Sei sulla pagina 1di 4

CONSTRUCTION WORK –

STEEL ERECTION
INFORMATION SHEET
This Information Sheet provides advice on crane operation. Workers must be trained and
managing risks associated with carrying out competent including holding the appropriate high
steel erection work including: risk work licence and instructed in the use of
control measures to manage the hazards and
 design and planning, and risks of steel erection work.
 hazards such as working at height, falling Further information is in the Information Sheet:
objects, steel structure collapse and High risk work licensing for dogging and
operating powered plant. Information sheet: Workplace induction for
construction workplaces.
What is steel erection work?
Steel erection work includes constructing, What do I need to do?
altering, repairing, maintaining, demolishing The work health and safety laws require that
and dismantling a steel structure. workers be consulted and given the necessary
Steel erection work includes erecting metal information, training, instruction and supervision
structures by joining together steel beams, to minimise the risks of steel erection work.
columns and surfaces to create a metal A focus on planning and completing detailed
skeleton. designs will help to ensure safety for workers
Further information is in the Cranes guidance at each stage of the steel erection process.
material.
Design and planning
When does steel erection become high Time spent at the design stage will minimise
risk construction work? work involving potentially dangerous onsite
Steel erection work can be high risk construction remedial work. It can also help to prevent
work when it involves any of the following, for structural instability including progressive
example: collapse and other hazards during erection.

 a risk of a person falling more than two There are two distinct phases of design—
metres1 structural design and the design for handling,
transportation and erection of the individual
 structural alterations or repairs requiring members and the structure.
temporary support to prevent collapse
Table 1 Roles and responsibilities
 work carried out in or near a shaft or trench
deeper than 1.5 metres
Roles Responsibility
 work carried out on or near energised
electrical installations or services, or Structural Ensures shop drawings comply
design with the structural design before
 an area where there is any movement
engineer steel members are fabricated.
of powered mobile plant.
Documents the erection sequence
A safe work method statement (SWMS) must
and provides it to the client.
be prepared for high risk construction work.
During the design considers:
Further information on SWMS is in the Code of
Practice: Construction work and the Information  the effect of the erection
Sheet: SWMS for high risk construction work. sequence on the stability
Steel erection work requires specialised skills of the structure
and qualifications such as dogging, rigging and
 safe access and working
places including anchorage
1
points for fall arrest systems
In South Australia the fall height limit for high
risk construction work is three metres.

978-1-76028-597-5 [PDF]
978-1-76028-598-2 [DOCX]
 training and qualification of workers
Roles Responsibility
 an emergency management plan, and
 the ease of connections for
components such as landing  access to the structure.
cleats
The person conducting a business or
 safe handling storing and undertaking should provide information to
transport of components contractors and sub-contractors on project
including providing details planning and the erection sequence including
of lifting points, and risk management procedures. The method of
erection should be regularly reviewed and
 all materials, for example updated to maintain safety by the structural
grades of steel and welding design engineer.
comply with standards
specified in the design. Further information is in the Code of Practice:
Safe design of structures.
Fabricator Ensures the accurate detailing
and manufacture of the steelwork What are the main hazards and their
according to the shop drawings. control measures?
Ensures steel members: Instability and collapse of the steel structure can
be a major hazard causing workers to fall or be
 are identifiable for the struck or crushed by steel beams or the steel
sequence of erection and structure.
fit together correctly, and
Other hazards include:
 will be supported and tied to
prevent movement during  falling from heights
loading or unloading and
 being hit by falling objects
transport.
 eye injuries from flying metal splinters
Erector Obtains the erection sequence
documentation.  back and spinal column injury from lifting
and moving heavy loads
Prepares the method of erection
according to the drawings.  exposure to very high noise levels, and

Provides a site plan with detailed  electric shock from touching live electric
information on the location and wires or from working with portable power
coverage of cranes, workers, tools.
unloading points and storage
areas, access to work areas Falls
and criteria for safety. The risk of falls must be managed using the
Considers the stability most effective control measures that are
requirements of all items of the reasonably practicable, in accordance with the
structure. hierarchy of control. If a single control measure
is not enough, use a combination of control
Considers the suitability of ground measures.
conditions for the safe movement
of mobile plant. Avoid the need to work at height by constructing
as much of the steelwork as possible (such as
modules or frames) at ground level or from
Consultation erected floor slabs or decks in the structure.
Consulting workers throughout the construction Alternatively, reducing the amount of time spent
process about the hazards, risks and control on working on the steel structure is the best
measures will help prevent injuries. means of minimising falls. For example:
Planning should also include consultation  where possible release the lifting sling or
between the structural design engineer, device from floor level by using long slings,
fabricator and erector on: remote release shackles or other suitable
 the structural design of the building devices, and

 plant and equipment to be used

Information Sheet: Construction work – Steel erection January 2016 Page 2 of 4


 inspect and test as much as possible at an alternative site-specific sequential
ground level. erection procedure
If working at height cannot be avoided, then the  verifying the footing concrete has reached
risk of falls can be minimised by using work the specified strength before erecting
platforms and elevating work platforms (EWPs) columns and checking fittings for supporting
to prevent falls. columns are adequate for the structural
capacity of the erection conditions
Further information on falls is in the Code of
Practice: Managing the risk of falls at  verifying the stability of the structure at the
workplaces and the Code of Practice: end of each work day, when fastenings may
Preventing falls in housing construction. be incomplete, and during strong winds
 seeking approval from the erection designer
Falling objects
to stop work at unscheduled points when the
Control measures to prevent injuries or death structure has not been completed to the
caused from being struck by falling objects specifications of the erection design, and
include, for example:
 obtaining written approval from the erection
 passing bolts and other equipment engineer before loads are placed on the
structure.
 using lifting beams to position members
to ensure the stability of the member
Plant
 limiting access to overhead work by setting
Plant used in steel erection such as cranes used
up exclusion zones
to lift loads and vehicles used to load, unload
 preventing loads from being lifted or and transport steel require specific control
transported over people or amenities measures.
 ensuring only a rigger or dogger slings loads Examples of control measures to prevent
and where appropriate fix taglines injuries from vehicles include:

 using perimeter screens, guardrails  clearly sequencing the loading and marking
including toe-boards and wire mesh, safety every steel member before loading
nets, cantilever work platforms, scaffolding  keeping the vehicle still until the steel is
with protective material and lanyards to secured
secure tools and equipment
 preventing movement of steel by supporting
 using approved bolt bags or baskets at all and securing it until it is ready to lift
times to prevent loose bolts or tools injuring
workers below, and to prevent slips and trips  inspecting the load to ensure the steel has
on loose bolts and tools left on the steel not shifted and could destabilise the vehicle
work, and
 monitoring the stability of the load regularly
 setting up a fully decked platform under all during unloading and if there is instability,
rigging work. ensuring the steel is individually restrained
and the loading configuration checked to
Collapse of the structure avoid the vehicle becoming unstable
In addition to planning at the design stage,  lifting loads in a level manner rather than
control measures to avoid the collapse of the vertically or on an angle
steel structure during erection include:
 securing loads to prevent inside lengths
 making sure all beams are secured before of steel from falling out of the load, and
releasing slings and all bolted connections
 using fall protection for workers and doggers
are effective to stabilise the structure
on the truck.
 adhering to design specifications, or where To avoid being struck by cranes or other
this is not possible seeking further advice
powered mobile plant the erector should:
from the designer
 ensure exclusion zones are in place
 starting erection in a nominated braced bay
so the building can be plumbed and made  check the location of any excavations,
self-supporting to further support the erected underground services and the proximity
steelwork. If this is not possible, ensure the of overhead electric lines
erection engineer is consulted on developing

Information Sheet: Construction work – Steel erection January 2016 Page 3 of 4


 check the ground capacity for supporting
loads
 have emergency procedures in place
 check weather conditions, and
 avoid lifting loads over people.
Further information is in the Code of Practice:
Managing the risks of plant in the workplace.

Crane operations
Cranes require safe systems and methods of
work, with different cranes being fit for different
purposes. For example, use articulating truck
type cranes for positioning smaller or lighter
pieces of steel, larger mobile cranes to position
heavier components requiring further reach, and
tower cranes for high rise steel construction.
Further guidance is in Cranes guidance material.

Erecting steel components


To ensure the safe erection of steel
components, the person conducting a business
or undertaking should comply with the
manufacturer’s or designer’s instructions.

Electricity
Working at heights and near electricity is a
hazard for workers. It may be appropriate to
have the electricity supply to the site isolated.
Exclusion zones for working near incoming
service lines and overhead power lines must
be maintained at all times.
Further information is in the General guide for
working in the vicinity of overhead and
underground electric lines.

Further information
For further information see the Code of Practice:
Construction work and the Safe Work Australia
website www.swa.gov.au.

Information Sheet: Construction work – Steel erection January 2016 Page 4 of 4

Potrebbero piacerti anche