velocity below
of smaller piping installed near deck level the erosive velocity of copper-nickel (11
where it could be easily daDlaged. fps). This low velocity results in low
Instrumented wellhead testing and subjective pressure drop so that pressure differences
test i ng on a vessel i ndi cated that overhead between nozzles is negligible. Additionally,
area/density spray removed more heat and design for area/density down spray gave us the
nearly matched impingement spray in equipment opportunity to loop many of the deluge zones
cool ing. Since hydrocarbon fires exist in to further reduce pressure differences. All
space and not on surfaces, filling space deluge zones originate at the manifold where
around equ i pment insures more contact with manual control override enables the personnel
flame for direct contact heat exchange. The to manually select zones to be deluged and to
result of the area coverage design was isolate a zone that may have been damaged in
improved cooling of the fire while still an initial event. Unless the fire pumps are
cooling the equipment and meeting the very large, this water conservation is
mechanical objectives that initiated our essential in delivering design spray to
studies. critical areas. As with the fire mains, our
initial retrofits utilized welded and flanged
Nozzle Selection spools while in later designs mechanical
grooved couplings replace the flanges.
Nozzle selection proved to be both interesting
and challenging. We determined that a 1/2" Material Select jon
minimum orifice, minimum free passage was
necessary to minimize plugging since strainers Material selection for deluge is even more
had proved ineffective with the stringy important than for fire mains if nozzle
material pumped from the Gulf. We knew that plugging is to be avoided. Autopsy of
droplet size would have to be a compromise existing galvanized carbon steel pipe systems
between the optimum for heat removal (300 found heavy, hard scale corrosion in all dry
micron) and wind resistance (600 micron). We pi pi ng. These scale sheets were generated
didn't know that we couldn't simply go to a downstream of system strainers and were large
catalog and find the answers. The fact that and strong enough to plug almost any size
nozzles circulate 300 to 500 cfm air for each nozzle. This scale also resists system
gpm of water delivery also means that they can flushing, so that even conscientious
do some strange things with their theoretical maintenance is no assurance that a few nozzles
patterns. Standard spri nkl er heads seem to might not plug on testing. As with the fire
provide the most uniform pattern performance mains, two materials were selected based on
with varying system pressure; however, their platform remaining life. For short lived
droplet size is always too fine to resist wind platforms, type 316L stainless steel was
drift. Whirl type nozzles produce a very good specified and for longer life platforms, 90-10
compromise droplet size, but their pattern copper nickel was specified. For both
narrows as pressure increases above 50-60 psi materials, a high volume fresh water
(Fig. 4). Spiral impingement nozzles produce test/fl ush system is provided to keep from
an average droplet somewhat finer than wetting equipment and decks with salt water
desirable for wind drift resistance, but their during function testing. This is absolutely
pattern enlarges as pressure increases if air essential for stainless steel systems as
is available to circulate into the pattern residual chlorides would rapidly pit the
(Fig. 5). material. It is also essential that stainless
steel systems be drained completely after the
Full cone spiral impingement nozzles produce fresh water flush. Since it is very difficult
2 or 3 bands of relatively coarse droplets to secure complete drainage in a retrofit
that surround wider bands of relatively fine system, later jobs have employed copper-nickel
droplets. We found that at our system design regardless of platform life expectancy.

487
4 DESIGN ENHANCEMENTS FOR OFFSHORE PLATFORM FIRE SYSTEMS OTC 6927

Incremental installed cost of the copper- corrosion resistant and durable in sea water
nickel was approximately 10% over stainless service and introducing new design
but it will avoid future maintenance or philosophies. Pumps, piping, valves and
replacement that would be necessary if the accessories must all be considered because
system could not be drained. failure of any component will reduce the
effectiveness of the whole system. Although
CQ!lW!l copper-nickel, bronze and FRP are more
expensive than carbon steel, they will perform
Control of deluge was by the same butterfly in this environment to give the expected
valves used manually but with normally open reliability and may even reduce the life cycle
cylinder type valve actuators. The fusible cost of a fire system. Automatic deluge is
plug loops required by API RP 14C (and the very effective in removing the heat from a
MMS) were re-arranged to coincide with the fire to minimize the possibility of
deluge zones, and output was fed to a new escalation. Even if an operator’s emergency
pneumatic control panel for the deluge valves. response plan calls for immediate evacuation
The panel was equipped with a dedicated air in the event of a large fire, the extra time
receiver to hold supply in the event of power purchased by deluge may be well worth the cost
failure in order to ensure that only tripped of a reliable system. System reliability can
deluge valves open. The panel also outputs to be significantly improved with an engineered
the platform control panel to actuate the design considering selection of materials,
platform Emergency Shutdown System (ESD). location of components (pumps, manifold,
control panel), controls logic, and nozzle
type and placement.
CONCIUSION.S

Offshore firewater systems can be improved


through selection of materials that are

W. FIRE MAIN E. FIRE MAIN


ZONE A ZONE B ZONE C ZONE N
.

4,
1. FIREPUMP2
FIREPUMPI

FIRE SYSTEM
MANIFOLD
FIG. 1

488
IMPINGEMENT SPRAY
(WLA-45)

6)

AREA SPRAY

489
40 psi 80 psi

WHIRL NOZZLE
FIG. 4

40 psi
80 psi

SPIRAL IMPINGEMENT
NOZZLE
FIG. 5

Potrebbero piacerti anche