Sei sulla pagina 1di 11

Available online at www.sciencedirect.

com

International Journal of Project Management 30 (2012) 352 – 362


www.elsevier.com/locate/ijproman

The impact of incentive mechanisms on project performance


Xianhai Meng ⁎, Brendan Gallagher
School of Planning, Architecture and Civil Engineering, Queen's University Belfast, David Keir Building, Stranmillis Road, Belfast, BT9 5AG, UK

Received 1 December 2010; received in revised form 18 August 2011; accepted 23 August 2011

Abstract

Contractual incentives have been increasingly practised in construction projects. In this study, a questionnaire survey is carried out in the United
Kingdom (UK) and the Republic of Ireland (ROI) to analyse the relationship between the use of incentives and the performance of a project. The
analysis is made in a comparative way. First of all, four payment methods are compared in terms of their impact on cost performance. Secondly,
incentive projects are compared with non-incentive projects in terms of time and quality performance. Thirdly, both time and quality performances
are compared between the projects with a single incentive and those with multiple incentives. The analysis results provide empirical evidence for
the significant impact of incentive mechanisms on project performance. Subsequent to the questionnaire survey, a case study is conducted to ex-
amine how to appropriately apply incentives in practice, revealing that the use of incentives aligns the contractor's objectives with the client's ex-
pectations in a project and in order to ensure the success of incentive mechanisms the contractor needs to make extra efforts for the enhancement of
project management processes, the creation of collaborative working environments, and the motivation of his staff and workforce.
© 2011 Elsevier Ltd. and IPMA. All rights reserved.

Keywords: Incentive; Disincentive; Performance; Construction project

1. Introduction and innovation (Dulaimi et al., 2005; Wong and Cheung, 2008),
cooperative procurement and relational contracting (Eriksson
Completion on time, on budget and with the specified quality and Westerberg, 2011; Matthews and Howell, 2005), and etc.
is widely recognised as the major objectives of a construction pro- On the other hand, incentive provisions can be used as a con-
ject and time, cost and quality are generally identified as the key tractual strategy with a significant potential to address perfor-
indicators of project success. From the client perspective, it is mance problems (Jaafari, 1996). According to Bubshait (2003),
ideal that a project is completed in minimum time, at minimum clients can provide time incentive for early completion, cost in-
cost, and with the best quality (Arditi et al., 1997). However, it centive for cost saving, quality incentive for zero or minor de-
is often difficult to achieve these major objectives in practice, es- fects, and sometimes safety incentive for complying with
pecially for large and complex projects (Harris et al., 2006). Many stricter safety rules and standards. In addition, different types
construction projects suffer from time delay, cost overrun and of incentives can be combined in order to make improvement
quality defect (Sun and Meng, 2009). So far, a large number of re- in two or more performance areas. The combination of incen-
search efforts have been made to identify various possible solu- tives is often called multiple incentives, which have proven com-
tions to performance problems, according to which project plicated to manage but may be fairly successful (Bower et al.,
performance can be improved by adopting total quality manage- 2002). In recent years, the importance of incentive mechanisms
ment (Arditi and Gunaydin, 1997; Pheng and Teo, 2004), project to project success has received an increasing recognition from
risk management (Baloi and Price, 2003; Kwak and Smith, 2009), construction researchers and practitioners. For example, Love
benchmarking (Love and Smith, 2003; Luu et al., 2008), learning et al. (2011) emphasised that project participants' behaviours
can be aligned through the use of incentives towards a project's
⁎ Corresponding author. performance objectives. Similarly, Rose and Manley (2011) saw
E-mail address: x.meng@qub.ac.uk (X. Meng). the use of incentives as a key means of improving project
0263-7863/$ - see front matter © 2011 Elsevier Ltd. and IPMA. All rights reserved.
doi:10.1016/j.ijproman.2011.08.006
X. Meng, B. Gallagher / International Journal of Project Management 30 (2012) 352–362 353

performance by simulating the motivation to work harder and In order to overcome the limitations within previous re-
smarter in pursuit of high-order performance objectives. searches, a comparative study is undertaken in the UK and ROI.
As mentioned above, existing research efforts mainly con- The research questions in this study concern: (1) whether the
tribute to the wide recognition of the importance of incentive use of incentives has a significant influence on performance im-
mechanisms to project success. Other contributions of existing provement; (2) what incentive approach is more effective; and
research efforts are reflected in the following four aspects: (1) (3) how an incentive mechanism works. This study is charac-
introducing the principle of contractual incentives; (2) estab- terised by (1) analysing the real data of performance outcomes
lishing different types of incentive contracts; (3) providing ref- rather than the respondents' perceptions; (2) investigating the
erential experiences for clients and contractors to practise roles of incentives in improving performance in terms of
contractual incentives; and (4) investigating the perceptions of time, cost and quality; (3) comparing incentive projects with
clients and contractors about the use of incentives. For exam- non-incentive projects; (4) distinguishing a single incentive
ple, Bower et al. (2002) pointed out that the basic principle of from multiple incentives; and (5) exploring the use of incentives
incentive contracting is simply to take advantage of a contrac- combined with disincentives. For time and cost performance,
tor's general objective to maximise his profits by giving him both the certainty of performance and the difference between ac-
the opportunity to make greater profits if he performs the con- tual and target performance are analysed. Similar to time perfor-
tract efficiently, whilst Herten and Peeters (1986), Bower mance, quality performance is also compared between incentive
et al. (2002) and Bubshait (2003) defined time, cost, quality and non-incentive projects and between the projects with a single
and multiple incentives as the common types of incentive con- incentive and those with multiple incentives. In doing so, this
tracts in construction projects. On the other hand, Jaraiedi et al. study addresses the problem identified from existing literature
(1995) developed a set of guidelines for the use of incentives in on quality incentive. Unlike previous studies using either a quan-
highway construction contracts, and Rose and Manley (2010) titative or a qualitative method, this research adopts a combina-
provided practical recommendations for clients who design tion of questionnaire survey and case study. Based on empirical
and implement financial incentives in their projects. In addi- information in breadth and depth, it provides an important oppor-
tion, Arditi and Yasamis (1998) and Bubshait (2003) compared tunity to look at the application of incentive mechanisms in more
the perceptions of clients and contractors regarding the use of detail and in a clearer way. The findings of this study are
incentives. According to Bubshait (2003), for example, approx- expected to benefit to both industrial practitioners and academ-
imately 64.0% of clients in the survey agreed that incentive pro- ic researchers in designing and implementing suitable contrac-
visions should be included at the bidding stage whilst 60.0% of tual incentives to pursue and achieve project success.
contractors believed that incentive provisions should be includ-
ed at the construction stage. 2. Incentive mechanisms
Although previous studies contribute to a good understand-
ing of incentive knowledge and experience and a wide recogni- As discussed above, there are different types of incentives in
tion of the importance of incentive mechanisms to project construction projects, e.g. time, cost and quality incentives.
success, there are obvious limitations within these studies. These incentives can be used individually or collectively. In ad-
First of all, most previous studies, such as Bubshait (2003), dition to incentives, disincentives are often seen in practice, e.g.
Ling et al. (2006), Chapman and Ward (2008) and Rose and time disincentive for late completion of a project (Shr and
Manley (2011), have not provided any empirical data for the Chen, 2004). Similarly, cost disincentive can be set for cost
performance outcomes of incentive projects. Therefore, it is overrun, and quality disincentive can be set for major defects.
not possible to measure the real effect of the use of incentives. Obviously, an incentive refers to a reward whilst a disincentive
Secondly, amongst the limited studies that link financial incen- represents a penalty (Bubshait, 2003). If completion on time, on
tives to real performance, most of them address only one per- budget and with the specified quality is considered as normal
formance area. For example, Arditi et al. (1997) only paid performance, the purpose of an incentive/disincentive scheme
attention to the effect of time incentive on time performance is to motivate the contractor for excellent performance or demo-
whilst Berends (2000) focused on the effect of a particular pay- tivate the contractor for poor performance. Incentives and disin-
ment method on cost performance. Therefore, there is a lack of centives can be used separately. On the other hand, it is possible
systematic research on the impact of incentive mechanisms on for disincentives to accompany incentives (Arditi et al., 1997;
project performance in all three performance areas. Thirdly, a Bubshait, 2003).
lack of comparison between incentive and non-incentive pro- By comparison, time and cost incentives have received
jects and a lack of comparison between a single incentive and much more research attention than quality incentive. For exam-
multiple incentives within almost all previous studies under- ple, Shr and Chen (2004) analysed how to set maximum time
mine their value. Finally, another limitation of previous studies incentive for highway construction projects whilst Chan et al.
is that only a few of them such as Walker et al. (2002) and (2010) evaluated how to achieve better performance through
Bower et al. (2002) have given a light touch on quality incen- target cost contract in an underground railway station modifica-
tive when focusing their research on something else, e.g. pro- tion project. On the other hand, Jaafari (1996) twinned time and
ject alliancing and other types of incentives. Therefore, there cost incentives in marine construction projects. Time incentive
is a barrier to a penetrating understanding of the link between is generally paid to the contractor in the form of a bonus, e.g. a
quality incentive and quality performance. certain amount for each day of early completion (Arditi et al.,
354 X. Meng, B. Gallagher / International Journal of Project Management 30 (2012) 352–362

1997). Similarly, quality incentive is also paid through a bonus. take into account the long-term needs of end users. On the
Instead of a bonus, cost saving is often split between the client whole, it is more related to quality performance although some-
and the contractor in terms of a sharing ratio (Al-Harbi, 1998; times delivery on time or overall performance is the basis of
Broome and Perry, 2002). The role of cost incentive greatly de- payment.
pends on the selection of payment methods because one payment Existing literature mainly focuses on time and cost incen-
method may involve cost incentive but another may not. This will tives. Research efforts for quality incentive are quite limited
be discussed in detail in the following. and there are no research efforts specific to quality-only incen-
The role of payment methods has been highlighted by many tive. In the current vision, Walker et al. (2002) may be the only
construction researchers. For example, Broome and Perry example in which both incentive and disincentive for quality
(2002) provided seven examples of using target cost contracts performance were specified together with incentives and/or dis-
and discussed the sharing ratios for cost under and over runs. incentives for time and cost performance when comparing pro-
Generally, there are four common types of payment methods: ject alliancing with project partnering in the National Museum
fixed price, cost plus fee, target cost, and payment based on of Australia Project. On the other hand, quality disincentive
final outcome. Fixed price and cost plus fee are widely recog- was briefly introduced by Bower et al. (2002) through several
nised as two basic and simple payment methods (Chapman case studies, in which the central theme was cost incentive
and Ward, 2003). With a fixed price contract, the client pays and disincentive. The lack of sufficient evidence for quality in-
the contractor a specified fixed amount for the entire scope of centive results in some questions, e.g. (1) is it possible to sepa-
work and the risk of overspending is carried by the contractor rate quality incentive from time and cost incentives in practice?
(Al-Harbi, 1998; Berends, 2000). For this reason, the fixed and (2) does quality incentive has a significant effect on quality
price contract can be considered as a cost disincentive. Some- performance improvement? These questions will be answered
times, a cost incentive is incorporated into the fixed price con- in this research based on the analysis of empirical data collected
tract to form a fixed price incentive contract (Rubin et al., 1999; from questionnaire survey and case study.
Ward and Chapman, 1995). The purpose of the incorporation is
to motivate the contactor to complete the project under budget
so that the contactor can share cost saving with the client. A 3. Research methods
cost plus fee contract is mainly divided into cost plus fixed
fee contract and cost plus percentage fee contract (Chappell The exploratory nature of this study requires a combination
et al., 2001). When a cost plus fee contract is used, the contrac- of quantitative and qualitative methodologies. In this study,
tor is reimbursed for all the expenses incurred from his work to- the research methods include literature review, questionnaire
gether with a fee (Al-Harbi, 1998; Broome and Perry, 2002). survey and case study. First of all, the literature on incentives
According to Bubshait (2003), this contract should be limited and performance was reviewed in the context of construction
to low cost projects, emergency work and short duration pro- projects. Based on the identification of strengths and weak-
jects because it lacks both an incentive for cost reduction and nesses within previous studies, the critical review helped to dis-
a disincentive for cost increase. cover the need for the current research. Subsequent to the
The weakness of a cost plus fee contract can be overcome to literature review, a preliminary questionnaire was developed.
some extent by introducing a target cost concept (Twort and As a pilot study, the preliminary questionnaire was reviewed
Rees, 2004). In recent years, the target cost contract has by some industrial experts, whose feedbacks contributed to a
gained increasing popularity. A main reason is that it provides refinement of the questionnaire. The main purpose of this
gain/pain sharing and therefore facilitates collaborative working study is to analyse the relationship between incentive mecha-
(Chan et al., 2010; Walker et al., 2002). With this payment meth- nisms and project performance in construction, e.g. whether
od, a target cost is estimated and mutually agreed by the two con- an incentive project is significantly better than a non-incentive
tracting parties and meanwhile a sharing formula is established project in terms of project performance, and whether a single
(Bower et al., 2002; Perry and Barnes, 2000). A target fee is incentive or multiple incentives are significantly more effective
paid to the contractor if the actual cost equals the target cost. for performance improvement. As a typical quantitative meth-
According to Twort and Rees (2004), the contractor shares a pro- od, a questionnaire survey was adopted as the main instrument
portion of cost underrun as a reward if his expenditure is less than to achieve the purpose. This is because it is easy to get informa-
the target whilst he has to bear a proportion of cost overrun if he tion from many people and its results are generalisable to the
expends more than the target. That is to say, both saving and survey population (Gillham, 2000; Presser et al., 2004). In
overspending are shared between the client and the contractor order to make comparative analysis, the questionnaire survey
according to the formula. Sometimes, a guaranteed maximum targeted both the projects in which incentives were established
price is added in the contract as a cost disincentive (Bower et between clients and main contractors and the projects in which
al., 2002; Chan et al., 2011). In addition to the target cost contract, there were no incentive mechanisms. Both building and civil
payment based on final outcome is another payment method pro- engineering projects were investigated. The questionnaire sur-
posed by the Office of Government Commerce (OGC). With this vey also covered both public and private sector projects
payment method, the contractor is paid on the basis of final out- throughout the UK and ROI. Each questionnaire response was
comes such as the achievement of expected standard of reliability specific to a completed project in which performance outcomes
and capability (OGC, 2003). Therefore, the contractor should were measurable.
X. Meng, B. Gallagher / International Journal of Project Management 30 (2012) 352–362 355

The questionnaire was divided into five sections. Section A so, it was possible for the researchers to understand who had
was designed to collect the information on the respondent orga- responded. As a result of the questionnaire survey, a total of
nisation, project region, project type, and project sector. Section 60 completed questionnaires were returned with a response
B contained two questions, concerning the adoption of partner- rate of 22.2%. The response rates of client, contractor, consul-
ing and payment method. Section C was related to the presence tant and other groups were 21.1%, 20.0%, 23.0% and 35.0%
of incentives, type of incentives, choice of a single incentive or respectively.
multiple incentives, and components of multiple incentives. A The statistical analysis of questionnaire results helps to ex-
respondent's perception on the influence of incentives on pro- plore the relationship between incentive mechanisms and pro-
ject management and working relationship was rated in Section ject performance. Even if a statistical relationship is identified,
D according to a five-point scale (1 = Strongly agree; 2 = Agree; however, it is still not very clear about how an incentive mech-
3 = Neither agree nor disagree; 4 = Disagree; and 5 = Strongly anism works in construction practice. This is why Tang et al.
disagree). Section E was used to explore the characteristics of (2008) recommended that incentive mechanisms should be
time, cost and quality performance in a completed project. linked not only to the final outcomes but also to the whole pro-
“Time certainty” was measured in terms of three options ject management process. Similarly, Rose and Manley (2011)
(1 = Early; 2 = On time; and 3 = Delayed). Similarly, three op- argued that offering an incentive does not assure project motiva-
tions were provided for “Cost certainty” (1 = Under budget; tion and performance automatically and the impact of any incen-
2 = On budget; and 3 = Over budget). In addition to “Time cer- tive will be compromised if clients ignore the importance of
tainty” and “Cost certainty”, a respondent was asked to provide working relationship with contractors. Although project man-
the information of project duration and project budget. If pro- agement process and working relationship were briefly consid-
ject completion was not on time and/or not on budget, the re- ered in the questionnaire, a need was further identified to
spondent further needed to answer how many months the explore how to ensure the success of incentive mechanisms dur-
project was completed early or delayed (“Time advance” or ing a project. For this reason, the questionnaire survey was fol-
“Time delay”), and/or how much the actual cost was saved or lowed by a case study, which is a suitable method for the
overspent (“Cost saving” or “Cost overrun”). On the other research need.
hand, “Defect” considered the condition of a completed project According to Punch (2005), properly conducted case studies
with respect to quality performance by using a five-point scale will make a valuable contribution to the research especially in
(1 = Defect free; 2 = Some defects with no significant impact on situations where existing knowledge is shallow, fragmentary
the client; 3 = Some defects with some impact on the client; or incomplete. The contribution is mainly reflected in three dif-
4 = Major defects with major impact on the client; and 5 = Totally ferent ways. First of all, it provides an important opportunity to
defective). learn from the study of a particular case in its own right. Sec-
Given that many organisations have good connections to the ondly, only in-depth case studies can give a clear understanding
Internet, the use of email and online survey is especially advan- of the key aspects of a new research area. Thirdly, the case
tageous in terms of convenience and access to many people study can be combined with other research methods to make
(Gray, 2009). For this reason, the formal questionnaire was a contribution to knowledge. In this research, the case study
sent to 270 construction practitioners through email. In this was conducted to examine the role of incentive mechanisms
study, the questionnaire respondents should be familiar with in performance improvement. To achieve this, three experts in-
project management and performance measurement in con- volved in a civil engineering project adopting multiple incen-
struction projects. On the other hand, the questionnaire survey tives were interviewed, who represented client, contractor and
needed both the respondents who had experienced incentive designer organisations respectively. As a complement to the
contracts and the respondents who had not such experience questionnaire survey, the case study made it possible to get a
for the purpose of comparing incentive with non-incentive pro- better and deeper understanding of incentive mechanisms in
jects. The 270 potential respondents were selected from expert construction practice, e.g. how to establish incentive mecha-
databases and other available sources. In order to ensure a rep- nisms appropriately in a project, and how to convert the use
resentative sample, the potential respondents were selected of incentives into the achievement of excellent performance.
carefully through the following criteria: (1) having sufficient
experience in project management; (2) holding key manage-
ment positions such as senior managers, project managers and 4. Analysis of questionnaire results
contract managers; (3) covering different regions of the UK
such as England, Scotland, Northern Ireland and Wales as Based on the data collected from the questionnaire survey, a
well as the ROI; and (4) working in different types of construc- quantitative analysis is made in a comparative way, based on
tion organisations such as project clients, main contractors, pro- which it is clear to see the influence of different payment methods
ject management consultants, and other types of organisations. on cost performance, the difference between incentive and non-
The majority of clients were local authorities or government incentive projects in terms of time and quality performance, and
agencies. Other types of organisations mainly referred to archi- the difference of time and quality performance between a single
tectural firms. A respondent had a flexibility of either filling in and multiple incentives. In addition, the statistical analysis pro-
the attached questionnaire or answering the online question- vides quantitative evidence for the successful application of in-
naire by clicking the web link provided in the email. In doing centive mechanisms in construction projects.
356 X. Meng, B. Gallagher / International Journal of Project Management 30 (2012) 352–362

4.1. Application of incentive mechanisms sector and partnering adoption. Although time incentive is not sig-
nificantly associated with project type and project sector, it is ob-
Four types of incentives are reported in the survey: time, cost, vious that the use of time incentive is more commonly used for
quality and safety. Safety incentive is only found in one civil en- civil engineering projects and the projects with partnering ar-
gineering project together with time and quality incentives. This is rangements compared to building projects and the projects with-
because contractors have to comply with the latest safety regula- out partnering arrangements. On the other hand, a significant
tions and generally there is no need for additional incentive to en- association is found at the 0.004 level between the use of time in-
sure safety performance. Cost incentive is usually incorporated centive and the sector of project. Time incentive is included in
into payment methods. Therefore, cost performance in a project most of public sector projects but is excluded in most of private
is mainly affected by selecting the most appropriate payment sector projects. A probable reason is that public sector projects
method, which will be discussed in detail later in this section. In- are not as effective as private sector projects, and therefore public
deed, disincentives are found in some surveyed projects either sector clients have to highlight the importance of value for money.
separately or combined with incentives. In order to simplify the In order to achieve this, they tend to adopt incentive mechanisms
research, however, disincentives usually do not distinguish from as their contractual strategies. In addition, time constraints for
incentives in the questionnaire analysis. As a result, time incentive public sector projects may be another reason.
covers both time incentive and time disincentive. Similarly, qual- Similar to time incentive, quality incentive is not significantly
ity incentive covers both quality incentive and quality disincen- associated with project type and partnering adoption although
tive. In the questionnaire analysis, disincentives distinguish from quality incentive is more commonly seen in civil engineering pro-
incentives only when discussing the influence of different pay- jects and the projects with partnering arrangements than in build-
ment methods on cost performance. ing projects and the projects without partnering arrangements.
According to early studies such as Herten and Peeters (1986), Unlike time incentive, the use of quality incentive in public sector
incentive contracts had only limited use in construction projects. projects is quite similar to that in private sector projects, and
By comparison, the use of incentives has been greatly increased therefore quality incentive is not significantly associated with
in today's construction practice. As shown in Table 1, time-only project sector. By comparison, 65.2% of public sector projects
incentive is applied in 12 (20.0% of) surveyed projects whilst in in the survey involve time incentive whilst only 26.1% of such
13 (21.7% of) surveyed projects time incentive is combined projects involve quality incentive, implying that time objective
with other incentives. In total, 25 (41.7% of) surveyed projects may have a higher priority than quality objective in public sector
adopt time incentive. On the other hand, quality-only incentive projects. There are different levels of statistical significance
exists in six (10.0% of) surveyed projects whilst in seven (Yung and Yip, 2010). Generally, the result of a statistical test
(11.7% of) surveyed projects there is a combination of quality is significant if P-value is less than 0.05. If P-value is more
and other incentives. Compared to other incentives especially than 0.05 but less than 0.10, the statistics can be considered to
quality and safety incentives, time incentive is in common use. be marginally significant (Oo et al., 2008). There is no statistical
The finding illustrates that timely completion is usually the main significance if P-value is more than 0.10. The Chi-square test
concern of a project client because it is directly related to return shows that payment methods are not significantly associated
on investment. As for the use of different payment methods and with both project type and project sector. On the other hand,
their impact on cost certainty, please see Table 3. there is a marginally significant association between payment
The 60 completed questionnaires are returned from different methods and partnering adoption at the 0.053 level. For example,
regions throughout the UK such as England, Scotland, Northern 58.8% of the projects using the target cost contract adopt partner-
Ireland and Wales as well as the ROI. The responses cover both ing whilst there is no partnering in 54.5% of the projects using the
civil engineering and building projects, both public sector and pri- cost plus fee contract.
vate sector projects, and both the projects without partnering and
those with partnering (project partnering or strategic partnering). 4.2. Impact of payment methods on cost performance
As seen in Table 2, comparisons are made between time incentive
and no time incentive projects in terms of project type, project Four payment methods are reported in the survey: fixed price
contract is reported in 20 (33.3% of) surveyed projects; target cost

Table 1
Distribution of various incentives in surveyed projects. Table 2
Use of time incentive in terms of three project characteristics.
Incentive Frequency
Time No time Chi-square test
Time Time incentive A single time incentive 12 (20.0%)
incentive incentive P-value
Time-involved multiple incentives 13 (21.7%)
n = 25 n = 35
No time incentive 35 (58.3%)
Quality Quality incentive A single quality incentive 6 (10.0%) Project type Civil engineering 19 20 0.131
Quality-involved multiple incentives 7 (11.7%) Building 6 15
No quality incentive 47 (78.3%) Project sector Public sector 15 8 0.004
Safety Safety incentive A single safety incentive 0 (0.0%) Private sector 10 27
Safety-involved multiple incentives 1 (1.7%) Adoption Partnering 17 18 0.199
No safety incentive 59 (98.3%) of partnering Non-partnering 8 17
X. Meng, B. Gallagher / International Journal of Project Management 30 (2012) 352–362 357

contract in 17 (28.3% of) surveyed projects; payment based on suggest that overemphasis on high quality may be compromised
final outcome contract in 12 (20.0% of) surveyed projects; and by additional payment. For this reason, it is important for a client
cost plus fee contract in 11 (18.3% of) surveyed projects. As to clearly identify the objectives and appropriately provide the re-
shown in Table 3, in terms of “Cost certainty” the fixed price con- quirements at the beginning of a project.
tract performs better than the other three payment methods. In The percent frequency of “Cost certainty” describes the like-
35.0% of the surveyed projects using the fixed price contract, lihood of a project completed under budget, on budget, or over
the actual cost is under budget. On the other hand, 30.0% of budget. If a project is under budget or over budget, “Percentage
such projects are over budget. Compared to the other three pay- cost saving” is defined as the ratio of cost saving to project bud-
ment methods, the fixed price contract is most likely to save get whilst “Percentage cost overrun” is defined as the ratio of
cost whilst it is least likely to overspend. In addition, the fixed cost overrun to project budget. The definition of these two vari-
price contract represents the largest percentage (35.0%) of the ables makes it possible to compare the extent of cost saving and
projects completed on budget. With a fixed price contract, the cli- cost overrun between different projects. Similar to the percent
ent has a maximum cost certainty. According to the Chi-square frequency of under budget completion and the percent frequen-
test, “Cost certainty” is marginally significantly associated with cy of over budget completion, as shown in Table 4, “Percentage
payment methods at the 0.095 level. It is evident that the likeli- cost saving” decreases and “Percentage cost overrun” increases
hood of under budget completion decreases and the likelihood step by step from the fixed price contract to the cost plus fee
of over budget completion increases gradually when moving contract. The only abnormality is 5.68% for “Percentage cost
from the fixed price contract to the cost plus fee contract. Placing overrun” under payment based on final outcome. The finding
fixed price and cost plus fee at the two extremes of the spectrum is supports the ranking of payment methods as follows: fixed
because under the fixed price contract the client pays a certain price, target cost, and cost plus fee. On the other hand, payment
amount for the contractor's work and the risk of overspending based on final outcome has more effect on quality performance
is completely taken by the contractor. On the other hand, cost is than on cost performance because amongst the surveyed pro-
reimbursed in full under the cost plus fee contract and therefore jects under payment based on final outcome 41.7% are defect
the contractor has no motivation to save cost. For this reason, a free, 25.0% have some defects with no significant impact,
client should be very careful for the choice of a cost plus fee con- 16.7% have some defects with some impact, 16.7% have
tract due to its high cost uncertainty. The finding is consistent major defects with major impact, and none is totally defective.
with previous studies such as Bubshait (2003). Unlike Bubshait If one-way analysis of variance (ANOVA) is further made, no
(2003), the finding in this study is based on the analysis of real significant differences are found at the 0.050 level for the
cost performance data rather than the analysis of respondents' means of “Percentage cost saving” and “Percentage cost over-
perceptions. run” across four payment method groups.
The analysis result presented in Table 3 also shows that the Most existing studies such as Al-Harbi (1998) have com-
target cost contract performs relatively well in terms of “Cost pared the payment methods in terms of which party is responsi-
certainty” and is ranked second. The surveyed projects that ble for taking the risk of overspending. As a matter of fact, the
adopt the target cost contract are 29.4% under budget, 23.5% payment methods can also be analysed from a perspective of in-
on budget, and 47.1% over budget. The finding indicates that centives or disincentives. For example, the fixed price contract
most of such projects are within budget (under budget or on mainly represents cost disincentive whilst the target cost con-
budget), which mainly results from the contractor's motive tract is more characterised by cost incentive. Cost incentive en-
for sharing cost saving or at least ensuring the target fee. How- courages saving. Compared to cost incentive, cost disincentive
ever, loss sharing may put a lower pressure on the contractor's discourages overspending and may be more effective for cost
cost control. As a result, a higher risk of overspending exists in control in practice. If a disincentive is combined with an incen-
such projects compared to those using the fixed price contract. tive, the joint effect should be more remarkable, e.g. more saving
Of the projects in which payment is determined by the final out- and less overspending. This is the reason for the development of
come, 75.0% are over budget and the risk of overspending is fixed price incentive and guaranteed maximum price contracts.
quite high, which is only 6.8% less than 81.8%, the percent fre- As discussed above, a major advantage of the target cost contract
quency of over budget completion for the projects under the is gain/pain sharing. However, gain/pain sharing is a double-edge
cost plus fee contract. As discussed above, payment based on sword. On one hand, it has become a common understanding that
final outcome depends on the achievement of expected standards gain/pain sharing is a motivator of collaborative working. On the
such as reliability and capability. Little or no emphasis has been other hand, the possibility of loss sharing to some extent weakens
placed on cost performance. The finding provides evidence to a contractor's awareness of cost control if the contractor is not

Table 3
Cost certainty under different payment methods.
Fixed price Target cost Payment based on final outcome Cost plus fee Chi-square test
n = 20 n = 17 n = 12 n = 11 P-value
Under budget 7 (35.0%) 5 (29.4%) 1 (8.3%) 1 (9.1%) 0.095
On budget 7 (35.0%) 4 (23.5%) 2 (16.7%) 1 (9.1%)
Over budget 6 (30.0%) 8 (47.1%) 9 (75.0%) 9 (81.8%)
358 X. Meng, B. Gallagher / International Journal of Project Management 30 (2012) 352–362

Table 4
Percentage cost performance under different payment methods.
Fixed price Target cost Payment based on final outcome Cost plus fee ANOVA
n = 20 n = 17 n = 12 n = 11
F-statistics P-value
Percentage cost saving 2.97% 2.34% 2.00% 0.50% 0.104 0.956
Percentage cost overrun 1.60% 1.72% 5.68% 3.79% 2.447 0.085

mature enough. As for the cost plus fee contract, both incentive for time incentive projects is greater than that for no time incen-
and disincentive do not exist. Unsurprisingly, it ranks last tive projects whilst the mean of “Percentage time delay” for time
amongst the payment methods in terms of cost performance. incentive projects is smaller than that for no time incentive pro-
jects. In terms of the extent of time advance or time delay, time
incentive projects are also found to perform better than no time
4.3. Relationship between time incentive and time performance incentive projects. Therefore, it is appropriate to conclude that
the use of time incentive not only leads to a higher likelihood
As mentioned above, time incentive are employed in 25 of early completion but also results in a greater extent of time ad-
(41.7% of) surveyed projects whilst a lack of time incentive is vance. On the other hand, both the likelihood of late completion
seen in 35 (58.3% of) surveyed projects. Of the projects with and the extent of time delay can be reduced if time incentive is
time incentive, 40.0% are completed early, 32.0% are on established in a construction project.
time, and 28.0% are delayed (Table 5). On the other hand, the Table 7 provides a comparison of “Time certainty” between
projects without time incentive are 5.7% completed early, the projects with a single time incentive and those with both
51.4% on time, and 42.9% delayed. By comparison, the pro- time and other incentives. Of the projects with a single time in-
jects with time incentive are more likely to be completed centive, 66.7% are completed early, 25.0% are on time, and
early whilst they are less likely to be delayed. For the projects 8.3% are delayed. On the other hand, the projects with both
without time incentive, it is difficult to achieve early comple- time and other incentives are 15.4% completed early, 38.5%
tion whilst it is easy to suffer late completion. Since there is on time, and 46.2% delayed. The Chi-square test reveals that
no time incentive, the time objective in such projects is to com- there is a significant association at the 0.022 level between
plete on time. This is why on time completion is more common “Time certainty” and the selection of a single time or time-in-
in such projects compared to those with time incentive. The volved multiple incentives. The finding indicates that in terms
Chi-square test demonstrates a significant association at the of “Time certainty” a single time incentive performs signifi-
0.005 level between “Time certainty” and time incentive. cantly better than time-involved multiple incentives. This is be-
Therefore, it can be concluded that time incentive has a signif- cause pursuing multiple objectives at the same time and with
icant impact on time performance. In other words, the use of the same importance is really a distraction for the performance
time incentive significantly contributes to the improvement of improvement efforts. Therefore, it is more appropriate to focus
time performance in a construction project. If a project needs on a single time incentive rather than look after multiple incen-
to be completed as early as possible, time incentive is identified tives if time objective is the primary concern of a project. Even
as an effective way of ensuring project success. if two or more objectives need to be considered at the same
Similar to “Percentage cost saving” for under budget comple- time, the identification of their priorities is extremely important
tion and “Percentage cost overrun” for over budget completion, and a trade-off is needed between different incentives.
“Percentage time advance” can be defined as the ratio of time ad-
vance to project duration for early completed projects whilst
“Percentage time delay” can be defined as the ratio of time 4.4. Relationship between quality incentive and quality
delay to project duration for delayed projects. The independent performance
sample T test is used to analyse the difference of “Percentage
time advance” and “Percentage time delay” between time incen- In the survey, a single quality incentive is reported in six
tive projects and no time incentive projects (see Table 6). Al- (10.0% of) surveyed projects, half of which are paid based on
though there are no significant differences between the two final outcome. Again, payment based on final outcome here is
groups, it is obvious that the mean of “Percentage time advance”
Table 6
Percentage time performance between time incentive and no time incentive projects.
Table 5 Time incentive No time incentive Independent sample
Time certainty comparison between time incentive and no time incentive projects. n = 25 n = 35 T test
Time incentive No time incentive Chi-square test t-statistics P-value
n = 25 n = 35 P-value
Percentage time 9.41% 8.25% 0.303 0.768
Early 10 (40.0%) 2 (5.7%) 0.005 advance
On time 8 (32.0%) 18 (51.4%) Percentage time 10.77% 14.91% 1.168 0.256
Delayed 7 (28.0%) 15 (42.9%) delay
X. Meng, B. Gallagher / International Journal of Project Management 30 (2012) 352–362 359

Table 7 with some impact and major defects with major impact can be
Time certainty comparison between a single time and time-involved multiple merged into “Defect impact”. If the Chi-square test is used be-
incentives.
tween quality/no quality incentive and defect/no defect impact,
A single time incentive Time-involved Chi-square test a significant association is found at the 0.019 level. Therefore,
n = 12 multiple incentives P-value
n = 13
the adoption of quality incentive proves to have a significant ef-
fect on the reduction in various defects. In addition to the em-
Early 8 (66.7%) 2 (15.4%) 0.022
phasis on total quality management, the role of quality
On time 3 (25.0%) 5 (38.5%)
Delayed 1 (8.3%) 6 (46.2%) incentive should not be ignored when pursuing zero or minor
defects in a construction project.
Of the six projects with a single quality incentive, 33.3% are
used as a tool of ensuring quality performance. Compared to a defect free, and 66.7% have some defects with no significant
single time incentive, the use of a single quality incentive is impact. Of the seven projects with quality-involved multiple in-
halved. On the other hand, there are seven (11.7% of) surveyed centives, 28.6% are defect free and 71.4% have some defects
projects with both quality and other incentives, in which the use with no significant impact. For both types of surveyed projects,
of payment based on final outcome is not found. 42.9% of such there are no responses to some defects with some impact, major
projects use quality and time incentives; 28.6% use quality and defects with major impact, and totally defective. According to
cost incentives; 14.3% use quality, time and cost incentives; the Chi-square test, there is no significant association between
and 14.3% use quality, time and safety incentives. Obviously, “Defect” and a single quality/quality-involved multiple incen-
quality incentive is more combined with time incentive in prac- tives (P-value = 0.853). In spite of that, it is evident that in
tice. Compared to time-involved multiple incentives, the use of terms of “Defect” a single quality incentive performs somewhat
quality-involved multiple incentives is nearly halved. The com- better than quality-involved multiple incentives. This is similar
parisons between quality incentive and time incentive in both to the finding aforementioned, which indicates that in terms of
single and multiple may explain why quality incentive specific “Time certainty” a single time incentive performs significantly
studies are quite limited within existing literature. better than time-involved multiple incentives. The two findings
Of the 13 surveyed projects (21.7%) with quality incentive suggest that using a single incentive is relatively simple and
in both single and multiple, as shown in Table 8, 30.8% are de- more effective because it concentrates on a particular perfor-
fect free and 69.2% have some defects with no significant im- mance area. However, it does not necessarily mean that multiple
pact. On the other hand, there are no signs of some defects incentives cannot be pursued in construction practice. As for
with some impact, major defects with major impact, and totally whether multiple incentives can be achieved successfully,
defective. The finding can be viewed as strong evidence for the please see case study.
contribution of quality incentive to quality performance im-
provement. Unlike the 13 projects with any quality incentive, 4.5. Impact of incentives on project management and working
some defects with some impact and major defects with major relationship
impact appear in 47 projects without any quality incentive,
which represent 78.3% of the survey sample. Although 25.5% Contractual incentives are based the contractor's perfor-
of such projects are defect free and 42.6% have some defects mance. Incentives can be considered as the input of a project.
with no significant impact, some defects with some impact On the other hand, project performance in terms of time, cost
and major defects with major impact account for 23.4% and and quality is the output of a project. During a project, there
8.5% in such projects respectively. By comparison, the projects are two key aspects: one is the project management processes
without quality incentive have to face greater risks of defects and the other is the working relationship between the client
and rework. Since both the projects with quality incentive and and the contractor. The former is a hard measure whilst the lat-
those without quality incentive are not subject to totally defec- ter is a soft measure. These two key elements link project input
tive, defect free and some defects with no significant impact with project output. Based on the experience in using contractu-
can be merged into “No defect impact” whilst some defects al incentives, 36 respondents have answered the questions

Table 8
Comparisons between quality and no quality incentive and between a single quality and quality-involved multiple incentives.
Quality incentive No quality incentive
n = 13 n = 47
A single quality incentive Quality-involved multiple incentives Total
n=6 n=7 n = 13
Defect free 2 (33.3%) 2 (28.6%) 4 (30.8%) 12 (25.5%)
Some defects with no significant impact 4 (66.7%) 5 (71.4%) 9 (69.2%) 20 (42.6%)
Some defects with some impact 0 (0.0%) 0 (0.0%) 0 (0.0%) 11 (23.4%)
Major defects with major impact 0 (0.0%) 0 (0.0%) 0 (0.0%) 4 (8.5%)
Totally defective 0 (0.0%) 0 (0.0%) 0 (0.0%) 0 (0.0%)
360 X. Meng, B. Gallagher / International Journal of Project Management 30 (2012) 352–362

regarding the influence of incentives on the effectiveness of sector project in which the client's funding was limited. The client
project management and relationship management. As seen in pursued value for money and also sought certainty of cost. For
Table 9, the majority of respondents either strongly agree or this reason, the target cost contract suited the requirements best.
agree that incentives have an important influence on both project The client believed that they would benefit more from cost saving
management and working relationship. By comparison, incen- than the Design and Build contractor. All three interviewees rea-
tives are believed to have more influence on project management lised the importance of establishing an accurate target cost. In
than on working relationship. Although there are a small number this project, the initial target cost was agreed when forming the
of negative voices, no one strongly disagrees with the influence Design and Build contract. It was possible for the target cost to
of incentives on project management and working relationship. be adjusted at a later stage. For example, the final target cost
The respondents' perceptions reflect the fact that the use of incen- was reached through value engineering during the design process,
tives enhances the contractors' awareness of performance im- which was 5% lower than the initial target cost.
provement, which in turn leads to much greater emphasis on The incentives/disincentives to time, quality and environ-
project management processes and working environments. Effec- mental performance were established through the negotiation
tive project management and collaborative working provide a between the client and the selected Design and Build contractor
solid basis for achieving excellent performance. after tender competition. According to the client interviewee,
this arrangement meant that they could lower the tender price
5. Case study and negotiate the incentive provisions once the Design and
Build contractor was selected. During the negotiation, both
The case study described the design and construction of an parties discussed the probabilities of potential risks and ana-
18.2 km section of a standard national road in the ROI. The dura- lysed their impact on each party so as to appropriately define
tion of the project was 22 months, and the value of the contract the rewards/penalties in terms of monetary value. In order to
was €81,000,000. As a county council, the client in this project maintain a good relationship with the contractor and encourage
decided to adopt the Design and Build approach. A joint venture the contractor to improve performance, the client had to balance
between construction company A and civil engineering company the incentives with the disincentives. A common understanding
B was awarded the Design and Build contract. The task of design amongst the three interviewees was that incentives/disincen-
was subcontracted to consulting company C. A standard form of tives had a significant impact on the effectiveness of project
contract by the International Federation of Consulting Engineers management processes. The interviewee from the contractor
(FIDIC) and a target cost payment method was chosen in the pro- stated that they took full advantage of management techniques
ject. On the other hand, multiple incentives were established, in- such as critical path analysis (CPA) in order to respond to time
cluding both rewards and penalties. A penalty was set if late incentive. The contractor also selected management staff care-
completion took place. A bonus was expected if the project was fully so that they were competent enough. In addition, the con-
completed earlier than the target date. Similarly, bonuses and tractor brought in a six day week with which bonus would be
penalties were designed to ensure pollution from construction in passed down to workers on construction site. All these efforts
the nearby river under a certain level and the avoidance of any provided the contractor with more opportunities for early com-
major defects. The use of target cost contract received a cost sav- pletion of the project.
ing of €500,000. As a result of using time incentive, the project The client required that defects should be controlled at a
was completed two months ahead of the schedule. minimum level. For this reason, a quality incentive/disincentive
Three experts involved in this project were interviewed. The was adopted in this project. A defect liability period was incor-
interviewee from the client organisation was a senior manager. porated into the contract, according to which the contractor still
The roles of interviewees from the Design and Build contractor had to pay the cost of rework after the defect liability period if
and the design subcontractor were site manager and senior engi- there were any avoidable defects. From the contractor perspec-
neer respectively. They provided their perceptions on the success- tive, quality control had a high priority and therefore increased
ful application of incentive mechanisms and their impact on attention was paid to the elimination of any major defects. The
performance improvement. The consensus was that the target use of incentives/disincentives led to the identification and es-
cost contract provided a gain/pain sharing scheme and it played tablishment of common goals and objectives, which made it
an important role in encouraging cost reduction efforts. According possible for both parties to work collaboratively together. Dur-
to the interviewee from the client perspective, this was a public ing the project, there were no claims, conflicts and disputes be-
tween the parties, which could be viewed as evidence for a good
Table 9 working relationship. Based on the use of multiple incentives,
Influence of incentives on project management and working relationship. the project had achieved a remarkable success. The client was
Influence on project Influence on working satisfied with early completion, cost saving, no major defects,
management relationship and environmental protection. On the other hand, the contractor
Strongly agree 17 (47.2%) 10 (27.8%) received incentive payment. The excellent overall performance
Agree 16 (44.4%) 11 (30.6%) also helped the contractor to earn a high reputation and therefore
Neither agree nor disagree 2 (5.6%) 12 (33.3%) could be viewed as a recognition reward. Based on the cooper-
Disagree 1 (2.8%) 3 (8.3%) ative experience in the project, the client intended to establish
Strongly disagree – –
a long-term business relationship with the contractor.
X. Meng, B. Gallagher / International Journal of Project Management 30 (2012) 352–362 361

The case study is a complement to the questionnaire survey. cost contributes to the improvement of cost performance; and (3)
Compared to the findings from the questionnaire survey, the zero or minor defects can be achieved through the use of quality
analysis of case study provides further evidence for the use of incentive as well as payment based on final outcome.
incentives in construction practice, which mainly include: Every research has its limitations. This study is not exceptional.
A major limitation of this study is the small sample size of ques-
• In addition to time, cost, quality and perhaps safety incen- tionnaire, which is partly due to the current economic climate. Fur-
tives, it is also possible to use environmental incentive in a ther research may be conducted to collect more empirical data so
construction project; that greater reliability will be provided for the results of data anal-
• Compared to a single incentive, the use of multiple incentives ysis. For example, cost incentive is only found in three surveyed
is complicated to manage and therefore becomes a challenge projects using the fixed price contract. For this reason, the fixed
to project participants, in spite of which the use of multiple in- price incentive contract is not considered separately in this study.
centives makes it possible to improve the overall performance If more empirical data can be collected, it is possible to distinguish
of a project if project participants can make extra efforts; the fixed price incentive contract from the fixed price contract and
• The combination of incentives and disincentives can be used make more accurate comparison of cost performance amongst dif-
not only for cost performance but also for time, quality and ferent payment methods. If more empirical data can be collected, it
environmental performance, which may have dual effects on is also possible to distinguish incentives from disincentives. When
a contractor's performance; incentives are combined with disincentives in practice, a balance
• It is more appropriate to prepare incentive mechanisms care- should be kept between them. However, how to define an optimal
fully through the negotiation between the client and the con- balance is a challenge in practice. For this reason, there is a need for
tractor in a project rather than specify them solely by the further research in this particular filed. In addition, further inves-
client because the identification of mutual benefits is ex- tigation is recommended for the appropriate balance of different
tremely important to the success of incentive mechanisms; performance objectives when multiple incentives are adopted in
• In order to ensure the success of incentive mechanisms, espe- construction projects.
cially for multiple incentives, the contractor in an incentive
project needs to enhance project management processes and References
develop good working relationships with the client and other
project participants, in addition to which attention should be Al-Harbi, K.M.A., 1998. Sharing fractions in cost-plus-incentive-fee contracts.
paid by the contractor to the motivation of his staff members International Journal of Project Management 16 (2), 73–80.
and workers; and Arditi, D., Gunaydin, H.M., 1997. Total quality management in the construction
process. International Journal of Project Management 15 (4), 235–243.
• The success of incentive mechanisms in a project can help to Arditi, D., Yasamis, F., 1998. Incentive/disincentive contracts: perceptions of
achieve a win–win result, which means that the client may owners and contractors. Journal of Construction Engineering and Manage-
benefit from value for money whilst the contractor may ben- ment 124 (5), 361–373.
efit from financial rewards and further business opportuni- Arditi, D., Khisty, J., Yasamis, F., 1997. Incentive/disincentive provisions in
ties due to client satisfaction. highway contracts. Journal of Construction Engineering and Management
123 (3), 302–307.
Baloi, D., Price, A.D.F., 2003. Modelling global risk factors affecting construction
6. Conclusions cost performance. International Journal of Project Management 21 (4), 261–269.
Berends, T.C., 2000. Cost plus incentive fee contracting: experiences and struc-
Based on a questionnaire survey in quantitative and a case turing. International Journal of Project Management 18 (3), 165–171.
Bower, D., Ashby, G., Gerald, K., Smyk, W., 2002. Incentive mechanisms for
study in qualitative, this research provides empirical evidence to
project success. Journal of Management in Engineering 18 (1), 37–43.
establish a link between incentives and performance in construc- Broome, J., Perry, J., 2002. How practitioners set share fractions in target cost
tion projects. On the whole, the embrace of incentives proves to contracts. International Journal of Project Management 20 (1), 59–66.
play a driving role in encouraging best practice and ensuring pro- Bubshait, A.A., 2003. Incentive/disincentive contracts and its effects on indus-
ject success. The main findings include: (1) the use of incentives is trial projects. International Journal of Project Management 21 (1), 63–70.
a trigger of aligning the objectives of different project parties and Chan, D.W.M., Lam, P.T.I., Chan, A.P.C., 2010. Achieving better performance
through target cost contracts: the tale of an underground railway station
devoting special efforts to significant performance improvement; modification project. Facilities 28 (5/6), 261–277.
(2) incentives should be used along with disincentives in order Chan, D.W.M., Chan, A.P.C., Lam, P.T.I., Wong, J.M.W., 2011. An empirical
to have a more positive effect on project performance; (3) multiple survey of the motives and benefits of adopting guaranteed maximum price
incentives may help to achieve an overall improvement of project and target cost contracts in construction. International Journal of Project
Management 29 (5), 577–590.
performance whilst a single incentive may be more effective in a
Chapman, C., Ward, S., 2003. Project Risk Management: Processes, Tech-
certain performance area; and (4) the contractor in an incentive niques and Insights, Second Edition. John Wiley and Sons, Chichester.
project needs to make both internal and external efforts, amongst Chapman, C., Ward, S., 2008. Developing and implementing a balanced incen-
which project management enhancement and staff motivation tive and risk sharing contract. Construction Management and Economics 26
are internal whilst inter-organisational relationship development (6), 659–669.
is external. In terms of time, cost and quality performance, it is Chappell, D., Marshall, D., Powell-Smith, V., Cavender, S., 2001. Building
Contract Dictionary. Blackwell, Oxford.
possible to draw the following conclusions: (1) time incentive is Dulaimi, M.F., Nepal, M.P., Park, M., 2005. A hierarchical structural model of
in common use due to the importance of time objective; (2) the ap- assessing innovation and project performance. Construction Management
propriate use of payment methods such as fixed price and target and Economics 23 (6), 565–577.
362 X. Meng, B. Gallagher / International Journal of Project Management 30 (2012) 352–362

Eriksson, P.E., Westerberg, M., 2011. Effects of cooperative procurement pro- Pheng, L.S., Teo, J.A., 2004. Implementing total quality management. Journal
cedures on construction project performance: a conceptual framework. In- of Management in Engineering 20 (1), 8–15.
ternational Journal of Project Management 29 (2), 197–208. Presser, S., Rothgeb, J.M., Couper, M.P., Lessler, J.T., Martin, E., Martin, J.,
Gillham, B., 2000. Developing a Questionnaire. Continuum, London. Singer, E., 2004. Methods for Testing and Evaluating Survey Question-
Gray, D.E., 2009. Doing Research in the Real World, Second Edition. SAGE, naires. Wiley-Interscience, Hoboken, New Jersey.
London. Punch, K.F., 2005. Introduction to Social Research: Quantitative and Qualita-
Harris, F., McCaffer, R., Edum-Fotwe, F., 2006. Modern Construction Manage- tive Approaches, Second Edition. SAGE, London.
ment, Six Edition. Blackwell, Oxford. Rose, T., Manley, K., 2010. Client recommendations for financial incentives on
Herten, H.J., Peeters, W.A.R., 1986. Incentive contracting as a project manage- construction projects. Engineering Construction and Architectural Manage-
ment tool. International Journal of Project Management 4 (1), 34–39. ment 17 (3), 252–267.
Jaafari, A., 1996. Twinning time and cost in incentive-based contracts. Journal Rose, T., Manley, K., 2011. Motivation toward financial incentive goals on
of Management in Engineering 12 (4), 62–72. construction projects. Journal of Business Research 64 (7), 765–773.
Jaraiedi, M., Plummer, R.W., Aber, M.S., 1995. Incentives/disincentives guide- Rubin, R.A., Fairweather, V., Guy, S.D., 1999. Construction Claims: Preven-
lines for highway construction contracts. Journal of Construction Engineer- tion and Resolution, Third Edition. John Wiley and Sons, New York.
ing and Management 121 (1), 112–120. Shr, J.F., Chen, W.T., 2004. Setting maximum incentive for incentive/disincen-
Kwak, Y.H., Smith, B.M., 2009. Managing risks in mega defense acquisition tive contracts for highway projects. Journal of Construction Engineering
projects: performance, policy, and opportunities. International Journal of and Management 130 (1), 84–93.
Project Management 27 (8), 812–820. Sun, M., Meng, X., 2009. Taxonomy for change causes and effects in construc-
Ling, F.Y.Y., R'ahman, M.M., Ng, T.L., 2006. Incorporating contractual incen- tion projects. International Journal of Project Management 27 (6), 560–572.
tives to facilitate relational contracting. Journal of Professional Issues in En- Tang, W., Qiang, M., Duffield, C.F., Young, D.M., Lu, Y., 2008. Incentives in
gineering Education and Practice 132 (1), 57–66. the Chinese construction industry. Journal of Construction Engineering and
Love, P.E.D., Smith, J., 2003. Benchmarking, benchaction and benchlearning: Management 134 (7), 457–467.
rework mitigation in projects. Journal of Management in Engineering 19 Twort, A.C., Rees, J.G., 2004. Civil Engineering Project Management, Fourth
(4), 147–159. Edition. Butterworth-Heinemann, Oxford.
Love, P.E.D., Davis, P.R., Chevis, R., Edwards, D.J., 2011. Risk/reward com- Walker, D.H.T., Hampson, K., Peters, R., 2002. Project alliancing vs project
pensation model for civil engineering infrastructure alliance projects. Jour- partnering: a case study of the Australian National Museum Project. Supply
nal of Construction Engineering and Management 137 (2), 127–136. Chain Management: An International Journal 7 (2), 83–91.
Luu, V.T., Kim, S.Y., Huynh, T.A., 2008. Improving project management per- Ward, S.C., Chapman, C.B., 1995. Evaluating fixed price incentive contracts.
formance of large contractors using benchmarking approach. International International Journal of Management Science 23 (1), 49–62.
Journal of Project Management 26 (7), 758–769. Wong, P.S.P., Cheung, S.O., 2008. An analysis of the relationship between
Matthews, O., Howell, G.A., 2005. Integrated project delivery: an example of learning behaviour and performance improvement of contracting organiza-
relational contracting. Lean Construction Journal 2 (1), 46–61. tions. International Journal of Project Management 26 (2), 112–123.
Office of Government Commerce, 2003. Achieving Excellence in Construction: Yung, P., Yip, B., 2010. Construction quality in China during transition: a re-
Procurement and Contract Strategies. OGC, London. view of literature and empirical examination. International Journal of Pro-
Oo, B.L., Drew, D.S., Lo, H.P., 2008. A comparison of contractors' decision to ject Management 28 (1), 79–91.
bid behaviour according to different market environments. International
Journal of Project Management 26 (4), 439–447.
Perry, J.G., Barnes, M., 2000. Target cost contracts: an analysis of the interplay be-
tween fee, target, share and price. Engineering Construction and Architectural
Management 7 (2), 202–208.

Potrebbero piacerti anche