Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
oleh
Ir. Abd Rahman Salleh
Bahagian Jambatan,
Cawangan Kejuruteraan Awam, Struktur & Jambatan
INTRODUCTION TO
BRIDGE
CONSTRUCTION
1. Construction Materials
i) Concrete
ii) Steel
iii) Masonry
iv) Timber
1
Why Bridges Need to be Built ?
Bridges need to be provided to carry right of way
across a natural or artificial obstacle such as a river,
canal, water course, ravines or another road or
another railway or connecting an island.
2. Structural System
i Simply Supported
ii Continuous
iii Cantilever
2
iv. Arch
v. Truss
vii. Frame
viii Suspension
ix Culvert
3. Deck Types
3
Bridge Terminology
The first step in understanding the principles &
processes of bridge construction is to know the basic
bridge terminology.
According to Departmental Standard BD 37/01”Loads
for Highway Bridges”, components of a bridge is
categorized into :-
i. Superstructure - in a bridge, that part of the structure
which is supported by the piers & abutments.
ii. Substructure - in a bridge, the wing walls & the piers,
towers & abutments that support the superstructure.
iii. Foundation - that part of substructure in direct contact
with, & transmitting load to, the ground.
Supervision of Bridge Construction 10
4
Supervision of Bridge Construction 13
Abutment
Abutments are part of the substructure that form the
terminal ends of the bridge & support the end spans.
Typical types of abutments are full heights, stub or
semi stub.
Full height abutment - cantilever abutment that
extends from the underpass grade line to the grade
line of the overpass roadway
Stub abutment - short abutments at the top of an
embankment or slope.
Semi-stub abutment - size between full height & stub
abutment
5
Retaining Wall
Bank Seat
Pile Bents
Approach Slab
A reinforced concrete slab used at the approaches of
a bridge to prevent settlement of the approach
pavement.
Pier
A vertical structure that supports bridge
superstructure. Piers transfer forces from the
superstructure to the foundations.
Piers allow the total length of the bridge to be
divided into viable span lengths
Selection of piers dependent upon flow of water &
bearing capacity of soil.
6
Those commonly found are :-
i. Wall type
Foundation
Deep foundation is commonly used such as :
- prestressed spun piles
- bored piles
- micro piles
- H- steel piles
- steel pipe piles
A bridge can also be founded on shallow foundation
provided that the underlying soil strata near ground
surface is a sound bed rock layer i.e spread
foundation, caisson.
Precast r.c piles may be used for pedestrian bridges
7
Type of Beams & girder
Bulb-T- Beam
Y-Beam
Prestressing
Application of tensile forces to the steel tendons
after the segments are in place. These forces allow
the span to carry the desired loads.
Tendon
Steel strands used for post tensioning.
Falsework
Structural system to support the vertical and horizontal
loads from forms, reinforcing steel, concrete, structural
steel, loads from placement operations & other related
loads.
Deck
The load bearing floor of a bridge which carries &
spreads the vehicular traffic to the main beams.
Usually bridge deck is constructed by cast-in-situ
reinforced concrete.
The deck must be constructed according to grade so
that surface water run-off efficiently drains through
water down pipe.
8
Diaphragm
Diaphragms are used as cross-braces between the
main structural members and are also part of the
superstructure.
Bearings
These are supports on a bridge pier, which carry the
weight of the bridge & control the movements at the
bridge supports, including the temperature expansion
& contraction.
They may be metal rockers, rollers or slides or merely
rubber or laminated rubber (Rubber with steel plates
glued into it).
Supervision of Bridge Construction 25
9
Pad bearing
Bearing strip
Laminated
bearing
Expansion Joints
These are provided to accommodate the translations
due to possible shrinkage & expansions due to
temperature changes.
Expansion joints are installed at deck slab in between
its span.
Type of expansion joints :
i. Asphaltic plug joint
ii. Compression seal joint
iii. Nosing
iv. Mechanical finger/comb joint
Mechanical type
Supervision of Bridge Construction 30
10
Spans & Span Length
Spans are the main terms when referring to bridge
design & construction.
A bridge is made up one or more spans. A span is a
segment of a bridge that crosses from one
substructure unit to the next, from abutment to
abutment, from abutment to pier, from pier to pier,
or from pier to abutment.
Span length refers to either the length of any
individual span within the structure or to the total
bridge length. Span lengths are considered as the
distance between centerlines of bearing from one
substructure unit to the next.
Supervision of Bridge Construction 31
Mainspan
The center or primary span of the bridge over the
river, typically the longest span of the bridge.
11
High Performance Concrete
Concrete meeting special combinations of
performance & uniformity requirements that cannot
always be achieved using conventional constituents &
normal mixing, placing & curing practices resulting in
longer structural life.
Deck Surfacing
Normally top of the deck is overlaid by a layer of 50-
60mm thick wearing course to give a comfort riding
quality & as water proving to the deck surface.
12
Method of construction must be fully understand to
avoid errors that may happen during construction &
may lead to serious consequences.
Quality control must be in-place efficiently in order
to produce high quality of bridges & lead to low cost
of maintenance.
Supervision of
Bridge Construction
13
Scope of works for the construction of bridge :-
a) Site clearance
b) Setting out
c) Temporary works
d) Excavation & earthworks
e) Bridge construction
- foundation
- sub-structures
- super-structures
Schematic diagram of
construction sequence
14
Prior construction of bridge the following relevant
matters should be taken :-
- Approval of temporary bridge, temporary crossing &
staging, coffer dam, formwork, beams erection
system.
- Calculation, shop drawings & method statements of
the above must be endorsed by the Professional
Engineer.
- Inspection of casting yard.
-Inspection of casting factory.
-Inspection of concrete batching plant.
-Site/accredited laboratory.
Supervision of Bridge Construction 43
15
After the contract is awarded, the first job is to
prepare the land for road / bridge construction
(ground clearing, setting out…).
The plots are then marked out with the layout of the
R.O.W. This is known as setting out which is an
essential step before proceeding to the next phase.
The setting out is a contractor's responsibility but
errors can result to serious problems in
constructing the bridge.
16
HODT/Designer must be consulted for further advise
on the following :
- redesign of affected beams if its need to be
changed
- position of bearings
- capacity of piles
- dimension of end diaphragm
- gap between end of beam & ballast wall
17
iv. Possibility of inadequate free board height
v. The horizontal alignment of bridge structure &
approach road may be affected.
- possibility of encroaching private lot & requires
additional land acquisition
vi. Horizontal & vertical alignment may not matching
the road alignments.
18
Temporary Works
Temporary Crossing
Detailed drawings of the temporary crossing as
specified in the Scope of Work required for the
execution & maintenance of the work need to be
submitted by the contractor for the approval.
The drawings must be submitted with the calculation
& description as necessary.
A competent & experienced professional engineer
must sign all submissions.
If the project involves upgrading or replacing the
existing bridge, the first stage is to divert the
affected road comprises of temporary bridge.
19
Works involve on water requires temporary crossing as
an access for the construction works.
Contractor should get the approval from JPS before
constructing temporary crossing, staging & cofferdam
Where bridge is located at wider river mouth or water
course, barges or pontoons are used for transporting
resources & may serve as working platform.
Temporary staging is also constructed to provide a
working platform for piling & piers works. This
temporary staging will extend from the temporary
crossing to around foundation location or cofferdam.
Temporary crossing
20
Temporary Works
61
Temporary Works
temporary
crossing
staging
Temporary Works
Piling machine
rests on
staging
21
Cofferdam
On completion of staging, temporary cofferdam will
be constructed in the location of each proposed
bridge pier.
Cofferdams constructed to allow dry foundation
installation.
The dimensions of the cofferdam will be slightly
larger than the dimensions of the pile cap to allow
the pile cap to be constructed within.
Cofferdam should be safety designed & constructed &
be made as water tight as it is necessary for the
proper performance of the work which must be done
inside.
Supervision of Bridge Construction 64
Temporary Works
22
Temporary Works
Paras air
Kerangka Sangga
Cerucuk keping
Pengedap konkrit
Pumping
of water
Piling Works
23
Matters that required attention during piling works:-
- Setting up of piling rigs, other machineries &
equipment.
- correct lifting of pile at the designed lifting points.
- pile position, cut-off level & as-built position.
pile jointing.
- pitching & driving of pile, it’s verticality/rake.
- driven length & set.
- cutting of pile heads, reinforcement anchorage
length/plug length.
- load tests on preliminary piles/working piles.
- pile integrity tests.
- usage of permanent casing, temporary casing,
bentonite.
- piling records.
Supervision of Bridge Construction 70
24
Control of rake pile inclination
25
Support packing of uniform thicknesses must be
provided between piles at the lifting points when
staking.
When lifting the pile, only the designed lifting &
support points must be used.
During driving & until the pile has set or been driven
to the required length, all exposed piles must be
supported & restrained to maintain position &
alignment & to prevent buckling & damage to the
piles.
26
When pile has been driven to the required set or
depth, the head of the pile must be cut off to the
level shown on the drawings.
Cutting must be done carefully to avoid shattering or
damaging the rest of the pile.
Any cracked or defective concrete must be cut away
& made good with new concrete properly bonded to
the old.
The length of reinforcing bars projecting above cut
off level must be as shown on the drawings.
After construction, actual pile locations must be
certified by a Licensed Surveyor employed by the
Contractor.
Supervision of Bridge Construction 79
Bored Piles
Permanent casings which form part of the designed
pile must be as specified on the Drawings.
Support fluid material i.e bentonite/polymer must
comply with the manufacturer’s certificate & mix
proportion.
A certificate must be obtained from the
manufacturer of the bentonite powder, showing the
properties of each consignment delivered to the site.
Bentonite must be mixed thoroughly with water to
make a suspension which will maintain the stability
of the pile excavation for the period necessary to
place concrete & complete construction.
Supervision of Bridge Construction 80
27
In the event of a rapid loss of bentonite suspension,
polymeric fluids or water from the piling excavation,
the excavation must be backfilled with lean concrete
or well compacted sand without delay.
A pile constructed in stable soil, without the use of
temporary casings or other support must be bored &
concreted without delay to ensure that the soil
characteristics are not significantly altered.
Sandy clays or clayey silts may soften significantly in
less than 12 hours.
The time interval between completion of boring &
placing of concrete is preferably within 6 hours.
28
When concrete is placing under water, 20% more
cement content mix should be used.
Concrete to be placed under water or support fluid
must be placed by tremie & should not be discharged
freely into the water or support fluid.
The tremie pipe must at all times penetrate the
concrete which has previously been placed & should
not withdraw from the concrete until the completion
of concreting.
Piling Works
Typical Conditions of Use Slump Range
(mm)
Placed into water-free unlined bore. Widely spaced
reinforcement leaving room for free movement 75 to 125
between bars.
29
88 Supervision of Bridge Construction
30
Supervision of Bridge Construction 91
Bridge Construction
Pile Head Cut Off
Formworks
Formworks must be provided similar to other buried
structural components as in the Specification.
Formwork must be rigid & tight to prevent leaking of
mortar from the concrete which may cause
honeycombing.
No concrete should be placed until the formwork has
been inspected & approved by the supervision team.
The main reinforcement is basically bi-directional.
Makes sure that the correct bar sizes & placements as
well as the lapping or staggered lapping to be
exercised on site.
Supervision of Bridge Construction 93
31
At the soffit, minimum concrete cover under
reinforcement bars are 75 mm & 50 mm to all sides
unless otherwise stated.
The concrete spacers must be of at least the same
strength as the concrete to be poured. Spacer blocks
must be as small as possible with 10mm nominal size
of aggregates.
Pile cap should be continuously cast.
To avoid segregation of the concrete & the
displacement of the reinforcement, the long troughs,
chutes, or pipes for conveying the concrete from the
hopper or bucket should be used for placing
concrete. 94
Supervision of Bridge Construction
Bridge Construction
Pile Caps
Concreting using sheet pile cutes Concreting from day time through
the night
32
Backfill
Pile cap must be backfill with suitable material &
properly compacted as per Specification by hand held
compactor.
Where pile cap is located below the river bed, well
compaction may slow down the degradation process
or scouring effect. Scouring of foundation may cause
lost of piles capacities.
Where below carriageway, well compaction may
prevent differential settlement between the top or
edge of pile cap & roadway.
Construction of
Abutments
33
Dimensional Control
If dimensional control is not emphasized, the
following may happen :
i. abutment wall will be affected in appearance.
ii. precast beams unable to fit the deviated span
between abutments or pier.
iii. adjustment of design or details i.e beams, width
of abutment, position of bearings, expansion
joints, etc.
iv. beam centerline & pile group capacity need to be
checked.
Bituminous Coating
The external wall surfaces of abutment in contact
with soil must be applied with waterproofing layer in
three (3) coats of bitumen solution as according to
the specification.
34
Supervision of Bridge Construction 103
Bridge Construction
BRIDGE SUPERSTRUCTURE DESIGN
Abutment
Corbel
Bituminous
coating
Abutment
Wall
35
Construction of Abutment
Ballast Wall
Plinth for
pad bearing
Abutment
Wall
Construction of Abutment
Shear Key
Construction of Abutment
Curtain wall
Shear keys
Pile Bent
36
Construction of Abutment
Cast-in-situ parapet
Wing
wall
Ballast wall
Construction of Piers
Dimensional control
Emphasized on the dimensional control is similar the
construction of abutment.
Special attention should be given to the construction
of pile bent pier type.
Any deviation of the pier either its location point or
its verticality may not matching the dimensions at
the soffit of cross head.
This will impair the aesthetic in view of piers
linearity in row or the symmetric of cross head.
37
Bridge Construction
Piers
Formworks
The forms are typically constructed to cast or build
segments of the pier vertically & moving the forms
upward as the pier construction takes place.
For long pier, metal forms are normally utilized
because wood forms have a tendency to bulge when
high lifts are poured.
Common type of forms used are Slip Form or Jump
Form depending on the shape of piers & the speed of
construction.
38
Bridge Construction
Piers
Bridge Construction
Piers
Pile-Bent System
Bridge Construction
Piers
39
BEARING
INSTALLATION
Bearing bedding
The beddings / plinths on top of abutment must be
constructed before placing the bearings for adjusting
the grade of beams & so the deck slab to be
constructed later.
The beddings must be made of epoxy mortar
material.
Ensure bedding level plane surface will touch the
entire plane surface of bearing.
No epoxy mortar bedding be loaded until its control
cube has attained the specified compressive strength.
40
The concrete surface on which the epoxy mortar
bedding are to be placed & the bearing surfaces on
the prestressed concrete beams must be kept free of
oil, grease, dirt, laitance & other foreign materials.
Immediately prior to placing the epoxy mortar the
concrete surface which is to receive the epoxy
mortar be primed with a 0.8mm thick cast of the
epoxy resin binder used in the mortar.
Bearings must be located so that their centre lines
are within ± 3mm of their correct position.
41
Elastomeric Bearing
Ensure elastomeric bearings have been tested in
accordance with the specifications.
No bearings is allowed to be installed until they have
been accepted in writing by the S.O.
Check for imprint of mark number, date of
manufacture & name of manufacturer on face of
bearings.
When installing bearing, ensure it’s entire bottom &
top faces touch the surface of plinth & soffit of beam
respectively.
This to avoid the occurrence of “walking bearing”.
Supervision of Bridge Construction 124
Bridge Construction
Bearings Installation
Elastomeric Bearing
42
Supervision of Bridge Construction 127
walking bearing
Dowel Bars
Dowel bars are provided to fix the superstructure
(pin-joint).
Normally dowel bars are installed at shear keys
constructed on top of abutment or pier surface.
Dowel bars must be of galvanized as shown on the
Drawings.
Dowel bars must be accurately installed in position &
direction.
43
Supervision of Bridge Construction 130
Construction of Abutment
44
PRESTRESSED CONCRETE
USED FOR BRIDGE
CONSTRUCTION
133
Bridge Construction
Methods of Prestressing
Pre-tensioning
A method of prestressing in which the tendons
are tensioned before the concrete is placed, &
the prestressing is transferred to the concrete
when concrete attains an acceptable specified
strength.
This technique is used principally for the
construction of relatively short span bridge decks
using standard JKR beams.
Bridge Construction
Methods of Prestressing
Post-tensioning
A method of prestressing in which the tendon is
tensioned after the concrete has reached an
acceptable specified strength. The tendons are
anchored against the hardened concrete
immediately after prestressing.
45
Difference between Pre-tensioned and Post-
tensioned concrete
Pre-tensioned Post-tensioned
Prestressing force applied before Prestressing force applied after
concrete cured concrete cured
Usually strands arranged in Usually strands arranged strands
straight profile in parabolic profile
For shorter span construction 10m
to 24m For wider range of construction
from span 10m to 300 m
Pre-tensioning Method
Pre-tensioning
Prestressing Bed
46
Pre-tensioning Process
Monostrand jack
Prestressing Strand
Post-tensioning Method
47
Bridge Construction
Post-tensioned Prestressing Equipments
METHOD EQUIPMENT
Prestressing Materials
Tendon Ducts
Ducts/sheaths are made of
galvanised corrugated steel, in
helical form.
Used to protect tendons in concrete.
Number of joints must be kept to a
practicable minimum & each joint
adequately sealed against the
ingress of any material.
Corrugated Galvanised Steel
Joints in adjacent sheaths must be Sheaths
staggered by at least 300mm.
Sheaths must be kept free from any
materials which is detrimental to
bond between sheath & concrete.
Supervision of Bridge Construction 144
48
Prestressing Materials
Tendon Ducts
The ends of ducts/sheaths must be always sealed
until the insertion works of tendon commence.
Cement grout will be pumped into the ducts to
protect prestressing strands from corrosion.
Prestressing Materials
Tendon Ducts
49
50
Prestressing Materials
Prestressing Strand
51
Prestressing Materials
Post-tensioned anchorage system
Sheath/Duct
Anchor block
Prestressing
Strand
52
Prestressing Materials
Post-tensioned anchorage system
53
Concrete Strength
Prestressing Materials
Prestressing Strand Handling
54
Prestressing Equipment
Prestressing Strand Handling
Stressing Jack
- Commonly hydraulically operated
- Pulling strand up to specific length (stroke)
Stressing Sequence
55
Stressing Sequence
56
Stressing Sequence
Stressing Force
Stressing Force
Where Pavg=Average Pressing force
Ls =Effective free strand length
Es = strand Young Modulus
Basic formula, Extension cal = Pavg .Ls
As.Es
Jacking Force at stressing end = Pj
Jacking Force at Dead End /non-stressing end = KPj
Where K =Losses of prestressing due to :
i. Elastic deformation of concrete
ii. Anchorage draw-in
iii. Friction losses
Pavg = (Pj +KPj)/2
57
Stressing Force
Tendons extension by site measurement
Slack due to draw-in at anchorage & stressing device could be unknown
during stressing
However the actual total extension measured at site, Mea could be
calculated by simple linear interpolation method
Jacking
Force ( kN)
i = Pi . (F/(PF - Pi)
PF Mea = F + i
Mea = F + Pi . (F/(PF - Pi)
= F [1+ (Pi/(PF - Pi)]
= F [(PF - Pi+ Pi)/(PF - Pi)]
Mea = F [(PF)/(PF - Pi)]
Pi Where
Pi = initial jacking force
PF = final jacking force
i = extension due to initial jacking force
i F (mm)
F = extension due to initial jacking force
Mea Supervision of Bridge Construction
172 Slack Mea = actual total extension measured at site
Stressing Force
Sample of Stressing
Record
174
58
Stressing Force
Possible Causes
Difference of prestressing strand sectional area or
E value which have been used for computation
extension.
High deviation in cable profile from specified in
drawing (due to wrong installation, displaced prior
or during concreting).
Blockage of duct during concreting.
Pressure gauge not in good working condition/not
calibrated.
Perform
Perform Perform tendon
Perform grout Check grout ducting
coupling profile
vent fixing vent position cleaning
ducting work inspection
work
Perform Perform
Strand Strand
Cutting Threading
59
Post-tensioning Works Flow
Procure Procure
ORGANIZE Set up Install
Stressing Jack Pressure Gauge Perform Jack
STRESSING Stressing Stressing
Calibration Calibration Positioning
EQUIPMENT Equipment Gauge
Certificate Certificate
Install Perform
Prepare
Stressing Prepare Jack Hydraulic
Stressing
Hydraulic Hoisting Facility System Trial
Platform
System Run
ORGANIZE Procure
Procure Procure Cable
STRESSING Tendon
Stressing Force Extension
PREPARATION Stressing
Calculation Calculation
WORK Sequence
CARRY OUT
Prepare Perform Perform Perform
ANCHORAGE Prepare
Anchorage Anchorages Anchor Head Wedges
COMPONENTS Anchor Heads
Recesses Cleaning Installation Fixing
INSTALLATION
Check Bearing
Surface
Condition
Arrange
CARRY OUT Verify Concrete Check Strand Barricade Arrange
Prestressing
STRESSING Transfer Stressing Working Prestressing
Jack
WORK Strength Length Area Tools
Accessories
60
Strand preparation / cutting
181 Supervision of Bridge Construction
182 Completed
Supervision of Bridge Construction reinforcement cage
61
184 Supervision of Bridge Construction
62
Stressing Works
189
Measurement of extension after final Pressure indicated on the reading
stressing, F unit
63
Launching Girder
Camber
Stressing Works
Safety
The prestressing operation can be a potentially
dangerous one due to the tremendous forces
involved.
If a failure occurs, there is a good possibility that
high velocity projectiles will be produced.
The field engineer should always stay alert & be
aware of the prestressing operation as follows:-
Stay clear of the area when the contractor is
unpacking the strands. Securing bands may spring in
any direction when released, causing injury.
Before the contractor begins the stressing operation,
check all of the high-pressure hoses for leaks and/or
poor condition. Worn or damaged hoses are to be
replaced only with hoses that can withstand the high
pressures involved.
Supervision of Bridge Construction 191
Stressing Works
Safety
64
Grouting
Grouting
65
{
VSL PLASTICIZER - MY
66
Grouting Process
Grouting tube
Grouting vent
Bridge Construction
Beams
Bridge Construction
Prestressed beams
Bulb T-beams are normally designed as a post-
tensioned member with 2 stage post-tensioning.
The first stage post-tensioning is carried out to
resist bending due to self weight of beam & dead
weight of deck slab.
The stresses due to these forces & bending is
within the allowable limits specified in the code.
The second stage prestressing is carried out to
provide full prestressing. From the above
sequence of stressing, the losses due to
prestressing will be reduced.
Supervision of Bridge Construction 201
67
Bridge Construction
Prestressed beams
Bridge Construction
Prestressed beams
Bridge Construction
Prestressed beams
68
Bridge Construction
Prestressed beams
Launching of Precast
Elements
Bridge Construction
Launching of Precast Elements
69
Bridge Construction
Launching of Precast Elements
Bridge Construction
Launching of Precast Elements
Bridge Construction
Launching of Precast Elements
-Ensure crane or beam launcher has the capacity,
stability & safety („fail-save‟ method) to avoid
fatality.
-Beam must be handled slowly & carefully without
sudden shock or impact avoiding any effect on the
integrity of prestressed tendons.
-Ensure the beam is lifted at the designated points
as indicated on the drawing.
70
Bridge Construction
Launching of Precast Elements
Bridge Construction
Launching of Precast Elements
Bridge Construction
Launching of Precast Elements
71
Bridge Construction
Launching of Precast Elements
Bridge Construction
Launching of Precast Elements
Bridge Construction
BRIDGE SUPERSTRUCTURE DESIGN
Placing of Beams
Bracing of beam
using steel bars
72
Bridge Construction
BRIDGE SUPERSTRUCTURE DESIGN
Placing of Beams
Bridge Construction
BRIDGE SUPERSTRUCTURE DESIGN
Beams diaphragms
Intermediate
Diaphragm
73
Bridge Construction
Deck Slab
Bridge Construction
Deck Slab
The fundamentals of deck slab construction are as
follows:-
i. Accuracy in the setting forms.
ii. Properly proportioned mix and consistency in
concrete.
iii. Proper handling and placing of the concrete
mix.
iv. Uniform "strike-off" or screeding.
v. Straight edging by experienced pavement finishers.
Bridge Construction
Deck Slab
74
Bridge Construction
Deck Slab
If placement at the time is imperative, chilled
water may be used for mixing concrete, forms &
bars cooled before placement to avoid significant
increase in concrete temperature; & wind speed
lowered by shielding.
The appropriate deck construction sequence
should be observed:
i) place complete deck at one time whenever
feasible.
ii) If multiple placements must be made on
simple spans, place each span in one
placement.
Supervision of Bridge Construction 223
Bridge Construction
Deck Slab
iii) If the bridge is simple spans, but cannot be
placed in a single placement, then divide the
deck longitudinally & make 2 placements.
iv) If bridge is simple spans & single placements
cannot be made over the full span length, then
place the center of span segment first & this
placement as large as possible.
v) If multiple placements must be made & the
bridge is continuous spans, then place
concrete in the center of the sagging moment
regions first, & observe a 72 hour delay between
placements.
Supervision of Bridge Construction 224
Bridge Construction
Deck Slab
75
Bridge Construction
Deck Slab
Bridge Construction
Deck Slab
76
INSTALLATION OF
EXPANSION JOINTS
Bridge Construction
Expansion Joints
Bridge Construction
Expansion Joints
Expansion joints are provided at joints between
span members to accommodate various
movements at the joints & at the same time permit
traffic to be carried across the gap between the two
independent members or bridge segments.
Shop drawings indicating the details types,
materials, dimensions & installation etc. which are
not shown on the construction drawings must be
obtained from the contractor.
77
Bridge Construction
Expansion Joints
Bridge Construction
Expansion Joints
When one half of the joint is being set, the other
half must be completely free from longitudinal
strain. In particular where strong backs or
templates are used to locate the two sides of a
joint, they must not be fixed simultaneously to both
sides.
Screw thread must be kept clean & free from rust.
Ramps must be provided & maintained to protect
all expansion joints from vehicular loading.
Bridge Construction
Expansion Joints
A poured sealant, must be placed when the mean
bridge temperature is between 21°C 38°C.
Proprietary expansion joints must be installed by
specialist workmen who have been trained &
approved by the joint's manufacturer.
Surfacing must be carried across the joint & then
cut back to accommodate the nosing. The cutting
must be done with a diamond saw to give a clean
edge throughout the depth of the material provided
to be removed.
78
Bridge Construction
Expansion Joints
Masking materials provided to prevent surfacing
materials adhering to concrete surface at the joint
must be properly located to prevent displacement
by the paving machine.
Reinforced elastomeric
expansion joint
Buried Joint
79
Nosing Joint
Reinforced Elastomeric
CONSTRUCTION OF
INTEGRAL ELEMENT
80
Bridge Construction
Fully Integral Bridge
Rigid connection between superstructure &
substructure at abutment & piers are transferred by
way :-
i) the beams or girders are cast into a concrete end
diaphragm
ii) which is connected to a concrete pile
cap/abutment
iii) and generally supported by a single row of
piles.
The critical detail that makes a bridge an integral
bridge is the connection of the superstructure to the
abutment &Supervision
pier. of Bridge Construction 241
Bridge Construction
Fully Integral Bridge
Elimination of expansion
joints offer better riding Continuous pavement surface
confort between bridge deck and
242 Supervision of Bridge Construction approach embankment
81
Typical Girder-Abutment-Pile Joint For Fully Integral Bridge
Hinged
Approach Slab
Precast Girder
Abutment Wall
Bridge Construction
Fully Integral Bridge
Precast beam
End Diaphragm
Abutment wall
Bridge Construction
Fully Integral Bridge
82
Bridge Construction
Fully Integral Bridge
Full Continuity at
abutments and piers
Flexible piers
Bridge Construction
Continuous deck slab over pier
Fully Integral Bridge
Bottom reinforcement
is provided to resist
tensile stress due to
creep and shrinkage
effect
Bridge Construction
BRIDGE SUPERSTRUCTURE DESIGN
Monolithic Connection
Prestressed JKR
Standard T-beam
83
Bridge Construction
Semi Integral Bridge
Rubber Bearing
Abutment
Precast Beam
Pier Crosshead
84
Multi-Spans Semi-Integral Bridge, Jambatan
Pinang Tunggal, Seberang Perai Utara
Bridge Construction
Construction Sequence of Integral Bridge
Bridge Construction
Construction Sequence of Integral Bridge
85
Bridge Construction
Construction Sequence of Integral Bridge
Bridge Construction
Construction Sequence of Integral Bridge
Bridge Construction
Construction Sequence of Integral Bridge
Deck
Precast beam
Abutment
86
BRIDGE SUPERSTRUCTURE DESIGN
Bridge Construction
Construction Sequence of a Single Span Integral Bridge
Piling & Construction of Abutments
87
Bridge Construction
Construction Sequence of Integral Bridge
Concreting of remaining ends Deck
Slab + top Abutment Walls + End
Diaphragms, Granular Fill below
Approach Slab
Bridge Construction
Integral Abutment Details
CONCRETE PARAPET
88
Bridge Construction
Parapet
Bridge Construction
Parapet
89
268 Supervision of Bridge Construction
PROTECTIVE COATING
90
Protective coating
Bridge Construction
Protective Coating
91
Bridge Construction
Protective Coating
Bridge Construction
Protective Coating
Bridge Construction
Protective Coating
92
Bridge Construction
Protective Coating
On very porous surfaces application must be
repeated until surface is completely saturated.
All treated surfaces must be allowed to dry for at
least 2 hours.
When the surface is visibly dry, the Topcoat then
applied.
A two coat, pinhole free application of the Topcoat
is applied. Four hours drying between coats must
be allowed.
Bridge Construction
As-Built Drawings
KURSUS PRA-PTK
SESSI 2-20007
Sekian
Terima kasih di atas perhatian
anda..!
93