Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
Column
Types of Columns
Columns can be classified bases on its Shape, Slenderness ratio, type of loading and Pattern of
lateral reinforcement.
Short Column [The length is less than the critical buckling length and it fails by shearing.
Intermediate Column
Based on shape
Rectangle
Square
Circular
Polygon
Beams
A beam is a structural member which spans horizontally between supports and carries loads which
act at right angles to the length of the beam. They are small in cross-section compared with their
span. The width and depth of a typical beam are “small” compared with its span. Typically, the
width and depth are less than span/10.
Generally a beam is subjected to two sets of external forces and two types of internal forces. The
external loads are the loads applied to the beam and reactions to the loads from the supports. The
two types of internal force are bending moments and shear forces. The internal shear force and
the internal bending moment can be represented as pairs of forces. The Figure below shows a
Typical Beam with Internal and external forces acting on it.
REINFORCEMENT (R/f)
Introduction
Reinforced concrete is the most commonly used structural material in engineering construction.
Although concrete is strong in resisting compressive stress, it is weak intention. Hence to
withstand tensional stresses, steel is need in concrete. The reinforcement in concrete may be
simple bars or rods bend and tied to a given schedule with stirrups. The nominal diameters of bars
used at site were Y10, Y12, Y16, Y20, Y25 and R6.
Steel is supplied in two basic types.
Bar code
Indication of Reinforcement in Drawings
Engineering drawings is a language to communicate with details. Therefore there is a standard to
indicate reinforcement in drawing such as,
5Y10-001-150:-Which means 5 Number of Tor steel, 10mm Diameter, Bar mark 001, At 150mm
CRS. At bottom face.
By preparing a bar schedule, and arranging them according to the lengths, it will lead to an
economical bar cutting, reduce the bar cutting wastages.
It is easy to manage the reinforcement stock required for identified time duration.
R6 0.222
R10 0.610
T10 0.617
T12 0.888
T16 1.580
T20 2.469
T25 3.858
T32 6.313
It is necessary to be careful about length when preparing bar schedules. In case of bending, bar
length will increased at the bending positions.
Lapping
Lapping is required when a bar isn’t long enough or a joint is required. Bars may be deliberately
left short for constructability and transportation concerns. The preferred method of lapping where
the two bars overlap each other for some minimum distance. This distance is called Lap length.
These two bars are in physical contact and wired together. It does not represent an actual bend in
the bar.
Fig 2: Lapping and cranking detail
Binding Wires
R/f bars are jointed with using wires which is called “binding wires”. Hackers are used to bind
these wires.
Cover Blocks
They were made up of 1:3 ratio of cement mortar. Cover blocks should be immersed in water for
28 days to get the maximum strength.All the beams were checked to ensure adequate cover
blocks are provided to the bottom and sides of the beam reinforcement. Main bars of the columns
were adjusted to ensure the covering requirements before concreting. Stools of correct height
were used to maintain the require gap between top and bottom reinforcement nets and cover
blocks were also provided to bottom reinforcement.
Cover to Reinforcement
Concrete cover for steel bar is much necessary to protect the steel against corrosion
(rusting) and to provide resistance against fire.
For R.C.C. Slab and staircase the cover is 20 mm.
Stirrups
Stirrups will be required at areas of high shear, such as bearing points and below large point
loads. Increasing concrete beam spans, to reduce the need for additional piers, has resulted in the
need for the use of steel stirrups. Concrete beams vary in depth. The deeper the beam, the more
shear capacity. When the depth is not adequate, steel stirrups must be added to increase the
shear capacity of the beam.
These stirrups are usually one piece of steel that is bent into a rectangular shape. The stirrup
typically wraps around the bottom and top bars of the beams. A designer should specify the size,
spacing and location along the length of the beam where the stirrups are required. In my site
specify the stirrup dimensions in our section drawings, so that the stirrup can be manufactured
prior to installation. The installer should be careful to fabricate the stirrup from one piece of steel
and adequately overlap each end.
Stools
Stools are used to separate the top reinforcement mesh and bottom reinforcement mesh.
Dimension of the Stools could be change as requirement. Those should be strength enough to
bear the loads without changing the gap of two layers. 12 mm or 16 mm bars are used to make the
stools.
Fig 5: Stools
Number of bars
Lap lengths
Dimensions of the element thickness of a slab, depth and width of a beam, etc…)
Column Reinforcement
The column reinforcement bars should be stared from the Footing. The upper column
reinforcement bars are cranked at the laps and connected. Special care should be taken in this to
ensure the lap lengths. After erection of main reinforcements, cover blocks were attached to
column reinforcements to maintain the required cover for column reinforcement. Most of Columns
centers were located at intersections of grid lines.
Stirrup spacing
According to the Column reinforcement details drawing the reinforcement detail for a typical
internal Column, from to basement to ground floor is as follows.
Column stirrups were tightened up to beam bottom level and rest is tightened once beam
reinforcement is fabricated. So Bar benders was instructed how to provide the stirrups. Mark the
stirrup spacing from the basement floor level in the Column main bars with a chalk as follow the
detail drawing.
E.g.:
Footing
Size – 1000 x 1000 x 250
Beam Reinforcement
Beam is a horizontal structural member resting on two or more supports. It is used to transfer the
load to the columns.Beam reinforcements are arranged after the construction of beam and slab
formwork.
First the top most reinforcement bars are hung over the beam formwork and then the stirrups are
placed and bound at correct positions. Thereafter the bottom reinforcement bars are placed and
bound to the stirrups. After that the rest of the reinforcement bars and tension bars are inserted
into the cage according to structural drawings. Then cover blocks are fixed to bottom and side
reinforcements before placing the concrete.
Top reinforcement of the beam shall be lapped at the middle of the span of between two
supports. Bottom reinforcement of the beam shall be lapped at the end of the span of the two
supports. Considering the region where the maximum bending movement is existing.
Lapping is did the place which the tension is didn’t act. Normally 2/3 of the length is choosing for
lapping. When lapping top & bottom re-bar, it is better to follow the following method.Otherwise, it
might cause to reduce the concrete covering thickness of the topmost& bottom most slab
reinforcement.
E.g-(Anchorage length 45 d (for top bars),12 d (for bottom bars)) where “d”, “Ø” is diameter of the
Bar.
= 72.5mm
= 827.5 mm
Bar schedule for Beam
Slab Reinforcement
Slab reinforcement is the most important part of the structure. It is important to have an idea on
slab reinforcement detailing. Following basic thing could be studied in drawing on slab
reinforcement detailing.
Distribution bar reinforcement
Small diameter bars, usually at right angles to the main reinforcement, intended to spread a
concentrated load on a slab and to prevent cracking.Standard method used for indicated the slab
top & bottom reinforcement.
First step of the fixing of slab reinforcement was placed the bottom most R/F (B1) of the slab.
Before placing the re-bar, correct spacing given in the detailing drawing were marked by using
piece of choke on the slab formwork. After placed the (B1) R/F then placed the (B2) R/F and
bound both R/F layers together by using binding wire. Then cover blocks for bottom most R/F were
fixed. Finally, Top R/F (T2), Topmost R/F (T1)& distribution bars were placed according to the
drawing and fixed together by using binding wire. Then Stools were fixed to separate the both top
& bottom R/F net as fulfilled the thickness.
Bar schedule for Stiffener column, Sill beam and Lintel beam
Table 5: Bar schedule for Stiffener column, Sill beam and Lintel beam
What do you mean by foundation in a building?
Foundation is the part of structure below plinth level up to the soil. It is in direct contact of soil and
transmits load of super structure to soil. Generally it is below the ground level. If some part of
foundation is above ground level, it is also covered with earth filling. This portion of structure is not
in contact of air, light etc, or to say that it is the hidden part of the structure.
Whenever construction workers begin work on a new building, they must first assess where and
how they will build the foundation.
When engineers design the foundation of a building, they must keep in mind how much the soil
will settle beneath it, as well as how much weight will go on top. If calculated incorrectly,
the foundation may fail and place the entire structure in peril.
Bearing capacity
The bearing capacity of soil is the maximum average contact pressure between the foundation and
the soil which should not produce shear failure in the soil.
Ultimate bearing capacity – is the theoretical maximum pressure which can be supported
without failure;
Allowable bearing capacity-is the ultimate bearing capacity divided by a factor of safety.
Sometimes, on soft soil sites, large settlements may occur under loaded foundations without
actual shear failure occurring; in such cases, the allowable bearing capacity is based on the
maximum allowable settlement.
Reinforcement for footing and column shaft and formwork for footing.
Refilling of earth in the building portion up to the required height according to plinth level
Fig 2:-Procedure for foundation
LOADS ON BUILDINGS-
The occupant load describes the number of square feet allocated to each person within a building.
Dead loads
Vertical loads due to weight of building and any permanent equipment
Dead loads of structural elements cannot be readily determined b/c weight depends on size
which in turn depends on weight to be supported initially weight must be assumed to make
a preliminary calculation, then actual weight can be used for checking the calculation
IBC requires floors in office buildings and others with live loads of 80psf or less here
partition locations are subject to change be designed to support a minimum partition load of
20psf & is considered part of the live load.
SETTLEMENT OF GROUND-
Settlement of a foundation that is caused by seasonal factors is especially noticeable during the
hot dry summer months. Below ground level, depending upon climate and environmental
conditions. The drying of the soils occur because of both evaporation and transpiration (water
being removed because of trees and shrubs). As the soils dry, they tend to consolidate; as they
consolidate, many times, a slab-on-grade foundation settles.
Rankine’s Formula
d=
?-Bearing capacity (safe)
?-Angle of repose
d-Dept
Net loading intensity of pressure coming on the soil should not exceed the safe bearing
capacity.
Foundation should be designed in such a way that settlement to the ground is limited and
uniform under whole of the building to avoid damage to the structure.
Whole design of the foundation, super structure and characteristics of the ground should be
studied to obtain economy in construction work.
Note: For structures being built in colder climates, engineers must consider frost heaves as well.
Frost heaves occur when moisture in the soil freezes, thereby changing the density of the
building’s support. A frost heave can cause damage to the foundation, thereby
compromising the structural integrity of the entire building.
Drier, warmer climates are not entirely exempt from such worries, however; certain soils will
expand and contract when moisture is added or taken away, and engineers must factor in
such movement when considering where and how to lay a foundation.
The length, width and depth of excavation should be checked with the help of center line
and level marked on the buries.
The excavated material/ earth should be dumped at a distance of 1 meter from the edges.
Arrangement of water pump should be made for pumping out rain water.
Any soft/ defective spots should be dug out and be filled with concrete/ hard material
Fig 4–Excavation
Footing
Footings that support walls and isolated pad footings that support concentrated loads. The footings
themselves are usually made of concrete and its wide bases placed directly beneath the load-
bearing beams or walls.
Fig 5–Footing
Transfer Loads – To transfer the live and dead loads of the building to the soil over a large
enough area so that neither the soil nor the building will move.
Resist Frost – In areas where frost occurs, to prevent frost from moving the building
1. Strip foundation–
This is the most common type, it is mainly used where you have strong soil base and non-
waterlogged areas. Most small buildings of just a floor are constructed with this type of
foundation.
Depends on the structural engineers recommendation, the depth of your foundation could
be from 600mm to 1200mm mostly for small scale buildings.
When the soil is excavated, a level at which the concrete will settle evenly is established,
then concrete is poured this may be from 150mm(6”) thick to 450mm(18”) thick depending
also on building after that block is set round the trenches at the center of foundation,the
foundation usually follows the block lines. The blocks are then layed to d.p.c level before
another concrete is poured on top this is the german or oversite concrete. This type seems
to be the cheapest.
This is mostly used when you want to make use of the under of building as parking space
or when the other space is not conducive to have foundation. This columns are thus
isolated and their foundations are referred to as pad.
3. Raft foundation–
Raft foundation is a thick concrete slab reinforced with steel which covers the entire contact area
of the structure like a thick floor. This concrete transfers loads from walls and columns to
the underlying rock or soil. That is laid on a soft ground consisting of an extended layer (soil are
sandy and loose). It is also recommended in waterlogged areas Sometimes area covered by
raft may be greater than the contact area depending on the bearing capacity of the soil
underneath. The reinforcing bars runs normal to each other in both top and bottom layers of
steel reinforcement.
Fig 8-Raft foundation
Combined footing
Combined footing is foundations supported more than one column and useful when its two
columns are so close that single footings cannot be used or is located at or near a property line.
Combined footing is usually support two or three columns not in a row. Combined footings are
used where the bearing areas of closely spaced columns overlap.
Ramp Foundation
Ramps are an important feature in accessing a home or agricultural building. This applies not only
to people who use wheelchairs but also to those who have difficulty climbing stairs, such as people
who have arthritis or hemiplegic and those who use walkers, crutches or canes. To be safe and
most effective, ramps should be built with a few basic guidelines in mind.
While constructed ramp the slope is extremely important because it affects how difficult it is to
travel up and down the ramp. If the slope is too steep, the ramp may be too difficult for someone to
use or may even be unsafe. The 1 to 12 slope should be seen as the steepest slope to be built and
may be too steep for some people.
Pile foundation
The most expensive and the strongest type of foundation, this requires specialist engineering to
do. The soil are bored deep down the earth and filled with concrete to be able to support loads of
multistory building on top. Most skyscrapers are constructed with this foundation type, a
waterlogged area of high building may also require this. It is the costliest hence it is used for high
rise building mostly.
Pier
Pier in building construction, vertical loadbearing member such as an intermediate support for
adjacent ends of two bridge spans. In foundations for large buildings, piers are usually cylindrical
concrete shafts, cast in prepared holes, while in bridges they take the form of caissons, which are
sunk into position. Piers serve the same purpose as piles but are not installed by hammers and, if
based on a stable substrate, will support a greater load than a pile. Especially adapted to large
construction jobs, pier shafts having widths of more than 1.8 m (6 feet) have been excavated to
depths greater.
Grillage foundation-
Stepped Foundation-
On sloping sites the so-called stepped foundation must be used, which is in fact just a special form
of the strip foundation.
Cantilever Foundation-
Cantilever footings are designed to accommodate eccentric loads.
Inverted Arch-